Guest:John Kursitis,Jerry Oliver,Mark Gruber,Steve Pierce
Applegate motioned to approve the minutes,second by Royer.
Carried 5 to 0.
Mark Gruber discussed purchasing the property next to the post
office to put in a woodshop.It is Zones C-2 and needs to be
changed to include woodshop.
Applegate motioned to recommend to the Council that they amend
ordinance C-l to include woodshop,and that Mark needs to get
signatures from surrounding owners within 200 feet of building.
Seconded by Christianson.Motion carried 5 to 0.
Mark Gruber presented the Lutheran building project.Applegate
motioned ,Korpanty seconded that the plans must meet the site
plan ordinance with no fee cost.Motion carried 5 to 0.Steve
Pierce has the plans and is reviewing them to make sure they are
meeting the Site Plan Ordinance.
Jerry Oliver of Civil Engineering representing Iowa Realty
discussed the land west of Southfork.He was there to discuss
the Dry Sewer Ordinance #2138.He would like the Commission to
waive the Ordinance so they could install septics like they have
at Southfork.The Commission discussed problems that would be
placed on the City in 20 years if they allowed this type of
septic if the DNR would shut them down.The Commission
recommends that we stick with the Ordinance of Dry Sewers.
Motioned by Royer,second by Applegate the we recommend to the
Council that they waive the Dry Sewer Ordinance.Motion defeatedo-6.(Steele arrived at 8:22)
Don Lee Bailey,Jr and Mayor Rosenkranz arrived at 8:30 P.M.
John Kursitis gave the P&Z an update of the Comprehensive Plan
and how it is progressing.He wanted the Commission to look over
a survey to be sent to the business owners.Applegate motioned,
Korpanty seconded to give their approval of the survey.Motion
carried 6 to 0.
1
June 3,1991 Minutes Continued
Motion by Applegate,second by Royer to except Phase I of the
Comprehensive Plan.Motion carried 6 to 0.
Royer motioned,Christianson seconded to adjourn the meeting at
9,25 P.M.
Respectfully submitted
Dianna Van Zee
June 25,1991
The Planning and Zoning Commission met June 25,1991 and was
called to order at 7:35 P.M.by Chairman Mark Casey.Dianna Van
Zee was present and taking minutes.
The following members were present:Applegate,Christianson,
Foster,Casey,Steele,Royer (arrived at 7:40 P.M.)
Absent:Korpanty
Guests:Jerry Oliver,Rick Ross,Bob Christianson,Mark Gruber,
Brian Redshaw,Bob Barrett--City Counci.l Representative,Steve
Pierce-City Engineer.
Jerry Oliver discussed Windfield.Windfield is zoned R-2,it
consists of 65 Acres,that 3.3 acres has been set aside for Park
land dedication,the lot were approximately 65ft wide.That
sanitary sewer has not been run to all of the land yet.Phase I
is adjacent to Mary Ann Estates and will be developed first.On
Windfield Parkway they would like no parking so it could be 25ft
wide and the rest of the development would have parking on one
side only.They do not want to fence along the railroad.If a
12in water main is ran along Warrior Lane they do not feel that
they should have to pay for the full cost of the main.They
would like a Boulevard entrance with an agreement to be worked