HomeMy WebLinkAbout2020-01-20-I01M Westown Meadows Park_Change Order 3AGENDA ITEM:
CITY OF WAUKEE, IOWA
CITY COUNCIL MEETING COMMUNICATION
MEETING DATE: January 20, 2020
AGENDA ITEM:Consideration of approval of Change Order No. 3 to Ball Team, LLC, for the
Westown Meadows Park Project increasing the contract in the amount of
$1,061.00.
FORMAT:Consent Agenda
SYNOPSIS INCLUDING PRO & CON: Change Order No. 3 to Ball Team, LLC, in the amount of
$1,061.00 includes a credit towards overages paid by the City for geotechnical
expenses, exchange/upgrade of door hardware for the restroom and storage
room, and additional earthwork and seeding of areas outside the perimeter of
the site. This change order also extends the contract deadline to June 1, 2020
to accommodate for site seeding and germination. The contractor plans to
seed as early as weather allows and anticipates having full establishment to
fulfill stormwater requirements by June 1, 2020. Representatives from Shive-
Hattery and City Staff have reviewed the quantities and find them to be
accurate.
FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS:
COMMISSION/BOARD/COMMITTEE COMMENT:
STAFF REVIEW AND COMMENT: Approve Payment
RECOMMENDATION: Approve the resolution.
ATTACHMENTS: I. Change Order No. 3
PREPARED BY: Matt Jermier
REVIEWED BY:
PUBLIC NOTICE INFORMATION –
NAME OF PUBLICATION:
DATE OF PUBLICATION:
I1M
Project # 418110-0
Shive-Hattery, Inc. | 4125 Westown Pkwy | Suite 100 | West Des Moines, IA 50266 | 515.223.8104 | shive-hattery.com
January 14, 2019
TO: Matt Jermier, Parks and Recreation Director
City of Waukee
805 University Ave
Waukee, IA 50263
RE: Change Order #3
City of Waukee – Westown Meadows Park
SH Project # 418110-0
Dear Mr. Jermier,
Attached please find a Change Order for the Westown Meadows Park project. The Change
Order includes the following items:
• A credit towards overages paid by the City for geotechnical expenses.
• Exchange/upgrade of door hardware for the restroom and storage room.
• Additional earthwork and seeding of areas outside the perimeter of the site.
• Modification of the completion date to June 1, 2020 to accommodate site seeding.
We have reviewed each of the Change Order Requests which are attached to this letter and
recommend approval. If City staff concurs with this change order, we recommend the City of Waukee
increase the contract price in the amount of $1,061.00 resulting in a total contract amount of
$658,873.00
Sincerely,
SHIVE-HATTERY, INC.
Emily C. Naylor
Project Manager
Enc. Change Order #3
COR #011 & #012
Memo regarding Completion Date Modification & Shared Materials Testing
WESTOWN MEADOWS PARK
Parks & Recreation
805 University Avenue Distribution:
Waukee, IA 50263 Owner __X__
Phone: (515) 978-0007 Engineer__X__
Contractor__X__
Other _____
Contractor:Ball Team, LLC
10550 New York, Suite 100
Urbandale, Iowa 50322
April 3, 2019
1 LS ($3,020.00)1.000 ($3,020.00)
2 COR-011 LS $431.00 1.000 $431.00
3 COR-012 LS $3,650.00 1.000 $3,650.00
$1,061.00
$651,853.00
$5,959.00
$657,812.00
$1,061.00
$658,873.00
244 Days
Owner:City of Waukee
□ ≤$500 Department Director X_______________________________________Date__________________Date___________________
□ $501 to $2,500 City Administrator X_______________________________________Date__________________Date___________________
□ >$2,501 City Council approved or ratified at Council meeting on Date___________________
The new Contract Sum including this Change Order will be
Date
THE CONTRACT IS CHANGED AS FOLLOWS:
Item No.Value AdjustmentQuantity AdjustmentUnit PriceUnit
Additional site grading and seeding at perimeter, outside construction limits
Item Code
1/14/2019
Additional geotechnical expenses
Date:
Signature:
Recommended By:
Project Title
Shive-Hattery Project File Number
Change Order Number
The Contract Time will be changed by
CHANGE ORDER SUMMARY
TOTAL
The Original Contract Sum was
Net Change by previously authorized Change Orders
The Contract Sum prior to This Change Order was
The Contract Sum will be increased by this Change Order in the amount of
Waukee Project File Number
Description
Door Hardware
Date:
Signature:
Name: Emily Naylor
Title: Project Manager
NOT VALID UNTIL SIGNED BY THE CONTRACTOR, OWNER'S REPRESENTATIVE (if applicable) AND OWNER
Shive-Hattery, Inc.
Checked By:
City of Waukee
Signature:
Name:
Title:
Date:
Ball Team, LLC
Contractor:
Name:
Title:
3
CHANGE ORDER #3
Orig. Contract Amount & Date
City of Waukee - Westown Meadows Park
418110-0
$651,853.00
P:\Projects\DM\4181100\Construction\CASupport\CO\ChangeOrder#03\ChangeOrder#03.xlsx 1 of 1
Project 418110-0
January 14, 2020
Matt Burch
Ball Team
10550 New York Avenue, Suite 100
Urbandale, IA 50322
RE: Westown Meadows Park Completion Date Modification & Shared Materials Testing
Dear Matt:
This memo is intended to clarify and document the owner’s expectations which are to prepare the
seedbed and seed as soon as possible in the Spring of 2020. Establishment of seeded areas is
anticipated to occur on or before June 1, 2020 and should the weather prohibit the earthwork operations
necessary to properly prepare the seedbed, additional contract extension will be considered.
Regarding the additional costs incurred by the owner for material testing relating to concrete flatwork,
the owner appreciates Ball Team’s willingness to pay for 50% of the overage as of January 14, 2020 in
the amount of $3,020.00. Any additional testing required for possible paving replacement after January
14, 2020 shall be paid for entirely by Ball Team.
The proposed Change Order #3 will extend the contract completion date by extended 244 days and the
completion date will become June 1, 2020.
Sincerely,
SHIVE-HATTERY, INC.
Emily Naylor
Project Manager
/EN
Copy: Matt Jermier, City of Waukee
Garrett King, Ball Team
10550 New York Avenue, Suite 100
Urbandale, IA 50322
Office: 515.440.4544
Owner:City of Waukee Project:Waukee Westown Meadows Park
230 W. Hickman Rd. Project No: 19-032
Waukee, IA 50263 Reference No:CR #11
Date: October 7, 2019
Description:
Remove exisitng deadbolt and thumbturn and replace new ADA deadbolt and thumbturn on restroom door.
TOTAL:$431
Accepted by:
City of Waukee
Date:
cc: File (1)
Owner Change Request
Dated: Prepared by: CR-#11ADA TumbturnCOST CODE DESCRIPTIONQTY UTLABOR UNIT LABORMATL UNITMATERIAL (w/tax) EQUIP SUB TOTAL 01.001Project Superintendent1HR0.00$75$0$0$0$0$7501.012Project Engineer1HR0.00$65$0$0$0$0$6508.111Door Hardware1LS0.00$0$0$0$0$268$268Walsh $140 $0 $0 $268 $408General Liability Insurance0.75%$3Contractor Fee5.00%$20 TOTAL$431Signature: Date: Waukee Westown Meadows Park10.7.19Garrett King
Page 1 of 1
Printed Oct 7, 2019 3:19 PM
2 Field Labor
1 Deadlock 475 LA KEYWAY 26D (L-SHOP KEY STD)
CHANGE OUT DEADBOLTS
key to work order 39507
Qty Product Description
Ball Team, LLC
10550 New York Ave. Suite 100
Urbandale, IA 50322
Customer:Ship To:
WAUKEE WESTOWN MEADOWS PARK
2445 SE WILLOWBROOK DR
Waukee, IA 50263
Tel: (515) 440-4544 Fax: (515) 457-8265
Account Code :
:
1822
Terms
Salesperson :
Net30
Michelle Smith
:
:
Purchase Order #
Shipped Via
Order Name :WAUKEE WESTOWN NEW DEADBOLT FOR RESTROOM
Customer Job #:DSM Install
418403Quote #
Quote Date Oct 7, 2019:
:
Expiration Date Jan 5, 2020:
Quote
Tel: 515-262-9822 Fax: 515-262-8315
Des Moines, IA 50317
Walsh Door & Security
2600 Delaware Ave
The above prices are quoted subject to acceptance prior to expiration date listed above and credit approval by an officer
of our company. State and local taxes are not included unless specifically noted. Material will be billed proportionately as
shipped. Full amount of invoice due when rendered, retainage is not acceptable. On shipments made by common carrier
consigned to the customer, all claims for damages in transit must be filed by consignee. We do not include cost of
unloading, storage or protection of material at jobsite.
268.00Pre-Tax Total :
004 - IA-POLK - 6%16.08:
Quote Total 284.08:
10550 New York Avenue, Suite 100
Urbandale, IA 50322
Office: 515.440.4544
Owner:City of Waukee Project:Waukee Westown Meadows Park
230 W. Hickman Rd. Project No: 19-032
Waukee, IA 50263 Reference No:CR #12
Date: November 8, 2019
Description:
Additional Grading and seeding at perimeter of site. Feather site into neighboring properties - work outside of grading
limits shown on plans.
TOTAL:$3,650
Accepted by:
City of Waukee
Date:
cc: File (1)
Owner Change Request
Dated: Prepared by: CR-#12Additional grading outside grading limitsCOST CODE DESCRIPTIONQTY UTLABOR UNIT LABORMATL UNITMATERIAL (w/tax) EQUIP SUB TOTAL 01.001Project Superintendent3HR0.00$75$0$0$0$0$22501.012Project Engineer1HR0.00$65$0$0$0$0$652.231Grading1LS0.00$0$0$0$0$1,500$1,500Iowa Pipe and Grading02.173Seeding0.38Acre0.00$0$0$4,373$0$0$1,662Unit Price from Bid Form $140 $4,373 $0 $1,500 $3,452General Liability Insurance0.75%$26Contractor Fee5.00%$173 TOTAL$3,650Signature: Date: Waukee Westown Meadows Park11.8.19Garrett King