HomeMy WebLinkAbout2020-08-17-J01S Wastewater Treatment Facility Demolition_Pmt Est 9AGENDA ITEM:
CITY OF WAUKEE, IOWA
CITY COUNCIL MEETING COMMUNICATION
MEETING DATE: August 17, 2020
AGENDA ITEM:Consideration of approval of Partial Payment Estimate No. 9 to
Wenthold Excavating, LLC for the Wastewater Treatment Facility
Demolition Project in the amount by $41,919.98.
FORMAT:Action
SYNOPSIS INCLUDING PRO & CON: Wenthold Excavating, LLC requested Payment
Estimate No. 9 for the work completed on the Wastewater Treatment
Facility Demolition Project in the amount of $41,919.98. Veenstra &
Kimm, Inc. has reviewed the payment estimate and recommends
payment.
The partial payment is for the pay period July 7, 2020 to July 31, 2020.
Pay Estimate No. 9 is for excavation and structure demolition.
FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS: $41,919.98
COMMISSION/BOARD/COMMITTEE COMMENT:
STAFF REVIEW AND COMMENT:
RECOMMENDATION: Approve Partial Payment No. 9
ATTACHMENTS: I. Partial Payment No. 9
II. Letter of Recommendation
PREPARED BY:Beth Richardson
REVIEWED BY:Sara Kappos SKK
PUBLIC NOTICE INFORMATION –
NAME OF PUBLICATION:
DATE OF PUBLICATION:
J1S