HomeMy WebLinkAbout2020-08-17-J01X Lift Station No. 3 Rehab Phase 2_Pmt Est 6AGENDA ITEM:
CITY OF WAUKEE, IOWA
CITY COUNCIL MEETING COMMUNICATION
MEETING DATE: August 17, 2020
AGENDA ITEM:Consideration of approval of Partial Payment Estimate No. 6 (Final) to
Synergy Contracting, LLC for the Lift Station No. 3 Rehabilitation Phase
2 – Backup Pump Replacement Project in the amount of $8,775.00
FORMAT:Consent Agenda
SYNOPSIS INCLUDING PRO & CON: Synergy Contracting, LLC requested Payment
Estimate No. 6 (Final) for the work completed on the Lift station No. 3
Rehabilitation Phase 2 – Backup Pump Replacement Project in the
amount of $8,775.00. Veenstra & Kimm, Inc. has reviewed the payment
estimate and recommends payment.
The partial payment is for pay period July 1, 2020 to August 7, 2020.
This pay estimate is for work on the backup pump.
FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS: $8,775.00
COMMISSION/BOARD/COMMITTEE COMMENT:
STAFF REVIEW AND COMMENT:
RECOMMENDATION: Approve Partial Payment No. 6 (Final)
ATTACHMENTS: I. Partial Payment No. 6 (Final)
II. Letter of Recommendation
PREPARED BY:Beth Richardson
REVIEWED BY:Sara Kappos SKK
PUBLIC NOTICE INFORMATION –
NAME OF PUBLICATION:
DATE OF PUBLICATION:
J1X