HomeMy WebLinkAbout2020-11-02-J01N SE Kettlestone Blvd Extension East of GPP_Change Order 2AGENDA ITEM:
CITY OF WAUKEE, IOWA
CITY COUNCIL MEETING COMMUNICATION
MEETING DATE: November 2, 2020
AGENDA ITEM:Consideration of approval of Change Order No. 2 to Concrete
Technologies, Inc. for the SE Kettlestone Boulevard Extension, East of
Grand Prairie Parkway Project decreasing the contract in the amount of
$74,629.19
FORMAT:Action
SYNOPSIS INCLUDING PRO & CON: The change order is for various quantity adjustments
to account for actual quantities installed in the field and material and
labor increases for concrete work in 2020. Due to delays in acquiring
property rights off Deseret Trust, the contractor was unable to install all
PCC pavement prior to the end of 2019 as scheduled.
FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS:The net result of this
Change Order decreases the contract price by $74,629.19.
COMMISSION/BOARD/COMMITTEE COMMENT:
STAFF REVIEW AND COMMENT:
RECOMMENDATION: Approve Change Order No. 2
ATTACHMENTS: I. Change Order No. 2
II. Letter of Recommendation
PREPARED BY:Beth Richardson
REVIEWED BY:Sara Kappos SKK
PUBLIC NOTICE INFORMATION –
NAME OF PUBLICATION:
DATE OF PUBLICATION:
J1N
8191 Birchwood Court, Suite L Johnston, IA 50131 Phone: (515) 254-1393 Fax: (515) 254-1642
October 28, 2020
Rudy Koester, P.E.
Director of Public Works
805 University Avenue
Waukee, IA 50263
RE: Change Order #2
SE Kettlestone Boulevard Extension
East of Grand Prairie Parkway
Dear Mr. Koester:
Attached please find a detailed Change Order for City Council approval on November 2, 2020.
Change Description
Various quantity adjustments to account for actual quantities installed in the field
Item CO2.1 Material and Labor increases for concrete work in 2020
o Due to delays in acquiring property rights off Deseret Trust, the contractor was unable to
install all PCC pavement prior end of 2019 as scheduled.
We have reviewed the submitted quantities and quote from Concrete Technologies, Inc. and quantities
appear to be in order with what was installed in the field and the quote appears to be in order with current
industry pricing. If City Staff concurs with this pricing, we recommend the City of Waukee Decrease the
contract price in the amount of $74,629.19 to complete the additional work associated with Change Order
#02.
Please let me know if you have any questions or need additional information.
Sincerely,
Foth Infrastructure and Environment, LLC
Joshua C. DeBower, P.E.
Lead Civil Engineer
Encl: Change Order #2 dated 10/27/2020
CHANGE ORDER 02 - FINAL
Distribution:
Owner - Finance ____
Owner - Public Works ____
Engineer ____
Contractor ____
Contractor:Concrete Technologies, Inc.
1001 SE 37th Street
Grimes, Ia 50111 $1,413,944.10 June 18, 2019
2.5 SY $3.85 -2092 ($8,054.20)
2.6 SY $17.35 -79 ($1,370.65)
3.1 TON $21.00 -150 ($3,150.00)
4.2 LF $118.00 -13 ($1,534.00)
4.7 LF $16.75 -307 ($5,142.25)
4.8 EA $368.00 -2 ($736.00)
4.10 LF $10.50 -500 ($5,250.00)
5.8 EA $440.00 -4 ($1,760.00)
6.1 EA $6,365.00 -1 ($6,365.00)
7.1 SY $76.50 72.25 $5,527.13
7.2 SY $95.00 8.5 $807.50
7.4 SY $115.00 1 $115.00
7.5 SF $39.50 -14 ($553.00)
7.6 SY $74.00 -96 ($7,104.00)
7.7 SY $51.00 -69.5 ($3,544.50)
7.8 SY $25.00 157.2 $3,930.00
8.2 LS $21,000.00 -1 ($21,000.00)
8.3 STA $685.00 2.16 $1,479.60
8.6 SF $32.00 -46.75 ($1,496.00)
8.7 LF $15.75 -15 ($236.25)
8.8 EA $210.00 -1 ($210.00)
8.10 CDAY $158.00 -30 ($4,740.00)
9.2 ACRE $2,940.00 0.4 $1,176.00
9.3 ACRE $1,995.00 -0.2 ($399.00)
9.5 LF $2.60 -1608 ($4,180.80)
9.6 LF $0.55 -1745 ($959.75)
9.7 LF $1.85 -3386 ($6,264.10)
3010-C-1000 TRENCH FOUNDATION
4010-E-1015 SANITARY SEWER, TRENCHED, PVC, 15 IN.
4040-A-1006 SUBDRAIN, PVC, CASE A, 6 IN.
2
Foth Project File Number
Orig. Contract Amount & Date
Value Adjustment
18W030.01
Item Code
SUBGRADE PREPARATION, 12 IN.2010-G-1012
Item No.Quantity
AdjustmentUnit Price
THE CONTRACT IS CHANGED AS FOLLOWS: Closeout change order to true up contract quantities to actual quantities installed. Added item for material and labor increase for concrete
work in calendar year 2020 due to delays getting easements.
Unit
2010-I-1000
Description
Project Title
Waukee Project File Number
October 27, 2020
Change Order Number
SE Kettlestone Boulevard Extension
MODIFIED SUBBASE, 12 IN.
Department of Public Works
805 University Avenue
Waukee, IA 50263
(515) 987-7920 Fax (515) 987-3979
Date
4040-C-1000 SUBDRAIN CLEANOUT, TYPE A-1
SPECIAL FIELD TILE REPAIR AND FITTINGS, PVC, UNSPECIFIED DIA.
SPECIAL VALVE ADJUSTMENT, GAS, MINOR
6010-A-1048 MANHOLE, SANITARY, SW-301, 48 IN.
7010-A1090 PAVEMENT, PCC, CLASS C, 10 IN.
7010-F-1060 MEDIAN, DOWELLED PCC, 6 IN.
7030-E-1006 SIDEWALK, PCC, 6 IN.
7040-H-1000 PAVEMENT REMOVAL
SPECIAL TEMPORARY TRAFFIC SIGNAL
8020-B-1000 PAINTED PAVEMENT MARKINGS, DURABLE
SPECIAL TYPE A SIGNS
SPECIAL POSTS FOR TYPE A SIGNS, PERFORATED SQUARE STEEL TUBE
SPECIAL EXISTING SIGNS TO BE REINSTALLED
SPECIAL VARIABLE MESSAGE BOARD
9010-B-1100 HYDRAULIC SEEDING, FERT. & MULCH., TYPE 1(PERM. LAWN MIX)
9010-B-1200 HYDRAULIC SEEDING, FERT. & MULCH., TYPE 2(PERM. COO-SEASON MIX)
9040-D-1012 FILTER SOCK, 12 IN.
9040-D-2012 FILTER SOCK, 12 IN., MAINTENANCE & REMOVAL
9040-N-1000 SILT FENCE, INSTALLATION
7030-G-1000 DETECTABLE WARNING
7030-H-1060 DRIVEWAY, PCC, 8 IN.
7030-I-1006 SHARED USE PATH, PCC, 6 IN.
CO#02-2020-1027-SE Kettlestone Blv Extention.xls Change Order 2 Page 1 of 2
9.8 LF $0.55 -280 ($154.00)
9.9 LF $0.10 -3666 ($366.60)
9.11 ACRE $1,575.00 -2.9 ($4,567.50)
9.12 EA $158.00 5 $790.00
CO1.1 SY $9.90 -767 ($7,593.30)
CO1.3 CY $4.00 -80 ($320.00)
CO1.4 SY $8.50 -115 ($977.50)
CO1.5 CY $7.50 -80 ($600.00)
CO2.1 LS $10,173.98 1 $10,173.98
($74,629.19)
$1,413,944.10
$66,910.60
$1,480,854.70
($74,629.19)
$1,406,225.51
0 Days
Recommended By:
Concrete Technologies, Inc.
Signature:
Name: Trent Petersen
Title: Project Manager
Date:
Owner:City of Waukee
□ ≤$500 Department Director X_______________________________________Date___________________
□ $501 to $2,500 City Administrator X_______________________________________Date___________________
□ Date___________________
□ >$2,501 City Council approved or ratified at Council meeting on Date___________________
NOT VALID UNTIL SIGNED BY THE CONTRACTOR, OWNER'S REPRESENTATIVE (if applicable) AND OWNER
Foth Infrastructure & Environment, LLC
The Contract Sum prior to This Change Order was
Checked By: Prepared By:
The new Contract Sum including this Change Order will be
The Original Contract Sum was
Date:
Name: Tim Moerman
Date:
The Contract Time will be increased by
CHANGE ORDER SUMMARY
Title: City AdministratorTitle: Lead Civil Engineer
Signature:
The Contract Sum will be decreased by this Change Order in the amount of
Net Change by previously authorized Change Orders
City of Waukee
Signature:
Name: Joshua C. DeBower, P.E.
9040-T-1000 INLET PROTECTION DEVICE
CEMENT TREATED SUBBASE
9040-N-2000 SILT FENCE, REMOVAL OF SEDIMENT
9040-N-3000 SILT FENCE, REMOVAL OF DEVICE
9040-Q-2000 EROSION CONTROL MULCHING, HYDROMULCHING
MATERIAL INCREASE FOR C4WRC20 TO C4WRC SWITCH
COLD WEATHER PROTECTION (2-LAYER OF BURLAP)
MATERIAL INCREASE FOR HOT WATER
MATERIAL AND LABOR INCREASES FOR CONCRETE WORK IN 2020
CO#02-2020-1027-SE Kettlestone Blv Extention.xls Change Order 2 Page 2 of 2