CITY OF WAUKEE, IOWA
CITY COUNCIL MEETING COMMUNICATION
MEETING DATE: July 8, 2019
AGENDA ITEM: Consideration of approval of Change Order No. 2 to Ball Team, LLC, for the
Waukee City Hall Renovation Project, increasing the contract in the amount
of $14,619.00.
FORMAT: Consent Agenda
SYNOPSIS INCLUDING PRO & CON: The proposed Change Order No. 2 consists of three
increases to the contract. The proposed changes are as follows:
1. Additional concrete pavers to be installed at the entrance because of the
favorable bid for the overall project.
2. Wood Sheathing removal and replacement which was determined was
necessary once the existing siding on the building was removed.
3. Replacement of concrete bases for new light poles because the bolt pattern
for the existing bases does not match the new fixtures. Additionally the
existing bases are not in very good shape.
FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS:
COMMISSION/BOARD/COMMITTEE COMMENT:
STAFF REVIEW AND COMMENT: The proposed changes are accounted for within the project
contingency.
RECOMMENDATION: Approve the Change Order
ATTACHMENTS: I. Change Order No. 2
PREPARED BY: Brad Deets