CITY OF WAUKEE, IOWA
CITY COUNCIL MEETING COMMUNICATION
MEETING DATE: January 3, 2022
AGENDA ITEM:Consideration of approval of a resolution approving 28E Agreement between
Urbandale Sanitary Sewer District; City of Grimes, Iowa; and the City of
Waukee, Iowa [WRA Grimes Connector]
FORMAT:Resolution
SYNOPSIS INCLUDING PRO & CON: The purpose of this Agreement is to document the
agreements of the Parties regarding design, construction, and cost allocations for: (1) interconnections
between existing USSD Sewer and the new Grimes Sewer; and (2) interconnections between existing
Waukee Sewer and the new Grimes Sewer.
FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS: $319,676.00
COMMISSION/BOARD/COMMITTEE COMMENT:
STAFF REVIEW AND COMMENT:
RECOMMENDATION: Approve the resolution and agreement.
ATTACHMENTS: I. Resolution
II. 28E Agreement
III. WRA Grimes Connector Contract 1 Receipt of Bids Updated Cost
Estimate Letter
PREPARED BY: Beth Richardson
REVIEWED BY: Rudy Koester RK
J9
1
THE CITY OF WAUKEE, IOWA
RESOLUTION 2022-
APPROVING 28E AGREEMENT BETWEEN URBANDALE SANITARY SEWER
DISTRICT, CITY OF GRIMES, IOWA, AND CITY OF WAUKEE, IOWA
[WRA GRIMES CONNECTOR]
IN THE NAME AND BY THE AUTHORITY OF THE CITY OF WAUKEE, IOWA
WHEREAS, the City of Waukee, Iowa is a duly organized municipality within Dallas County;
AND,
WHEREAS, the Urbandale Sanitary Sewer District (“USSD”) currently possesses a sanitary
sewer which serves the residents of the USSD; AND,
WHEREAS, the City of Waukee currently possesses a sanitary sewer which serves the residents
of Waukee; AND,
WHEREAS, the City of Grimes has joined the regional sanitary sewer system, the Wastewater
Reclamation Authority (“WRA”), and is in the planning stages of building and constructing a
sanitary trunk sewer to provide service to the residents of Grimes; AND,
WHEREAS, Grimes is willing to design and size the Grimes Sewer to allow for the flow
to/from certain parts of both the USSD Sewer and the Waukee Sewer into the Grimes Sewer and
vice versa, through certain interconnections between the new Grimes Sewer and existing USSD
Sewer, as well as certain interconnections between the new Grimes Sewer and existing Waukee
Sewer; AND,
WHEREAS, the Parties desire to enter into this Agreement to set forth and to establish their
agreement with respect to the design and allocation of costs of the Grimes Sewer which are
designed to serve the Parties’ respective territories in the area shown on the Parties’ Joint Trunk
Sewer Map, attached hereto as Exhibit A and incorporated herein by this reference.
NOW THEREFORE BE IT RESOLVED by the City Council of the City of Waukee approve
a 28E Agreement between the Urbandale Sanitary Sewer District; City of Grimes, Iowa; and
City of Waukee, Iowa [WRA Grimes Connector] is hereby approved.
Passed by the City Council of the City of Waukee, Iowa, and approved the 3rd day of January,
2022.
____________________________
Courtney Clarke, Mayor
Attest:
___________________________________
Rebecca D. Schuett, City Clerk
2
RESULTS OF VOTE: AYE NAY ABSENT ABSTAIN
Anna Bergman Pierce
R. Charles Bottenberg
Chris Crone
Larry R. Lyon
Ben Sinclair
Prepared by and Return to: Paul A. Drey, Esq., 6701 Westown Parkway, Suite 100, West Des Moines, IA 50266; 515 -274-1450
28E AGREEMENT
BETWEEN
URBANDALE SANITARY SEWER DISTRICT,
CITY OF GRIMES, IOWA, AND CITY OF WAUKEE, IOWA,
REGARDING WRA GRIMES CONNECTOR
THIS 28E AGREEMENT (“Agreement”), made and entered into this ___ day of
December, 2021 (“Effective Date”), by and among the Urbandale Sanitary Sewer District, a
sanitary sewer district organized and existing under Chapter 358 of the Iowa Code (“USSD”), the
City of Grimes, Iowa, an Iowa municipal corporation (“Grimes”), and the City of Waukee, Iowa,
an Iowa municipal corporation (“Waukee”) (and USSD, Grimes and Waukee together hereinafter
referred to as the “Parties”).
WITNESSETH:
WHEREAS, the USSD currently possesses a sanitary sewer which serves the residents of
the USSD (“USSD Sewer”);
WHEREAS, Waukee currently possesses a sanitary sewer which serves the residents of
Waukee (“Waukee Sewer”);
WHEREAS, Grimes has joined the regional sanitary sewer system, the Wastewater
Reclamation Authority (“WRA”), and is in the planning stages of building and constructing a
sanitary trunk sewer (“Grimes Sewer”) to provide service to the residents of Grimes;
WHEREAS, Grimes is willing to design and size the Grimes Sewer to allow for the flow
to/from certain parts of both the USSD Sewer and the Waukee Sewer into the Grimes Sewer and
vice versa, through certain interconnections between the new Grimes Sewer and existing USSD
Sewer, as well as certain interconnections between the new Grimes Sewer and existing Waukee
Sewer; and
WHEREAS, the Parties desire to enter into this Agreement to set forth and to establish
their agreement with respect to the design and allocation of costs of the Grimes Sewer which are
designed to serve the Parties’ respective territories in the areas shown on the Parties’ Joint Trunk
Sewer Map, attached hereto as Exhibit A and incorporated herein by this reference.
NOW, THEREFORE, it is agreed by and among the parties as follows:
1. 28E Agreement. This Agreement is entered into in accordance with the provisions
of the Code of Iowa, Chapter 28E. The purpose of this Agreement is to document the agreements
of the Parties regarding design, construction, and cost allocations for: (1) interconnections between
existing USSD Sewer and the new Grimes Sewer; and (2) interconnections between existing
Waukee Sewer and the new Grimes Sewer. This Agreement shall not be construed to create any
separate legal or administrative entity. After execution by the Parties, this Agreement shall be
filed with the Iowa Secretary of State in accordance with the provisions of Iowa Code § 28E.8.
2. Definitions. The following terms shall have the meanings set forth herein for the
purposes of this Agreement:
(a) “Service Area” or “Service Areas” for each of the Parties are identified on Exhibit
A.
(b) “Project Costs” of a particular trunk line or segment shall mean and include the cost
of construction, contingency, engineering services (including design and construction), surveying
and testing, administrative expenses, legal expenses and easement and right-of-way acquisition.
The proposed Project Costs for each segment are set forth on Exhibit B attached hereto.
(c) “Proportional Basis” refers to an allocation of costs to the Parties in proportion to
their respective assigned design flow in the particular segment of which the costs are to be
allocated.
3. Completed Segments: Summary of Project Costs and Allocations.
(a) Allocations of Project Costs. The following information is also set forth in Exhibit
B for each sewer: (i) the initial cost allocation for each sewer to the Parties; and (ii) the final
proposed cost sharing percentage based upon the Proportional Basis calculation for the sewers to
each of the Parties. The allocation of cost to each Party shall be based on the final cost of project
allocated by the Parties’ percentage shares as set forth in Exhibit B.
(b) Connection, Capacity Interests and Reversionary Interests. The Parties agree that
each of them shall have the right to connect their sanitary sewer systems to the Grimes Sewer. The
Parties further acknowledge and agree that there will be no formal capacity allocations for the
Grimes Sewer as it is the intent of the Parties that the Grimes Sewer will become a WRA sewer
after its acceptance. Accordingly, in lieu of formal capacity allocations, the Parties mutually agree
to request that WRA assign the Parties’ respective capacity interests and reversionary interests
based on the proportional allocation of capacity as set forth in Exhibit B, and a true up of these
project costs will occur among the Parties once the final project costs and proportional capacity
allocations are known.
4. Process.
(a) Construction/Project Oversight. Grimes shall be the contracting party and shall
ensure the contract meets the Project specifications. Upon the receipt of the bids, Grimes shall
inform the USSD and Waukee of the bid amounts. In the event the bids come in more than twenty
percent (20%) higher than the Engineer’s estimate for the Project, then the Parties shall discuss the
bids and move forward, unless any of the Parties object to the Project Bid Costs. In this event,
new bids may be obtained. In all other events, Grimes may move forward and award the Contract.
In the event Contractor requests a change order, said change order will be presented to all the
Parties for review. Grimes has the prior consent of Waukee and USSD to approve all change
orders unless said change order impacts the payment of either Waukee or USSD on its portion of
the Project by more than five percent (5%). In that case, said affected Party must also consent to
said change order before Grimes may approve.
(b) Payment Process.
The procedure for payment of partial pay estimates is as follows:
(1) Partial payment estimates must be submitted by any Contractor to Veenstra
& Kimm, Inc. by noon on Monday, eight (8) days prior to the second (2nd) Tuesday of each
month.
(2) Veenstra & Kimm, Inc. will submit the partial payment estimates to Grimes
Waukee and the USSD by the close of business on the first (1st) Tuesday of each month.
(3) The USSD and Waukee will approve the partial payment estimate at their
next regularly scheduled meeting and authorize payment to Grimes for their share of the
partial pay estimate.
(4) Grimes will approve the partial pay estimate at its meeting on the second
(2nd) Tuesday of each month.
(5) Grimes will make the partial payment on the day following the approval of
the estimate in accordance with its normal payment procedure.
(6) USSD and Waukee will pay their respective shares of the partial pay
estimate to the Grimes within five (5) days following the meeting at which the partial pay
estimate is approved by their respective governing bodies.
(c) Waukee Payments. Waukee may elect to pay its portion of the estimate
construction costs upfront, rather than pay monthly payments pursuant to the procedure
identified in 4(b) above. If Waukee elects to pay its portion of the estimated construction
costs upfront, and its actual share of the final construction costs is determined to be less
than Waukee’s upfront payment, Grimes will refund the difference to Waukee.
(d) Final Cost Estimate / Cost Determination. At least fourteen (14) days prior to
Grimes accepting the construction project, Grimes will report the final cost and cost share
to the USSD and Waukee. The USSD and Waukee will have seven (7) days to object or
inquire for additional information. Payments from USSD and Waukee will be due for the
final estimate and retainage in the same manner and procedures as any other pay estimate
is outlined in 4(b) above.
5. Maintenance and Repairs.
(a) Maintenance and Repairs by WRA. The Parties acknowledge and agree that it is
intended that the Grimes Sewer will be operated by WRA, and all maintenance and repair and
other operations for the Grimes Sewer shall be performed by the WRA as it (WRA) has done in
the past in similar arrangements. All costs associated therewith are to be paid by WRA, and the
Parties hereto shall not be obligated by reason of this Agreement to perform maintenance or repairs
or to be responsible for any costs incurred directly or in association with any of the following: (a)
reconstruction of the trunk sewer line by removing and replacing any portion of the trunk sewer
lines from one manhole to the next manhole; (b) upsizing a trunk sewer line or otherwise increasing
the capacity of an existing sewer line; or (c) constructing a parallel or relief trunk sewer line, unless
otherwise agreed by the Parties in a separate written agreement between the Parties.
6. Term. The duration of this Agreement shall be for a period of twenty-five (25)
years from and after the Effective Date of this Agreement, provided, however, that with the consent
of the Parties the duration of this Agreement may be extended. This Agreement may be terminated
only by unanimous written consent of the Parties.
7. Notice. Any notice or demand desired or required to be given hereunder shall be
in writing and deemed given when personally delivered or when deposited in the United States
mail, postage prepaid, sent certified or registered, and addressed as follows:
(a) If to USSD, to:
President, Urbandale Sanitary Sewer District
c/o Paul A. Drey
6701 Westown Parkway, Suite 100
West Des Moines, Iowa 50266
Copy to:
Paul A. Drey, Attorney for USSD
Brick Gentry P.C.
6701 Westown Parkway, Suite 100
West Des Moines, Iowa 50266
(b) If to Grimes, to:
City Administrator
Grimes City Hall
101 NE Harvey Street
Grimes, Iowa 50111
Copy to:
Director of Public Works
City of Grimes
1700 SE Destination Drive
Grimes, IA 50111
(c) If to Waukee, to:
City Administrator
Waukee City Hall
230 Hickman Road
Waukee, Iowa 50263
Copy to:
Public Works Director
City of Waukee
805 University Ave.
Waukee, Iowa 50263
or to such other address or person as hereafter shall be designated in writing by the applicable
party.
8. Miscellaneous. This Agreement constitutes the entire agreement between the
Parties hereto pertaining to the subject matter hereof and supersedes all negotiations, preliminary
agreements and all prior and contemporaneous discussions, agreements, and understandings of the
Parties in connection with the subject matter hereof. No amendment, change or modification of
any of the terms, provisions or conditions of this Agreement shall be effective unless made in
writing and signed by all Parties. Waiver of any provision of this Agreement shall not be deemed
a waiver of future compliance therewith and such provision shall remain in full force and effect.
In the event any provision of this Agreement is held invalid, illegal, or unenforceable, in whole or
in part, the remaining provisions of this Agreement shall not be affected thereby and shall continue
to be valid and enforceable. This Agreement shall be governed by and construed in accordance
with the laws of the State of Iowa. This Agreement shall be binding upon and shall inure to the
benefit of the Parties hereto and their respective legal representatives, heirs, successors and
permitted assigns. Nothing in this Agreement, express or implied, is intended to confer upon any
party, other than the Parties hereto (and their respective heirs, legal representatives, successors and
permitted assigns), any rights, remedies, obligations, or liabilities under or by reason of this
Agreement. In addition to any other remedies available at law or in equity to the Parties hereto
with respect to a breach hereof, the Parties hereto each reserve the right to enforce this Agreement
by specific performance. The titles or captions of paragraphs in this Agreement are provided for
convenience of reference only and shall not be considered a part hereof for purposes of interpreting
or applying this Agreement and such title or captions do not define, limit, extend, explain, or
describe the scope or extent of this Agreement or any of its terms or conditions. Words and phrases
herein shall be construed as in the singular or plural number, and as masculine, feminine, or neuter
gender, according to the context.
[Remainder of page intentionally left blank. Signature pages follow.]
CITY OF GRIMES, IOWA
By: Scott Mikkelsen, Mayor
ATTEST:
By: Rochelle Williams, City Clerk
STATE OF IOWA )
) ss:
COUNTY OF POLK )
On this ____ day of December, 2021, before me, a Notary Public in and for the State of
Iowa, personally appeared Scott Mikkelsen and Rochelle Williams, to me personally known, and,
who being by me duly sworn, did say that they are the Mayor and City Clerk, respectively, of the
City of Grimes, Iowa; and that the instrument was signed on behalf of the City of Grimes, Iowa,
by authority of its City Council, as contained in Ordinance No. _______ passed (the Resolution
adopted) by the City Council, under Roll Call No. ____________ of the City Council on the ____
day of December, 2021, and that the Mayor and City Clerk acknowledged the execution of said
instrument to be their voluntary act and deed and the voluntarily act and deed of the City of Grimes,
Iowa, by it voluntarily executed.
Notary Public in and for the State of Iowa
My commission expires:
CITY OF WAUKEE, IOWA
By: Courtney Clarke, Mayor
ATTEST:
By: Becky Schuett, City Clerk
STATE OF IOWA )
) ss:
COUNTY OF DALLAS )
On this ____ day of December, 2021, before me, a Notary Public in and for the State of
Iowa, personally appeared Courtney Clarke and Becky Schuett, to me personally known, and, who
being by me duly sworn, did say that they are the Mayor and City Clerk, respectively, of the City
of Waukee, Iowa; and that the instrument was signed on behalf of the City of Waukee, Iowa, by
authority of its City Council, as contained in Ordinance No. _______ passed (the Resolution
adopted) by the City Council, under Roll Call No. ____________ of the City Council on the ____
day of December, 2021, and that the Mayor and City Clerk acknowledged the execution of said
instrument to be their voluntary act and deed and the voluntarily act and deed of the City of
Waukee, Iowa, by it voluntarily executed.
Notary Public in and for the State of Iowa
My commission expires:
EXHIBIT A
WRA Grimes Connector – Parties’ Joint Trunk Sewer Map
(including Service Areas of the Parties)
EXHIBIT B
Project Costs, Initial Cost Allocations, and
Proposed Cost Sharing Percentages
The cost estimate was prepared by Veenstra & Kimm, Inc. based on material quotations provided
by likely suppliers during the week of October 18, 2021.
Description Estimated Construction Engineering Total
Contract 1 – Reach 1 $1,335,740 $65,182 $1,400,922
Contract 1 – Reach 2 $8,062,855 $393,454 $8,456,309
Total $9,398,595 $458,636 $9,857,231
The costs for Reach 1 and Reach 2 constituting Contract 1 are to be allocated on a proportionate
basis using the capacity allocated to each entity. For Reach 1 the cost allocation would be as
follows:
Grimes 58.39%
USSD 22.15%
Waukee 19.46%
For Reach 2 the cost allocation would be as follows:
Grimes 72.50%
USSD 27.50%
The cost allocation excluding easement cost is as follows:
Description Total Cost Grimes USSD Waukee
% Cost % Cost % Cost
Contract 1 - Reach 1 $1,400,922 58.39% $817,999 22.15% $310,304 19.46% $272,619
Contract 1 - Reach 2 $8,456,309 72.50% $6,130,824 27.50% $2,325,485
Total $9,857,231 $6,948,823 $2,635,789 $272,619