HomeMy WebLinkAbout2022-01-17-I01F_05 SE Ashworth Rd, SE Parkview Crossing Dr to SE Glacier Trl_Change Order 2AGENDA ITEM: CITY OF WAUKEE, IOWA CITY COUNCIL MEETING COMMUNICATION MEETING DATE: January 17, 2022 AGENDA ITEM:Consideration of approval of Change Order No. 2 to Alliance Construction for the SE Ashworth Road Corridor Improvements – SE Parkview Crossing Drive to SE Glacier Trail Project increasing the contract amount by $8,970.02. FORMAT:Motion SYNOPSIS INCLUDING PRO & CON: Change Order No. 2 is for core drilling structures for subdrain added at the back of curb, watermain bored under Ashworth to maintain traffic, credit to contractor for pavement not replaced, deletion of certified plan inspection, sawcut for water main bore, added pavement markings to accommodate traffic over winter shutdown, pavement marking removal, and additional compensation for surveying Mid American and Century Link proposed facilities within project corridor. FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS: The net result of this Change Order increases the contract price in the amount of $8,970.02. COMMISSION/BOARD/COMMITTEE COMMENT: STAFF REVIEW AND COMMENT: RECOMMENDATION: Approve the change order. ATTACHMENTS: I. Change Order No. 2 II. Letter of Recommendation PREPARED BY:Beth Richardson REVIEWED BY:Sara Kappos SKK PUBLIC NOTICE INFORMATION – NAME OF PUBLICATION: DATE OF PUBLICATION: I1F5 8191 Birchwood Court, Suite L Johnston, IA 50131 Phone: (515) 254-1393 January 4, 2022 Sara Kappos, P.E. Assistant Public Works Director 805 University Avenue Waukee, IA 50263 RE: Change Order #2 SE Ashworth Road Corridor Improvements – SE Parkview Crossing Drive to SE Glacier Trail Dear Ms. Kappos: Attached please find a detailed Change Order for City Council approval on January 17, 2022. Change Description: • Item CO 4.20 Core Drill Structures for Subdrain o Subdrain added at BOC. Outlet structures needed to be core drilled to attach subdrain. • Item CO 5.16 Water Main, Trenchless, Restrained Joint, PVC C900, DR18, 6 In. o Added water main bore under Ashworth to maintain traffic. • Item CO 5.17 Water Main, Trenchless, Restrained Joint, PVC C900, DR18, 8 In. o Added water main bore under Ashworth to maintain traffic. • Item 7.15 Pavement Removal o Water main bored under Ashworth to maintain traffic. Credit to contractor for pavement not removed. • Item 7.16 Temporary Pavement, HMA or PCC, 8 In. o Water main bored under Ashworth to maintain traffic. Credit to contractor for pavement not replaced. • Item CO 7.17 Delete Certified Plant Inspection o CPI allowed not to be utilized on the project. • Item CO 7.18 Sawcut for Water Main Bore o Water main bored under Ashworth to maintain traffic . Added saw cutting for patches prior to change. • Item CO 8.25 Painted Pavement Markings, Waterborne o Added markings to accommodate traffic over winter shutdown. • Item CO 8.26 Painted Symbols and Legend, Waterborne o Added markings to accommodate traffic over winter shutdown. • Item CO 8.27 Pavement Marking Removal o Added markings to accommodate traffic over winter shutdown. • Item CO 11.9 Private Utility Survey o Additional Compensation for surveying Mid American and Century Link proposed facilities within project corridor. Sara Kappos, P.E. Error! Reference source not found. January 4, 2022 Page 2 C:\pw_workdir\pw_ie\fvd_amw2\d0546107\Ltr_2022-0104_Waukee-SE Ashworth Road Corridor Improvements-Recommend CO2.docx We have reviewed the submitted quotes from Alliance Construction and they appear to be in order with current industry pricing. If City Staff concurs with this pricing, we recommend the City of Waukee Increase the contract price in the amount of $8,970.02 to complete the additional work associated with Change Order #2. If you have any questions, please contact me. Sincerely, Foth Infrastructure & Environment, LLC Andy Floy, P.E. Lead Civil Engineer Encl: Change Order #2 dated 1/4/2022 CHANGE ORDER 02 Distribution: Owner - Finance ____ Owner - Public Works ____ Engineer ____ Contractor ____ Contractor:Alliance Construction Group 3000 SE Grimes Blvd, Suite 800 Grimes, Iowa 50111 $4,510,016.01 February 22, 2021 CO 4.20 EA $143.00 6.00 $858.00 CO 5.16 LS $1,854.08 1.00 $1,854.08 CO 5.17 LS $1,854.07 1.00 $1,854.07 7.15 SY $6.00 -62.85 ($377.10) 7.16 SY $53.00 -62.85 ($3,331.05) CO 7.17 LS -$6,615.67 1.00 ($6,615.67) CO 7.18 LS $984.00 1.00 $984.00 CO 8.25 STA $57.20 100.86 $5,769.19 CO 8.26 EA $93.50 1.00 $93.50 CO 8.27 STA $82.50 11.61 $957.83 CO 11.9 LS $6,923.17 1.00 $6,923.17 $8,970.02 $4,510,016.01 $6,120.10 $4,516,136.11 $8,970.02 $4,525,106.13 0 Days Recommended By: Alliance Construction Group Signature: Name: Ryan McKinney Title: Project Manager Date: Owner:City of Waukee □ ≤$500 Department Director X_______________________________________Date___________________ □ $501 to $2,500 City Administrator X_______________________________________Date___________________ □ Date___________________ □ >$2,501 City Council approved or ratified at Council meeting on Date___________________ DELETE CERTIFIED PLANT INSPECTION 7040-H-1000 PAVEMENT REMOVAL Special WATER MAIN, TRENCHLESS, RESTRAINED JOINT, PVC C900, DR18, 8 IN. Special TEMPORARY PAVEMENT, HMA OR PCC, 8 IN. SE Ashworth Road Corridor Improvements SE Parkview Crossing to SE Glacier 2 19W019.01 Waukee Project File Number Item No. January 4, 2022 Department of Public Works 805 University Avenue Waukee, IA 50263 (515) 987-7920 Fax (515) 987-3979 Project Title Unit Foth Project File Number Orig. Contract Amount & Date Date Change Order Number Value AdjustmentQuantity AdjustmentUnit Price THE CONTRACT IS CHANGED AS FOLLOWS: Additional compensation for survey to stake Mid American and Century Link proposed facilities within project cooridor. Certified plant inspection deleted from project. Water main bored under Ashworth instead of open cut so traffic could be maintained safely. This includes credit for the pavement not removed and patched. Waterborne pavement markings added to accomodate traffic over winter shutdown. Subdrain added in location not shown in plans. Item Code Description 11010-A-999 Special WATER MAIN, TRENCHLESS, RESTRAINED JOINT, PVC C900, DR18, 6 IN. Special Special SAWCUT FOR WATER MAIN BORE PAINTED SYMBOLS AND LEGEND, WATERBORNE Special CORE DRILL STRUCTURES FOR SUBDRAIN Date: The Contract Time will be increased by CHANGE ORDER SUMMARY NOT VALID UNTIL SIGNED BY THE CONTRACTOR, OWNER'S REPRESENTATIVE (if applicable) AND OWNER The Original Contract Sum was The new Contract Sum including this Change Order will be Signature: Name: Andy Floy, P.E. Date: Name: Tim Moerman Title: Lead Civil Engineer Signature: The Contract Sum will be increased by this Change Order in the amount of Net Change by previously authorized Change Orders Title: City Administrator Foth Infrastructure & Environment, LLC Prepared By:Checked By: City of Waukee 8020-K-1000 PAVEMENT MARKING REMOVAL The Contract Sum prior to This Change Order was 8020-G-1000 8020-B-1000 PAINTED PAVEMENT MARKINGS, WATERBORNE PRIVATE UTILITY SURVEY CO#02 - 2022-0104-SE Ashworth Road Corridor Improvents.xls Change Order 1 Page 1 of 1