HomeMy WebLinkAbout2022-01-17-I01F_07 Ute Ave-Ashworth Rd Intersection_Change Order 2AGENDA ITEM:
CITY OF WAUKEE, IOWA
CITY COUNCIL MEETING COMMUNICATION
MEETING DATE: January 17, 2022
AGENDA ITEM:Consideration of approval of Change Order No. 2 to Concrete
Technologies, Inc. for the Ute Avenue and Ashworth Road Intersection
Project increasing the contract amount by $28,658.76.
FORMAT:Consent Agenda
SYNOPSIS INCLUDING PRO & CON: Change Order No. 2 includes work associated with
revisions to underground utility design, traffic control related items, and construction survey for
MidAmerican Energy overhead power relocation.
FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS: The net result of this
Change Order increases the contract price in the amount of $28,658.76.
COMMISSION/BOARD/COMMITTEE COMMENT:
STAFF REVIEW AND COMMENT:
RECOMMENDATION: Approve the change order.
ATTACHMENTS: I. Change Order No. 2
II. Letter of Recommendation
PREPARED BY:Beth Richardson
REVIEWED BY:Sara Kappos SKK
PUBLIC NOTICE INFORMATION –
NAME OF PUBLICATION:
DATE OF PUBLICATION:
I1F7
2727 SW SNYDER BOULEVARD | P.O. BOX 1159 | ANKENY, IA 50023-0974
autofill
v:\projects\2020\120.0783.01\construction\co_2022-01-12_letterco02.docm
January 12, 2022
Mr. Rudy Koester, P.E.
City of Waukee
805 University Avenue
Waukee, IA 50263
RE: CHANGE ORDER NO. 02
UTE AVENUE AND ASHWORTH ROAD INTERSECTION PROJECT
Dear Rudy:
Enclosed is change order 02 for the Ute Avenue and Ashworth Road Intersection project. This
change order includes work associated with revisions to underground utility design, traffic
control related items, and construction survey for MidAmerican Energy overhead power
relocation.
We recommend approval of change order 02 in the amount of $28,658.76 to the prime
contractor, Concrete Technologies, Inc. of Grimes, Iowa. Substantial completion date remains
unchanged with this change order. Please place this change order on the next available city
council meeting agenda for approval.
Sincerely,
SNYDER & ASSOCIATES, INC.
Nathan Carhoff, P.E.
Project Manager
Enclosure
CHANGE ORDER REQUEST
21-050- - Ute Avenue & Ashworth Road Intersection
Page 1
DATE: 11/23/2021
CR#: 1
To: Sarah Kappos From: Trent Petersen
City of Waukee 1001 SE 37th Street
1205 6th Street Grimes, IA 50111
Waukee, IA 50263 ,
Phone: Phone: 515-252-1520
Fax: Fax: 515-252-1642
Email: skappos@waukee.org Email: tpetersen@cti-ia.com
CC:
Below is the detail for our proposal to complete the following changes in contract work:
Pending Change Order: Hydrant Blow off
Reference: Watermain Installation
Proposed Scope of Work: Installation and removal of Hydrant for Blow off for B/T Tests.
PCO Item Status Quantity UM Unit Price Amount
1 : Hydrant Blow off Pending 1.000 EA $7400.00000 $7400.00
2 : Prime Contractor Mark Up Pending 7400.000 EA $0.10000 $740.00
Submitted By:
Total Amount:
Approved By:
$8140.00
11/23/2021
Date Sarah Kappos Date
City of Waukee
1
Nate Carhoff
To:Trent Petersen
Subject:RE: Ute Avenue and Ashworth Road Intersection - Revision 04
From: Trent Petersen <TPetersen@cti-ia.com>
Sent: Monday, December 6, 2021 3:14 PM
To: Nate Carhoff <ncarhoff@snyder-associates.com>
Cc: Grant Arndorfer <grant@ppgconstruct.com>
Subject: FW: Ute Avenue and Ashworth Road Intersection - Revision 04
I was out on Friday let me know if you received the price for the 60” Man Hole. Please add .10% for the Prime
Contractor mark up.
Thx
From: Grant Arndorfer <grant@ppgconstruct.com>
Sent: Friday, December 3, 2021 9:18 AM
To: Trent Petersen <TPetersen@cti-ia.com>
Subject: Re: Ute Avenue and Ashworth Road Intersection - Revision 04
Trent. We are looking at $4,000 for the 60" Manhole
Grant Arndorfer
Project Manager
Precision Pipe & Grading
515-341-6881
grant@ppgconstruct.com
From: Grant Arndorfer <grant@ppgconstruct.com>
Sent: Tuesday, November 30, 2021 5:32 PM
To: Trent Petersen <TPetersen@cti-ia.com>
Subject: Re: Ute Avenue and Ashworth Road Intersection - Revision 04
Trent. Remind me what manhole they want to switch to a 60".
Grant Arndorfer
Project Manager
Precision Pipe & Grading
515-341-6881
grant@ppgconstruct.com
From: Trent Petersen <TPetersen@cti-ia.com>
Sent: Tuesday, November 30, 2021 11:46 AM
To: Grant Arndorfer <grant@ppgconstruct.com>; Jimmie Abbas <jim@ppgconstruct.com>
Subject: FW: Ute Avenue and Ashworth Road Intersection - Revision 04
I need a price for the 60” manhole Please.
2
Thank you
Trent Petersen
From: Trent Petersen
Sent: Tuesday, November 16, 2021 1:23 PM
To: Grant Arndorfer <grant@ppgconstruct.com>; 'Jimmie Abbas' <jim@ppgconstruct.com>
Subject: FW: Ute Avenue and Ashworth Road Intersection - Revision 04
From: Nate Carhoff <ncarhoff@snyder-associates.com>
Sent: Tuesday, November 16, 2021 1:20 PM
To: Trent Petersen <TPetersen@cti-ia.com>
Cc: Derek J. Alleman <dalleman@shive-hattery.com>; grant@ppgconstruct.com; Rudy Koester (rkoester@waukee.org)
<rkoester@waukee.org>; Sara Kappos (skappos@waukee.org) <skappos@waukee.org>; Tim Royer (troyer@waukee.org)
<troyer@waukee.org>; Dalton Stifel <dstifel@waukee.org>
Subject: Ute Avenue and Ashworth Road Intersection - Revision 04
Trent,
Per discussions at recent construction progress meetings, attached is a plan revision which includes the revised water
main alignment/profile at Sugar Creek, temporary installation of a hydrant on Xenia’s main and installation of a new
valve, west Hunter Hollow. Also attached is an updated CAD file of proposed features in DGN and DWG format. A
complete updated construction set can be downloaded via the link below:
https://snyder-associates.filegenius.com/downloadPublic/jy7x13qo1m22w9k
This revision includes two new items, please provide a cost for the following:
1. Temporary installation of the fire hydrant on the existing Xenia main.
2. 60-inch diameter manhole.
Please contact me with any questions.
Thank you,
Nathan Carhoff, P.E.
Civil Engineer
SNYDER & ASSOCIATES, INC.
P: 515.964.2020 x2567 | C: 515.864.1882
2727 SW SNYDER BLVD, P.O. BOX 1159, ANKENY, IA 50023
NOTICE: This E-mail (including all attachments) is covered by the Electronic Communications Privacy Act, 18 U.S.C. §§ 2510-2521, is confidential and may
contain legally privileged information. If you are not the intended recipient, you are hereby put on notice that any retention, dissemination, distribution, or copying of
this communication or any part thereof is strictly prohibited. Please call or reply to the sender immediately that you have received this message in error, then
permanently delete it.
Trent Petersen
Concrete Technologies, Inc.
1001 SE 37th St.
Grimes, IA 50111
December 3, 2021
Invoice No:4215880 - 2
Ute Ave at Ashworth Staking
Services provided through November 26, 2021:
Phase 70 Construction
Total Fee 26,900.00
Percent Complete 23.00 Total Earned 6,187.00
Previous Fee Billing 4,304.00
Current Fee Billing 1,883.00
Total Fee 1,883.00
$1,883.00Total this Phase
Phase 95 Add Services
Task 800 Staking for MidAmerican
Hours Rate Total
Grade 5 Technician 3.50 110.00 385.00
Survey crew member (with equipment)15.00 109.00 1,635.00
Totals 18.50 2,020.00
Total Labor 2,020.00
Reimbursable Expenses
Reimb Exp/Mileage Heavy Duty Veh 23.76
Total Reimbursables 23.76 23.76
$2,043.76Total this Task
Task 802 Staking for Mediacom
Hours Rate Total
Grade 5 Technician 5.50 110.00 605.00
Survey crew member (with equipment)6.00 109.00 654.00
Totals 11.50 1,259.00
Total Labor 1,259.00
$1,259.00Total this Task
Task 803 Additional Storm
TERMS: PAYMENT SHALL BE DUE UPON RECEIPT.
ACH PAYMENTS NOW ACCEPTED. PLEASE EMAIL AR@SHIVE-HATTERY.COM FOR DETAILS.
Project 24215880CTI - Ute Ave at Ashworth Staking Invoice
Hours Rate Total
Grade 5 Technician 1.00 110.00 110.00
Survey crew member (with equipment)8.00 109.00 872.00
Totals 9.00 982.00
Total Labor 982.00
$982.00Total this Task
$4,284.76Total this Phase
$6,167.76AMOUNT DUE THIS INVOICE
MBB
Page 2TERMS: PAYMENT SHALL BE DUE UPON RECEIPT.
ACH PAYMENTS NOW ACCEPTED. PLEASE EMAIL AR@SHIVE-HATTERY.COM FOR DETAILS.