HomeMy WebLinkAbout2022-02-22-I01F_02 Triumph Park_Pmt Est 16AGENDA ITEM:
CITY OF WAUKEE, IOWA
CITY COUNCIL MEETING COMMUNICATION
MEETING DATE: February 22, 2022
AGENDA ITEM:Consideration of approval of Payment Estimate No. 16 to Larson
Construction, Co., Inc., for the Triumph Park Project in the amount of
$141,159.92.
FORMAT:Consent Agenda
SYNOPSIS INCLUDING PRO & CON: Payment Estimate No. 16 to Larson Construction, Co.,
Inc., is for fire suppression and HVAC and electrical work in both the
maintenance building and the concession stands. Minimal outside work was
completed due to the cold temperatures. The quantities completed to date
have been reviewed and agreed upon by the contractor, City of Waukee Staff,
and Confluence. The Triumph Park Project to date is 84% complete.
FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS:
COMMISSION/BOARD/COMMITTEE COMMENT:
STAFF REVIEW AND COMMENT: Approve Payment
RECOMMENDATION: Approve the resolution.
ATTACHMENTS: I. Letter of Recommendation
II. Payment Estimate No. 16
PREPARED BY: Matt Jermier
REVIEWED BY:
PUBLIC NOTICE INFORMATION –
NAME OF PUBLICATION:
DATE OF PUBLICATION:
I1F2
thinkconfluence.com
February 1, 2022
Mr. Matt Jermier, Parks and Recreation Director
Parks and Recreation Department
City of Waukee
805 University Avenue
Waukee, IA 50263
RE: Contractor Application for Payment #16 - Triumph Park
Dear Mr. Jermier:
Attached please find contractor Application for Payment #16 in the amount of $141,159.92 for approval and
signature by Waukee City Council. This is a smaller payment application due to the colder temperatures and no
outdoor work being completed. A large portion of this work was fire suppression and HVAC work on the
concessions buildings.
Confluence recommends approval and payment as indicated.
If there are any questions, please let me know.
Sincerely,
Confluence
Matthew O. Carlile, ASLA, LEED AP
Principal
Confluence
525 17th Street
Des Moines, Iowa 50309
Cc: Project File