SYNOPSIS INCLUDING PRO & CON: The applicant is requesting approval of a preliminary
plat for a 592-acre subdivision for a data center project. The property is
located north of Hickman Road and east of S Avenue. The plat includes
one (1) lot for the initial phase of the data center project. Lot 1 is 228.82-
acres in area. Two (2) addition outlots are shown for future development.
Outlot Y is 94.88-acres in area and Outlot Z is 268.37-acres in area.
Access to Lot 1 will be provided by S Avenue, for which the developer
will undertake improvements to pave S Avenue.
FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS:
COMMISSION/BOARD/COMMITTEE COMMENT: The Planning and Zoning
Commission reviewed the request at their meeting on February 8,
2022, recommended approval subject to remaining staff comments:
Approval of a Preliminary Plat for Morgan Plat 2
Community Development Director, Andy Kass, introduced the request for approval of a
Preliminary Plat, Final Plat, and Site Plan for Project Morgan Plat 2 as submitted by the
applicant, Apple, Inc. The subject property is generally located north of Hickman Road, between
S Avenue and T Avenue, containing approximately 592 acres. The property was rezoned in 2017
in anticipation of a data center.
Mr. Kass advised that the site plan identifies the construction of a number of buildings. Building
WKE.01 is 315, 773 square feet in size for a data center building. WKE.01-Administration
Building, is approximately 63,349 square feet in area, a maintenance building is shown to be
10,511 square feet in area, and 4 network distribution buildings are shown to be 2,210 square feet
in area. A small guard building is shown at the entrance to the site. Any future data center
buildings will require separate site plan approvals.
Mr. Kass advised that the applicant will be required to pace S Avenue as part of public
improvements, and that the applicant has already constructed much of the storm water
infrastructure on the property. Sanitary sewer and water extensions will also be the responsibility
J6
of the applicant. At this time Parking, landscaping, open space, and elevation requirements have
all been met. Staff would recommend approval subject to any remaining staff comments.
Commissioner Broderick questioned if there was a reason for the “U” shaped pond. Ryan
Hardisty of Civil Design Advantage and representative of the Applicant advised that the
area is very flat, so the U Shape allowed an increase in depth to accommodate stormwater
runoff from both S Avenue and the subject property.
Commissioner Koshy questioned if S Avenue will be constructed in Phases. Mr. Hardisty
advised that it will be paved all at once.
Commissioner Koshy questioned if any other boundary protections aside from the guard
gate existed for the site. Mr. Hardisty advised that large berms were incorporated into the
landscaping around the property, and an 8-foot fence is intended to be installed at the
boundary of the site.
Commissioner Gerlitz questioned if there was a timeline for the other buildings. Mr. Kass
advised not at this time.
Commissioner Broderick moved to approve a Preliminary Plat for Project Morgan Plat subject to
any remaining staff comments. Commissioner Streit seconded the motion. Ayes: Hoifeldt, Streit,
Broderick, Koshy, Tessau, and Gerlitz. Nays: none. Motion Carried.
STAFF REVIEW AND COMMENT: Staff’s position is that the proposed preliminary plat
meets the intent and the requirements of the Zoning Ordinance and the
Waukee Subdivision Ordinance.
RECOMMENDATION: Staff recommends approval of the Preliminary Plat for Morgan Plat 2.
ATTACHMENTS: I. Resolution
II. Staff Report
III. Preliminary Plat
PREPARED BY: Andy Kass, Community Development Director
REVIEWED BY:
PUBLIC NOTICE INFORMATION –
NAME OF PUBLICATION:
DATE OF PUBLICATION:
THE CITY OF WAUKEE, IOWA
RESOLUTION 2022-
APPROVING THE MORGAN PLAT 2 PRELIMINARY PLAT
IN THE NAME AND BY THE AUTHORITY OF THE CITY OF WAUKEE, IOWA
WHEREAS, the City of Waukee, Dallas County, State of Iowa, is a duly organized Municipal
Organization; AND,
WHEREAS, the City of Waukee Planning and Zoning Commission reviewed and recommended
approval of a Preliminary Plat for Morgan Plat 2 on February 8, 2022; AND,
WHEREAS, the Preliminary Plat for Morgan Plat 2 is in general conformance with section §176
– Subdivision Regulations of the Waukee Municipal Code.
NOW THEREFORE BE IT RESOLVED by the City Council of the City of Waukee, Iowa on
this the 7th day of March, 2022 that the Preliminary Plat for Morgan Plat 2 Place be approved.
____________________________
Courtney Clarke, Mayor
Attest:
___________________________________
Rebecca D. Schuett, City Clerk
RESULTS OF VOTE: AYE NAY ABSENT ABSTAIN
Anna Bergman Pierce
R. Charles Bottenberg
Chris Crone
Larry R. Lyon
Ben Sinclair
PLANNING AND ZONING COMMISSION STAFF REPORT
PROJECT: Morgan Plat 2 / Project Morgan WKE Site –
Preliminary Plat, Final Plat, & Site Plan
PREPARED BY: Andy Kass AICP, Community
Development Director
REPORT DATE: February 4, 2022
MEETING DATE: February 8, 2022
GENERAL INFORMATION
Applicant: Apple, Inc.
Owner:
Apple, Inc.
Owner’s Representative:
Ryan Hardisty, P.E. with Civil Design Advantage
Request: The applicant is requesting approval of a preliminary
plat, final plat, and site plan for a data center project.
Location and Size: Property is generally located north of Hickman Road,
between S Avenue and T Avenue, and containing
approximately 592 acres more or less.
AREA MAP
ABOVE: Aerial of Property identifying the proposed plat (outlined in ORANGE).
February 4, 2022
2 of 3
LAND USES AND ZONING
Location Existing Land Use Comprehensive Plan Current Zoning
Property in
Question
Vacant –
Undeveloped
Neighborhood
Residential
M-1 (Light Industrial District) / PD-1
(Planned Development Overlay)
North Vacant –
Undeveloped
Neighborhood
Residential
N/A (Dallas County)
South Vacant –
Undeveloped
Neighborhood
Residential
M-1 (Light Industrial District) / PD-1
(Planned Development Overlay)
East Vacant –
Undeveloped
Neighborhood
Residential
M-1 (Light Industrial District) / PD-1
(Planned Development Overlay)
West Vacant –
Undeveloped
Neighborhood
Residential
M-1 (Light Industrial District) / PD-1
(Planned Development Overlay)
HISTORY
The subject property is located north of Hickman Road and between T Avenue and S Avenue. The property was
annexed into the City of Waukee and rezoned in 2017. Apple, Inc., purchased the property and much of the
surrounding property with the intent to develop a data center. The applicant has submitted a detailed site plan for the
first phase of the data center project.
PROJECT DESCRIPTION
The site plan identifies the construction of a number of buildings for the data center. Building WKE.01 is 315,773 square
feet in area and is a data center building. Building WKE.01 is 63,349 square feet in area and is an administration building.
A maintenance building (WKE.93) is show shown to be 10,511 square feet in area. Network distribution buildings
(WKE.51, WKE.52, WKE.53, & WKE.54) are shown to be 2,210 square feet in area. A small guard building is shown at
the entrance to the site. Future data center buildings are shown on the site plan as well. The future buildings will require
additional site plan approvals. All proposed buildings meet the requirements of the M-1/PD-1 zoning district.
Table 1: M-1/PD-1 Zoning District Bulk Regulations
Category M-1/PD-1 (minimum)
Lot Area No minimum
Lot Width No minimum
Front Yard Setback 50 feet
Rear Yard Setback 50 feet
Side Yard Setback 25 feet
Setback Between Buildings 25 feet
Building Height 80 feet (maximum)
The final plat identifies one (1) lot and one (1) outlot to be platted. Staff is working with the applicant to address some
remaining comments as it relates to the platting of the site which may increase the number of lots platted. If there are
changes in the number of lots platted, the change would be minimal. The M-1/PD-1 zoning district does not have any
minimum requirements as it relates to lo area or width.
February 4, 2022
3 of 3
STREET IMPROVEMENTS, ACCESS & PARKING
The applicant will be required to pave S Ave as part of the public improvements for the site. Staff has been reviewing the
plans for S Avenue concurrently with the site plan and plats. Access into the site is provided from S Avenue on the west
side of the site. A total of 60 parking spaces are required for the first phase. The site plan identifies that 114 parking
spaces are to be provided.
UTILITIES
The applicant made improvements to the site in 2017 and 2018 when they constructed much of the stormwater
infrastructure on the property. A number of ponds on the site will provided detention for this phase and subsequent
future phases. Similar to the S Avenue road improvements, the applicant will be required to extend sanitary sewer and
water main along their plat boundaries and into their site. Staff has been reviewing the plans for public utilities
concurrently with the site plan and plats. Utilities located within the site will be privately owned and maintained by the
applicant.
LANDSCAPING & OPEN SPACE
As part of the planned development that was approved for the development, a 50-foot landscape buffer and a five-foot
berm along the perimeter of the property are shown on the site plan. In addition, the site plan demonstrates compliance
with all other required open space plantings. The site plan identifies that nearly 72% of the site will be open space.
BUILDING ELEVATIONS
Elevations of the proposed buildings have been provided and included for your review. The proposed materials include
precast concrete panels, architectural metal panels, glazing, fiber cement board. The proposed materials to be utilized on
the buildings are consistent with those identified within the Site Plan Ordinance.
STAFF RECOMMENDATION
The preliminary plat, final plat, and site plan meet the requirements of the Zoning Ordinance and the Planned
Development Agreement. The preliminary plat and final plat are in general conformance with the Subdivision Ordinance
and the Waukee Standard Specifications for Public Improvements. Staff recommends approval of the preliminary plat and
final plat for Morgan Plat 2 and the site plan for Project Morgan WKE Site, subject to remaining staff comments.
UPFFOS/D
J
J
JLVF J
LVDLVDLVDOS/DLVDLVDLVDJ
F
J
J
J
J J
J J
JJ
JJ
J
J
JJ
JJ
3333
JJ
JJ
JJ
JJ
JJ
J J
J J
J
J
J
J
J1/ A-7101RISER0601
POE0503TRAP0901
NDS1000SECU
R
I
T
Y
0701POE0502
ELECENCL
O
S
U
R
E
A
0301ELECENCLO
S
U
R
E
B
0302ADM
I
N
/
M
D
F
0501
GENER
A
T
O
R
ENCLO
S
U
R
E
2/ A-7101
F FOS/D
J
J
J
LVF
J
LVD
LVD LVD
OS/D
LVDLVD
LVD J
F
J
J
J
JJ
JJ
JJ
JJ
J
J
JJ
JJ
3
3
33
JJ
JJ
JJ
JJ
JJ
JJ
JJ
J
J
J
J
J
1/ A-7101
RISER0601POE0503
TRAP0901 NDS1000
SECUR
IT
Y
0701
POE0502
ELECENCLOSU
RE
A0301ELECENCLOSU
RE
B0302 ADMIN
/MD
F
0501
GENERAT
O
R
ENCLOSU
R
E
2/ A-7101
FFOS/D
J
J
J
LVF
JLVDLVDLVD
OS/D
LVDLVD
LVDJ
F
J
J
J
J J
J J
JJ
JJ
J
J
JJ
JJ
3
3
3
3
JJ
JJ
JJ
JJ
JJ
J J
J J
J
J
J
J
J
1/ A-7101
RISER0601 POE0503
TRAP0901NDS1000SECU
RI
TY
0701
POE0502
ELEC
ENCLO
SUR
E
A
0301ELECENCLOSU
RE
B0302ADMIN/MDF0501
GENERAT
O
R
ENCLOSU
R
E
2/ A-7101
F FOS/D
J
J
J
LV F
J
LVD
LVD LVDOS/DLVD LVDLVD J
F
J
J
J
JJ
JJ
JJ
JJ
J
J
JJ
JJ
3
3
33
JJ
JJ
JJ
JJ
JJ
JJ
JJ
J
J
J
J
J
1/ A-7101 RISER0601
POE0503TRAP0901
NDS1000SECU
R
I
T
Y
0701 POE0502
ELEC
ENCLO
S
U
R
E
A
0301
ELEC
ENCL
O
S
U
R
E
B
0302 ADMIN/MDF0501
GENER
A
T
O
R
ENCLO
S
U
R
E
2/ A-7101EV CHARGINGONLYEV CHARGINGONLYEV CHARGINGONLYEV CHARGINGONLYEV CHARGINGONLYEV CHARGINGONLYEV CHARGINGONLYEV CHARGINGONLYEV CHARGINGONLYEV CHARGINGONLYNOPARKINGNOPARKINGN
O
PARKINGNOPARKINGNOPA
R
KI
N
G
LOT 2OUTLOT 'Z'S89°42'13"W 141.82'S00°27'11"W 1086.91'S00°27'11"W 350.00'S00°27'11"W 166.51'S89°55'20"W 5.00'S89°34'55"W 1319.80'S89°34'41"W 1497.46'N45°11'24"W 35.21'N00°02'31"E 2519.15'N00°21'50"E 1518.60'N89°34'38"E 781.15'N00°21'56"E 1064.81'N89°34'43"E 743.59'N89°34'37"E 1318.18'S00°07'28"W 1262.17'N89°35'32"E 131.58'S00°17'47"E 371.33'S00°17'47"E 50.00'S89°42'13"W 576.00'N89°42'13"E 576.00'S00°17'47"E 1841.00'N89°34'37"E 0.17'N89°36'38"E 1325.88'N89°36'36"E 1224.83'S45°01'50"E 35.13'S00°19'44"W 2556.81'S00°19'21"W 2534.94'S45°07'20"W 35.48'S89°55'20"W 2535.55'N89°55'20"E 310.00'N00°27'11"E 350.00'S89°55'20"W 310.00'ADMINDATA CENTERGUARDHOUSEMIDAMERICANENERGYSUBSTATIONNDSNDSMAINTENANCEBUILDINGNDSNDSOUTLOT 'Y'LOT 1S00°02'31"W 3545.42'N89°57'29"W 1165.75'N00°02'31"E 3545.42'S89°57'29"E 1165.75'S00°17'47"E 1841.00'WAUKEE, IOWAMorgan Plat 2Morgan Plat 2PRELIMINARY PLAT FOR:PRELIMINARYNOT FOR CONSTRUCTIONLEGAL DESCRIPTIONZONINGENGINEER / SURVEYOROWNER / APPLICANTBENCHMARKSLEGENDSHEET INDEXDATE OF SURVEYSITE ADDRESS’”’”WAUKEE, IOWA
REVISIONS
ENGINEER: TWCENGINEER: RAHCIVIL DESIGN ADVANTAGE FIRST SUBMITTAL 10/26/2021
DATE
MORGAN PLAT 22104.260PHONE: (515) 369-4400
3405 S.E. CROSSROADS DRIVE, SUITE G
GRIMES, IOWA 50111
SECOND SUBMITTAL 01/04/2022
THIRD SUBMITTAL 01/22/2022
FOURTH SUBMITTAL 02/08/2022
COVERC0.1HICKMAN ROAD / HWY 6(ROW WIDTH VARIES)(PUBLIC STREET)280TH PLACE(PUBLIC STREET)T AVENUE
(PUBLIC STREET)
S AVENUE(PUBLIC STREET)STORM WATER DETENTION POINDSLOT 1 OPEN SPACE REQUIREDNOTESDEVELOPMENT SUMMARYADJACENT PROPERTY OWNERS(NOT IN PLAT)VICINITY MAPWAUKEE, IOWAPROJECTLOCATIONHICKMAN RD / HWY 6T AVE 270TH PL280TH PLS AVE RACCOON RIVER VALLEY TRAILCITY OF WAUKEECORPORATE LIMITSLOT 3108496 SF2.49 AC(NOT IN PLAT)
UPFF OS/DJ
J
J LVFJ
LVDLV DLVDOS/DLVDLVDLVDJ F
J
J
J
J J
J J
JJ
JJ
J
J
JJ
JJ
3
3
33JJJJJJ
JJ JJ
J J
J J
J
JJ
JJ1/ A-7101RISER0601POE0503TRAP0901NDS1000SECURITY0701POE0502ELECENCLOSURE A0301ELECENCLOSURE B0302ADMIN/MDF0501GENERATORENCLOSURE2/ A-7101F FOS/D JJJLVFJLVDLVDLVDOS/DLVD LVDLVD JFJ JJJJJJJJJJJJ JJJJ3333JJJJJJJJJJJJJJJJJJJ1/ A-7101 RISER0601POE0503TRAP0901NDS1000SECURITY0701POE0502ELECENCLOSURE A0301 ELECENCLOSURE B0302 ADMIN/MDF0501GENERATORENCLOSURE 2/ A-7101FFOS/DJJJLVF JLVDLVDLVDOS/DLVDLVDLVDJ FJJJ JJJ JJJJJJJJJJJ3333JJJJJJJJJJJJJJJJJJJ1/ A-7101RISER0601POE0503 TRAP0901NDS1000SECURITY0701POE0502 ELECENCLOSURE A0301ELECENCLOSURE B0302ADMIN/MDF0501 GENERATORENCLOSURE2/ A-7101
F FOS/D
J
J
JLVF
J
LVD
LVD LVDOS/DLVD LVDLVDJ
F
J
J
J
JJ
JJ
JJ
JJ
J
J
JJ
JJ
3
3
3
3
JJ
JJ
JJ
JJ
JJ
JJ
JJ
J
J
J
J
J
1/ A-7101 RISER0601POE0503TRAP0901NDS1000SECURITY0701POE0502ELECENCLOSURE A0301ELECENCLOSURE B0302ADMIN/MDF0501GENERATORENCLOSURE2/ A-7101EV CHARGINGONLYEV CHARGINGONLYEV CHARGINGONLYEV CHARGINGONLYEV CHARGINGONLYEV CHARGINGONLYEV CHARGINGONLYEV CHARGINGONLYEV CHARGINGONLYEV CHARGINGONLYNOPARKINGNOPARKINGNOPARKINGNOPARKINGNOPARKINGLOT 3LOT 2OUTLOT 'Z'S89°42'13"W 141.82'S00°27'11"W 1086.91'S00°27'11"W 350.00'S00°27'11"W 166.51'S89°55'20"W 5.00'S89°34'55"W 1319.80'S89°34'41"W 1497.46'N45°11'24"W 35.21'N00°02'31"E 2519.15'N00°21'50"E 1518.60'N89°34'38"E 781.15'N00°21'56"E 1064.81'N89°34'43"E 743.59'N89°34'37"E 1318.18'S00°07'28"W 1262.17'N89°35'32"E 131.58'S00°17'47"E 371.33'S00°17'47"E 50.00'S89°42'13"W 576.00'N89°42'13"E 576.00'S00°17'47"E 1841.00'N89°34'37"E 0.17'N89°36'38"E 1325.88'N89°36'36"E 1224.83'S45°01'50"E 35.13'S00°19'44"W 2556.81'S00°19'21"W 2534.94'S45°07'20"W 35.48'S89°55'20"W 2535.55'N89°55'20"E 310.00'N00°27'11"E 350.00'S89°55'20"W 310.00'ADMINDATA CENTERGUARDHOUSEMIDAMERICANENERGYSUBSTATIONNDSNDSMAINTENANCEBUILDINGNDSNDSOUTLOT 'Y'LOT 1S00°02'31"W 3545.42'N89°57'29"W 1165.75'N00°02'31"E 3545.42'S89°57'29"E 1165.75'S00°17'47"E 1841.00'HICKMAN ROAD / HWY 6(ROW WIDTH VARIES)(PUBLIC STREET)280TH PLACE(PUBLIC STREET)T AVENUE
(PUBLIC STREET)
S AVENUE(PUBLIC STREET)
WAUKEE, IOWA
REVISIONS
ENGINEER: TWCENGINEER: RAHCIVIL DESIGN ADVANTAGE FIRST SUBMITTAL 10/26/2021
DATE
MORGAN PLAT 22104.260PHONE: (515) 369-4400
3405 S.E. CROSSROADS DRIVE, SUITE G
GRIMES, IOWA 50111
SECOND SUBMITTAL 01/04/2022
THIRD SUBMITTAL 01/22/2022
FOURTH SUBMITTAL 02/08/2022
DIMENSION PLANC1.0
LOT 1OUTLOT 'Y'LOT 1280TH PLACE(PUBLIC STREET)S AVENUE(PUBLIC STREET)
WAUKEE, IOWA
REVISIONS
ENGINEER: TWCENGINEER: RAHCIVIL DESIGN ADVANTAGE FIRST SUBMITTAL 10/26/2021
DATE
MORGAN PLAT 22104.260PHONE: (515) 369-4400
3405 S.E. CROSSROADS DRIVE, SUITE G
GRIMES, IOWA 50111
SECOND SUBMITTAL 01/04/2022
THIRD SUBMITTAL 01/22/2022
FOURTH SUBMITTAL 02/08/2022
DIMENSION PLANC1.1SHEET INDEXMATCH LINEMATCH LINE
DETENTION PONDDETENTION POND
LOT 1OUTLOT 'Z'LOT 2OUTLOT 'Y'LOT 1280TH PLACE(PUBLIC STREET)WAUKEE, IOWA
REVISIONS
ENGINEER: TWCENGINEER: RAHCIVIL DESIGN ADVANTAGE FIRST SUBMITTAL 10/26/2021
DATE
MORGAN PLAT 22104.260PHONE: (515) 369-4400
3405 S.E. CROSSROADS DRIVE, SUITE G
GRIMES, IOWA 50111
SECOND SUBMITTAL 01/04/2022
THIRD SUBMITTAL 01/22/2022
FOURTH SUBMITTAL 02/08/2022
DIMENSION PLANC1.2SHEET INDEXMATCH LINE
MATCH LINEMATCH LINE
DETENTIONPONDDETENTION PONDOUTLOT 'Z'280TH PLACE(PUBLIC STREET)T AVENUE
(PUBLIC STREET)
WAUKEE, IOWA
REVISIONS
ENGINEER: TWCENGINEER: RAHCIVIL DESIGN ADVANTAGE FIRST SUBMITTAL 10/26/2021
DATE
MORGAN PLAT 22104.260PHONE: (515) 369-4400
3405 S.E. CROSSROADS DRIVE, SUITE G
GRIMES, IOWA 50111
SECOND SUBMITTAL 01/04/2022
THIRD SUBMITTAL 01/22/2022
FOURTH SUBMITTAL 02/08/2022
DIMENSION PLANC1.3SHEET INDEXMATCH LINEMATCH LINELOT 2
F FOS/D JJJ
LVFJLVDLVDLVDOS/DLVDLVDLVDJ
FJ JJJJ
JJ
JJJJJJ
JJ
JJ3
33
3
JJ
JJ
JJ
JJ
JJ
JJ
JJ
J
J
JJ
J
1/ A-7101
RISER0601POE0503TRAP0901NDS1000SECURITY0701POE0502ELECENCLOSURE A0301ELECENCLOSURE B0302ADMIN/MDF0501GENERATORENCLOSURE2/ A-7101
FFOS/DJJJLVFJLVDLVDLVDOS/DLVDLVDLVDJFJJJJJJJJJJJJJJJJJ3333JJJJJJJJJJJJJJJJJJJ1/ A-7101RISER0601POE0503TRAP0901NDS1000SECURITY0701POE0502ELECENCLOSURE A0301ELECENCLOSURE B0302ADMIN/MDF0501GENERATORENCLOSURE2/ A-7101NOPARKINGLOT 1OUTLOT 'Y'OUTLOT 'Y'LOT 1S AVENUE(PUBLIC STREET)
WAUKEE, IOWA
REVISIONS
ENGINEER: TWCENGINEER: RAHCIVIL DESIGN ADVANTAGE FIRST SUBMITTAL 10/26/2021
DATE
MORGAN PLAT 22104.260PHONE: (515) 369-4400
3405 S.E. CROSSROADS DRIVE, SUITE G
GRIMES, IOWA 50111
SECOND SUBMITTAL 01/04/2022
THIRD SUBMITTAL 01/22/2022
FOURTH SUBMITTAL 02/08/2022
DIMENSION PLANC1.4SHEET INDEXMATCH LINEMATCH LINEMATCH LINE
FFOS/DJJJLVFJLVDLVDLVDOS/DLVDLVDLVDJFJJJJJJJJJJJJJJJJJ3333JJJJJJJJJJJJJJJJJJJ1/ A-7101RISER0601POE0503TRAP0901NDS1000SECURITY0701POE0502ELECENCLOSURE A0301ELECENCLOSURE B0302ADMIN/MDF0501GENERATORENCLOSURE2/ A-7101F FOS/D
JJJLVFJ
LV
D
LVDLVDOS/DLVDLVDLVDJF
J
JJJJ
JJ JJJJJJ
JJ
JJ
333
3
JJ
JJ
JJ
JJ
JJ
JJ
JJ
J
J JJ
J
1/ A-7101 RISER0601POE0503TRAP0901NDS1000SECURITY0701POE0502ELECENCLOSURE A0301ELECENCLOSURE B0302ADMIN/MDF0501GENERATORENCLOSURE2/ A-7101
LOT 2LOT 1OUTLOT 'Z'LOT 2MIDAMERICANENERGYSUBSTATIONOUTLOT 'Y'OUTLOT 'Y'WAUKEE, IOWA
REVISIONS
ENGINEER: TWCENGINEER: RAHCIVIL DESIGN ADVANTAGE FIRST SUBMITTAL 10/26/2021
DATE
MORGAN PLAT 22104.260PHONE: (515) 369-4400
3405 S.E. CROSSROADS DRIVE, SUITE G
GRIMES, IOWA 50111
SECOND SUBMITTAL 01/04/2022
THIRD SUBMITTAL 01/22/2022
FOURTH SUBMITTAL 02/08/2022
DIMENSION PLANC1.5SHEET INDEXMATCH LINE
MATCH LINE MATCH LINEMATCH LINE
OUTLOT 'Z'T AVENUE
(PUBLIC STREET)
WAUKEE, IOWA
REVISIONS
ENGINEER: TWCENGINEER: RAHCIVIL DESIGN ADVANTAGE FIRST SUBMITTAL 10/26/2021
DATE
MORGAN PLAT 22104.260PHONE: (515) 369-4400
3405 S.E. CROSSROADS DRIVE, SUITE G
GRIMES, IOWA 50111
SECOND SUBMITTAL 01/04/2022
THIRD SUBMITTAL 01/22/2022
FOURTH SUBMITTAL 02/08/2022
DIMENSION PLANC1.6SHEET INDEXMATCH LINE
MATCH LINEMATCH LINE
UPEV CHARGINGONLYEV CHARGINGONLYEV CHARGINGONLYEV CHARGINGONLYEV CHARGINGONLYEV CHARGINGONLYEV CHARGINGONLYEV CHARGINGONLYEV CHARGINGONLYEV CHARGINGONLYNOPARKINGNOPARKINGNOPARKINGNOPARKINGDETENTION PONDDETENTION PONDLOT 1OUTLOT 'Y'S AVENUE(PUBLIC STREET)
WAUKEE, IOWA
REVISIONS
ENGINEER: TWCENGINEER: RAHCIVIL DESIGN ADVANTAGE FIRST SUBMITTAL 10/26/2021
DATE
MORGAN PLAT 22104.260PHONE: (515) 369-4400
3405 S.E. CROSSROADS DRIVE, SUITE G
GRIMES, IOWA 50111
SECOND SUBMITTAL 01/04/2022
THIRD SUBMITTAL 01/22/2022
FOURTH SUBMITTAL 02/08/2022
DIMENSION PLANHICKMAN ROAD / HWY 6(ROW WIDTH VARIES)(PUBLIC STREET)C1.7SHEET INDEXMATCH LINE MATCH LINE
UPEV CHARGINGONLYEV CHARGINGONLYEV CHARGINGONLYEV CHARGINGONLYEV CHARGINGONLYEV CHARGINGONLYEV CHARGINGONLYEV CHARGINGONLYEV CHARGINGONLYEV CHARGINGONLYNOPARKINGNOPARKINGNOPARKINGNOPARKINGDETENTION PONDDETENTION PONDDETENTION PONDLOT 1LOT 3OUTLOT 'Z'OUTLOT 'Y'HICKMAN ROAD / HWY 6(ROW WIDTH VARIES)(PUBLIC STREET)WAUKEE, IOWA
REVISIONS
ENGINEER: TWCENGINEER: RAHCIVIL DESIGN ADVANTAGE FIRST SUBMITTAL 10/26/2021
DATE
MORGAN PLAT 22104.260PHONE: (515) 369-4400
3405 S.E. CROSSROADS DRIVE, SUITE G
GRIMES, IOWA 50111
SECOND SUBMITTAL 01/04/2022
THIRD SUBMITTAL 01/22/2022
FOURTH SUBMITTAL 02/08/2022
DIMENSION PLANC1.8SHEET INDEXMATCH LINE MATCH LINEMATCH LINE
DETENTION PONDDETENTION PONDOUTLOT 'Z'HICKMAN ROAD / HWY 6(ROW WIDTH VARIES)(PUBLIC STREET)T AVENUE
(PUBLIC STREET)
WAUKEE, IOWA
REVISIONS
ENGINEER: TWCENGINEER: RAHCIVIL DESIGN ADVANTAGE FIRST SUBMITTAL 10/26/2021
DATE
MORGAN PLAT 22104.260PHONE: (515) 369-4400
3405 S.E. CROSSROADS DRIVE, SUITE G
GRIMES, IOWA 50111
SECOND SUBMITTAL 01/04/2022
THIRD SUBMITTAL 01/22/2022
FOURTH SUBMITTAL 02/08/2022
DIMENSION PLANC1.9SHEET INDEXMATCH LINE
MATCH LINE
UPFF OS/DJ
J
J LVFJ
LVDLV DLVDOS/DLVDLVDLVDJ F
J
J
J
J J
J J
JJ
JJ
J
J
JJ
JJ
3
3
33JJJJJJ
JJ JJ
J J
J J
J
JJ
JJ1/ A-7101RISER0601POE0503TRAP0901NDS1000SECURITY0701POE0502ELECENCLOSURE A0301ELECENCLOSURE B0302ADMIN/MDF0501GENERATORENCLOSURE2/ A-7101F FOS/D JJJLVFJLVDLVDLVDOS/DLVD LVDLVD JFJ JJJJJJJJJJJJ JJJJ3333JJJJJJJJJJJJJJJJJJJ1/ A-7101 RISER0601POE0503TRAP0901NDS1000SECURITY0701POE0502ELECENCLOSURE A0301 ELECENCLOSURE B0302 ADMIN/MDF0501GENERATORENCLOSURE 2/ A-7101FFOS/DJJJLVF JLVDLVDLVDOS/DLVDLVDLVDJ FJJJ JJJ JJJJJJJJJJJ3333JJJJJJJJJJJJJJJJJJJ1/ A-7101RISER0601POE0503 TRAP0901NDS1000SECURITY0701POE0502 ELECENCLOSURE A0301ELECENCLOSURE B0302ADMIN/MDF0501 GENERATORENCLOSURE2/ A-7101
F FOS/D
J
J
JLVF
J
LVD
LVD LVDOS/DLVD LVDLVDJ
F
J
J
J
JJ
JJ
JJ
JJ
J
J
JJ
JJ
3
3
3
3
JJ
JJ
JJ
JJ
JJ
JJ
JJ
J
J
J
J
J
1/ A-7101 RISER0601POE0503TRAP0901NDS1000SECURITY0701POE0502ELECENCLOSURE A0301ELECENCLOSURE B0302ADMIN/MDF0501GENERATORENCLOSURE2/ A-7101EV CHARGINGONLYEV CHARGINGONLYEV CHARGINGONLYEV CHARGINGONLYEV CHARGINGONLYEV CHARGINGONLYEV CHARGINGONLYEV CHARGINGONLYEV CHARGINGONLYEV CHARGINGONLYNOPARKINGNOPARKINGNOPARKINGNOPARKINGNOPARKINGLOT 3LOT 2OUTLOT 'Z'NORMAL POOL= 1023.60100 YR ELEV = 1029.27NORMAL POOL= 1029.78100 YR ELEV = 1035.28NORMAL POOL= 1031.14100 YR ELEV = 1032.93NORMAL POOL= 1035.04100 YR ELEV = 1037.77NORMAL POOL= 1023.60100 YR ELEV = 1029.27NORMAL POOL= 1032.08100 YR ELEV = 1035.07GRADING LIMITSNORMAL POOL= 1035.04100 YR ELEV = 1037.77NORMAL POOL= 1025.14100 YR ELEV = 1034.10ADMINDATA CENTERGUARDHOUSEMIDAMERICANENERGYSUBSTATIONNDSNDSMAINTENANCEBUILDINGNDSNDSOUTLOT 'Y'LOT 1HICKMAN ROAD / HWY 6(ROW WIDTH VARIES)(PUBLIC STREET)280TH PLACE(PUBLIC STREET)T AVENUE
(PUBLIC STREET)
S AVENUE(PUBLIC STREET)
WAUKEE, IOWA
REVISIONS
ENGINEER: TWCENGINEER: RAHCIVIL DESIGN ADVANTAGE FIRST SUBMITTAL 10/26/2021
DATE
MORGAN PLAT 22104.260PHONE: (515) 369-4400
3405 S.E. CROSSROADS DRIVE, SUITE G
GRIMES, IOWA 50111
SECOND SUBMITTAL 01/04/2022
THIRD SUBMITTAL 01/22/2022
FOURTH SUBMITTAL 02/08/2022
GRADING PLANC2.0
LOT 1OUTLOT 'Y'LOT 1280TH PLACE(PUBLIC STREET)S AVENUE(PUBLIC STREET)
WAUKEE, IOWA
REVISIONS
ENGINEER: TWCENGINEER: RAHCIVIL DESIGN ADVANTAGE FIRST SUBMITTAL 10/26/2021
DATE
MORGAN PLAT 22104.260PHONE: (515) 369-4400
3405 S.E. CROSSROADS DRIVE, SUITE G
GRIMES, IOWA 50111
SECOND SUBMITTAL 01/04/2022
THIRD SUBMITTAL 01/22/2022
FOURTH SUBMITTAL 02/08/2022
GRADING PLANC2.1SHEET INDEXMATCH LINEMATCH LINE
NORMAL POOL= 1025.14
100 YR ELEV = 1034.10
LOT 1OUTLOT 'Z'LOT 2NORMAL POOL= 1023.60100 YR ELEV = 1029.27OUTLOT 'Y'LOT 1280TH PLACE(PUBLIC STREET)WAUKEE, IOWA
REVISIONS
ENGINEER: TWCENGINEER: RAHCIVIL DESIGN ADVANTAGE FIRST SUBMITTAL 10/26/2021
DATE
MORGAN PLAT 22104.260PHONE: (515) 369-4400
3405 S.E. CROSSROADS DRIVE, SUITE G
GRIMES, IOWA 50111
SECOND SUBMITTAL 01/04/2022
THIRD SUBMITTAL 01/22/2022
FOURTH SUBMITTAL 02/08/2022
GRADING PLANC2.2SHEET INDEXMATCH LINEMATCH LINE
F FOS/D JJJ
LVFJLVDLVDLVDOS/DLVDLVDLVDJ
FJ JJJJ
JJ
JJJJJJ
JJ
JJ3
33
3
JJ
JJ
JJ
JJ
JJ
JJ
JJ
J
J
JJ
J
1/ A-7101
RISER0601POE0503TRAP0901NDS1000SECURITY0701POE0502ELECENCLOSURE A0301ELECENCLOSURE B0302ADMIN/MDF0501GENERATORENCLOSURE2/ A-7101
FFOS/DJJJLVFJLVDLVDLVDOS/DLVDLVDLVDJFJJJJJJJJJJJJJJJJJ3333JJJJJJJJJJJJJJJJJJJ1/ A-7101RISER0601POE0503TRAP0901NDS1000SECURITY0701POE0502ELECENCLOSURE A0301ELECENCLOSURE B0302ADMIN/MDF0501GENERATORENCLOSURE2/ A-7101NOPARKINGF.F.E.=1045.10F.F.E.=1045.10F.F.E.=1044.20F.F.E.=1045.50OUTLOT 'Y'OUTLOT 'Y'LOT 1S AVENUE(PUBLIC STREET)
WAUKEE, IOWA
REVISIONS
ENGINEER: TWCENGINEER: RAHCIVIL DESIGN ADVANTAGE FIRST SUBMITTAL 10/26/2021
DATE
MORGAN PLAT 22104.260PHONE: (515) 369-4400
3405 S.E. CROSSROADS DRIVE, SUITE G
GRIMES, IOWA 50111
SECOND SUBMITTAL 01/04/2022
THIRD SUBMITTAL 01/22/2022
FOURTH SUBMITTAL 02/08/2022
GRADING PLANC2.3SHEET INDEXMATCH LINEMATCH LINE MATCH LINE
FFOS/DJJJLVFJLVDLVDLVDOS/DLVDLVDLVDJFJJJJJJJJJJJJJJJJJ3333JJJJJJJJJJJJJJJJJJJ1/ A-7101RISER0601POE0503TRAP0901NDS1000SECURITY0701POE0502ELECENCLOSURE A0301ELECENCLOSURE B0302ADMIN/MDF0501GENERATORENCLOSURE2/ A-7101F FOS/D
JJJLVFJ
LV
D
LVDLVDOS/DLVDLVDLVDJF
J
JJJJ
JJ JJJJJJ
JJ
JJ
333
3
JJ
JJ
JJ
JJ
JJ
JJ
JJ
J
J JJ
J
1/ A-7101 RISER0601POE0503TRAP0901NDS1000SECURITY0701POE0502ELECENCLOSURE A0301ELECENCLOSURE B0302ADMIN/MDF0501GENERATORENCLOSURE2/ A-7101F.F.E.=1045.10LOT 2LOT 1OUTLOT 'Z'LOT 2MIDAMERICANENERGYSUBSTATIONF.F.E.=1045.10OUTLOT 'Y'OUTLOT 'Y'WAUKEE, IOWA
REVISIONS
ENGINEER: TWCENGINEER: RAHCIVIL DESIGN ADVANTAGE FIRST SUBMITTAL 10/26/2021
DATE
MORGAN PLAT 22104.260PHONE: (515) 369-4400
3405 S.E. CROSSROADS DRIVE, SUITE G
GRIMES, IOWA 50111
SECOND SUBMITTAL 01/04/2022
THIRD SUBMITTAL 01/22/2022
FOURTH SUBMITTAL 02/08/2022
GRADING PLANC2.4SHEET INDEXMATCH LINEMATCH LINE
MATCH LINE
UPEV CHARGINGONLYEV CHARGINGONLYEV CHARGINGONLYEV CHARGINGONLYEV CHARGINGONLYEV CHARGINGONLYEV CHARGINGONLYEV CHARGINGONLYEV CHARGINGONLYEV CHARGINGONLYNOPARKINGNOPARKINGNOPARKINGNOPARKINGNORMAL POOL= 1029.78100 YR ELEV = 1035.28NORMAL POOL= 1031.14100 YR ELEV = 1032.93F.F.E.= 1045.50F.F.E.= 1045.50LOT 1OUTLOT 'Y'HICKMAN ROAD / HWY 6(ROW WIDTH VARIES)(PUBLIC STREET)S AVENUE(PUBLIC STREET)
WAUKEE, IOWA
REVISIONS
ENGINEER: TWCENGINEER: RAHCIVIL DESIGN ADVANTAGE FIRST SUBMITTAL 10/26/2021
DATE
MORGAN PLAT 22104.260PHONE: (515) 369-4400
3405 S.E. CROSSROADS DRIVE, SUITE G
GRIMES, IOWA 50111
SECOND SUBMITTAL 01/04/2022
THIRD SUBMITTAL 01/22/2022
FOURTH SUBMITTAL 02/08/2022
GRADING PLANC2.5SHEET INDEXMATCH LINEMATCH LINE
UPEV CHARGINGONLYEV CHARGINGONLYEV CHARGINGONLYEV CHARGINGONLYEV CHARGINGONLYEV CHARGINGONLYEV CHARGINGONLYEV CHARGINGONLYEV CHARGINGONLYEV CHARGINGONLYNOPARKINGNOPARKINGNOPARKINGNOPARKINGNORMAL POOL= 1035.17100 YR ELEV = 1037.77NORMAL POOL= 1032.08
100 YR ELEV = 1035.07NORMAL POOL= 1031.14100 YR ELEV = 1032.93F.F.E.= 1045.50F.F.E.= 1045.50LOT 1LOT 3OUTLOT 'Z'OUTLOT 'Y'HICKMAN ROAD / HWY 6(ROW WIDTH VARIES)(PUBLIC STREET)WAUKEE, IOWA
REVISIONS
ENGINEER: TWCENGINEER: RAHCIVIL DESIGN ADVANTAGE FIRST SUBMITTAL 10/26/2021
DATE
MORGAN PLAT 22104.260PHONE: (515) 369-4400
3405 S.E. CROSSROADS DRIVE, SUITE G
GRIMES, IOWA 50111
SECOND SUBMITTAL 01/04/2022
THIRD SUBMITTAL 01/22/2022
FOURTH SUBMITTAL 02/08/2022
GRADING PLANC2.6SHEET INDEXMATCH LINEMATCH LINE
UPFF OS/DJ
J
J LVFJ
LVDLV DLVDOS/DLVDLVDLVDJ F
J
J
J
J J
J J
JJ
JJ
J
J
JJ
JJ
3
3
33JJJJJJ
JJ JJ
J J
J J
J
JJ
JJ1/ A-7101RISER0601POE0503TRAP0901NDS1000SECURITY0701POE0502ELECENCLOSURE A0301ELECENCLOSURE B0302ADMIN/MDF0501GENERATORENCLOSURE2/ A-7101F FOS/D JJJLVFJLVDLVDLVDOS/DLVD LVDLVD JFJ JJJJJJJJJJJJ JJJJ3333JJJJJJJJJJJJJJJJJJJ1/ A-7101 RISER0601POE0503TRAP0901NDS1000SECURITY0701POE0502ELECENCLOSURE A0301 ELECENCLOSURE B0302 ADMIN/MDF0501GENERATORENCLOSURE 2/ A-7101FFOS/DJJJLVF JLVDLVDLVDOS/DLVDLVDLVDJ FJJJ JJJ JJJJJJJJJJJ3333JJJJJJJJJJJJJJJJJJJ1/ A-7101RISER0601POE0503 TRAP0901NDS1000SECURITY0701POE0502 ELECENCLOSURE A0301ELECENCLOSURE B0302ADMIN/MDF0501 GENERATORENCLOSURE2/ A-7101
F FOS/D
J
J
JLVF
J
LVD
LVD LVDOS/DLVD LVDLVDJ
F
J
J
J
JJ
JJ
JJ
JJ
J
J
JJ
JJ
3
3
3
3
JJ
JJ
JJ
JJ
JJ
JJ
JJ
J
J
J
J
J
1/ A-7101 RISER0601POE0503TRAP0901NDS1000SECURITY0701POE0502ELECENCLOSURE A0301ELECENCLOSURE B0302ADMIN/MDF0501GENERATORENCLOSURE2/ A-7101EV CHARGINGONLYEV CHARGINGONLYEV CHARGINGONLYEV CHARGINGONLYEV CHARGINGONLYEV CHARGINGONLYEV CHARGINGONLYEV CHARGINGONLYEV CHARGINGONLYEV CHARGINGONLYNOPARKINGNOPARKINGNOPARKINGNOPARKINGNOPARKINGLOT 3LOT 2OUTLOT 'Z'ADMINDATA CENTERGUARDHOUSEMIDAMERICANENERGYSUBSTATIONNDSNDSMAINTENANCEBUILDINGNDSNDSOUTLOT 'Y'LOT 1WAUKEE, IOWA
REVISIONS
ENGINEER: TWCENGINEER: RAHCIVIL DESIGN ADVANTAGE FIRST SUBMITTAL 10/26/2021
DATE
MORGAN PLAT 22104.260PHONE: (515) 369-4400
3405 S.E. CROSSROADS DRIVE, SUITE G
GRIMES, IOWA 50111
SECOND SUBMITTAL 01/04/2022
THIRD SUBMITTAL 01/22/2022
FOURTH SUBMITTAL 02/08/2022
UTILITY PLANC3.0HICKMAN ROAD / HWY 6(ROW WIDTH VARIES)(PUBLIC STREET)280TH PLACE(PUBLIC STREET)T AVENUE
(PUBLIC STREET)
S AVENUE(PUBLIC STREET)
F FOS/D JJJ
LVFJLVDLVDLVDOS/DLVDLVDLVDJ
FJ JJJJ
JJ
JJJJJJ
JJ
JJ3
33
3
JJ
JJ
JJ
JJ
JJ
JJ
JJ
J
J
JJ
J
1/ A-7101
RISER0601POE0503TRAP0901NDS1000SECURITY0701POE0502ELECENCLOSURE A0301ELECENCLOSURE B0302ADMIN/MDF0501GENERATORENCLOSURE2/ A-7101
FFOS/DJJJLVFJLVDLVDLVDOS/DLVDLVDLVDJFJJJJJJJJJJJJJJJJJ3333JJJJJJJJJJJJJJJJJJJ1/ A-7101RISER0601POE0503TRAP0901NDS1000SECURITY0701POE0502ELECENCLOSURE A0301ELECENCLOSURE B0302ADMIN/MDF0501GENERATORENCLOSURE2/ A-7101NOPARKINGLOT 1OUTLOT 'Y'OUTLOT 'Y'LOT 1S AVENUE(PUBLIC STREET)
WAUKEE, IOWA
REVISIONS
ENGINEER: TWCENGINEER: RAHCIVIL DESIGN ADVANTAGE FIRST SUBMITTAL 10/26/2021
DATE
MORGAN PLAT 22104.260PHONE: (515) 369-4400
3405 S.E. CROSSROADS DRIVE, SUITE G
GRIMES, IOWA 50111
SECOND SUBMITTAL 01/04/2022
THIRD SUBMITTAL 01/22/2022
FOURTH SUBMITTAL 02/08/2022
UTILITY PLANC3.1SHEET INDEXMATCH LINEMATCH LINE
FFOS/DJJJLVFJLVDLVDLVDOS/DLVDLVDLVDJFJJJJJJJJJJJJJJJJJ3333JJJJJJJJJJJJJJJJJJJ1/ A-7101RISER0601POE0503TRAP0901NDS1000SECURITY0701POE0502ELECENCLOSURE A0301ELECENCLOSURE B0302ADMIN/MDF0501GENERATORENCLOSURE2/ A-7101F FOS/D
JJJLVFJ
LV
D
LVDLVDOS/DLVDLVDLVDJF
J
JJJJ
JJ JJJJJJ
JJ
JJ
333
3
JJ
JJ
JJ
JJ
JJ
JJ
JJ
J
J JJ
J
1/ A-7101 RISER0601POE0503TRAP0901NDS1000SECURITY0701POE0502ELECENCLOSURE A0301ELECENCLOSURE B0302ADMIN/MDF0501GENERATORENCLOSURE2/ A-7101
LOT 2LOT 1OUTLOT 'Z'LOT 2MIDAMERICANENERGYSUBSTATIONOUTLOT 'Y'OUTLOT 'Y'WAUKEE, IOWA
REVISIONS
ENGINEER: TWCENGINEER: RAHCIVIL DESIGN ADVANTAGE FIRST SUBMITTAL 10/26/2021
DATE
MORGAN PLAT 22104.260PHONE: (515) 369-4400
3405 S.E. CROSSROADS DRIVE, SUITE G
GRIMES, IOWA 50111
SECOND SUBMITTAL 01/04/2022
THIRD SUBMITTAL 01/22/2022
FOURTH SUBMITTAL 02/08/2022
UTILITY PLANC3.2SHEET INDEXMATCH LINEMATCH LINE
UPEV CHARGINGONLYEV CHARGINGONLYEV CHARGINGONLYEV CHARGINGONLYEV CHARGINGONLYEV CHARGINGONLYEV CHARGINGONLYEV CHARGINGONLYEV CHARGINGONLYEV CHARGINGONLYNOPARKINGNOPARKINGNOPARKINGNOPARKINGLOT 1OUTLOT 'Y'HICKMAN ROAD / HWY 6(ROW WIDTH VARIES)(PUBLIC STREET)S AVENUE(PUBLIC STREET)
WAUKEE, IOWA
REVISIONS
ENGINEER: TWCENGINEER: RAHCIVIL DESIGN ADVANTAGE FIRST SUBMITTAL 10/26/2021
DATE
MORGAN PLAT 22104.260PHONE: (515) 369-4400
3405 S.E. CROSSROADS DRIVE, SUITE G
GRIMES, IOWA 50111
SECOND SUBMITTAL 01/04/2022
THIRD SUBMITTAL 01/22/2022
FOURTH SUBMITTAL 02/08/2022
UTILITY PLANC3.3SHEET INDEXMATCH LINEMATCH LINE
UPEV CHARGINGONLYEV CHARGINGONLYEV CHARGINGONLYEV CHARGINGONLYEV CHARGINGONLYEV CHARGINGONLYEV CHARGINGONLYEV CHARGINGONLYEV CHARGINGONLYEV CHARGINGONLYNOPARKINGNOPARKINGNOPARKINGNOPARKINGLOT 1LOT 3OUTLOT 'Z'OUTLOT 'Y'HICKMAN ROAD / HWY 6(ROW WIDTH VARIES)(PUBLIC STREET)WAUKEE, IOWA
REVISIONS
ENGINEER: TWCENGINEER: RAHCIVIL DESIGN ADVANTAGE FIRST SUBMITTAL 10/26/2021
DATE
MORGAN PLAT 22104.260PHONE: (515) 369-4400
3405 S.E. CROSSROADS DRIVE, SUITE G
GRIMES, IOWA 50111
SECOND SUBMITTAL 01/04/2022
THIRD SUBMITTAL 01/22/2022
FOURTH SUBMITTAL 02/08/2022
UTILITY PLANC3.4SHEET INDEXMATCH LINEMATCH LINE