HomeMy WebLinkAbout2022-03-07-J07 Morgan Plat 2_Final Plat AGENDA ITEM:
CITY OF WAUKEE, IOWA
CITY COUNCIL MEETING COMMUNICATION
MEETING DATE: March 7, 2022
AGENDA ITEM: Consideration of approval of a resolution approving a final plat for
Morgan Plat 2
FORMAT: Resolution
SYNOPSIS INCLUDING PRO & CON: The applicant is requesting approval of a final plat
for a 592-acre subdivision for a data center project. The property is
located north of Hickman Road and east of S Avenue. The plat includes
one (1) lot for the initial phase of the data center project. Lot 1 is 228.82-
acres in area. Two (2) addition outlots are shown for future development.
Outlot Y is 94.88-acres in area and Outlot Z is 268.37-acres in area.
Access to Lot 1 will be provided by S Avenue, for which the developer
will undertake improvements to pave S Avenue.
FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS:
COMMISSION/BOARD/COMMITTEE COMMENT: The Planning and Zoning
Commission reviewed the request at their meeting on February 8,
2022, recommended approval subject to remaining staff comments:
Approval of a Final Plat for Morgan Plat 2
Community Development Director, Andy Kass, introduced the request for approval of a
Preliminary Plat, Final Plat, and Site Plan for Project Morgan Plat 2 as submitted by the
applicant, Apple, Inc. The subject property is generally located north of Hickman Road, between
S Avenue and T Avenue, containing approximately 592 acres. The property was rezoned in 2017
in anticipation of a data center.
Mr. Kass advised that the site plan identifies the construction of a number of buildings. Building
WKE.01 is 315, 773 square feet in size for a data center building. WKE.01-Administration
Building, is approximately 63,349 square feet in area, a maintenance building is shown to be
10,511 square feet in area, and 4 network distribution buildings are shown to be 2,210 square feet
in area. A small guard building is shown at the entrance to the site. Any future data center
buildings will require separate site plan approvals.
Mr. Kass advised that the applicant will be required to pace S Avenue as part of public
improvements, and that the applicant has already constructed much of the storm water
infrastructure on the property. Sanitary sewer and water extensions will also be the responsibility
of the applicant. At this time Parking, landscaping, open space, and elevation requirements have
all been met. Staff would recommend approval subject to any remaining staff comments.
Commissioner Broderick questioned if there was a reason for the “U” shaped pond. Ryan
Hardisty of Civil Design Advantage and representative of the Applicant advised that the
area is very flat, so the U Shape allowed an increase in depth to accommodate stormwater
runoff from both S Avenue and the subject property.
Commissioner Koshy questioned if S Avenue will be constructed in Phases. Mr. Hardisty
advised that it will be paved all at once.
Commissioner Koshy questioned if any other boundary protections aside from the guard
gate existed for the site. Mr. Hardisty advised that large berms were incorporated into the
landscaping around the property, and an 8-foot fence is intended to be installed at the
boundary of the site.
Commissioner Gerlitz questioned if there was a timeline for the other buildings. Mr. Kass
advised not at this time.
Commissioner Broderick moved to Approve the Final Plat for Project Morgan Plat 2 subject to
any remaining staff comments. Commissioner Tessau seconded the motion. Ayes: Hoifeldt,
Streit, Broderick, Koshy, Tessau, and Gerlitz. Nays: none. Motion Carried.
STAFF REVIEW AND COMMENT: Staff’s position is that the proposed final plat meets the
intent and the requirements of the Zoning Ordinance and the Waukee
Subdivision Ordinance.
RECOMMENDATION: Staff recommends approval of the Final Plat for Morgan Plat 2.
ATTACHMENTS: I. Resolution
II. Staff Report
III. Final Plat
PREPARED BY: Andy Kass, Community Development Director
REVIEWED BY:
PUBLIC NOTICE INFORMATION –
NAME OF PUBLICATION:
DATE OF PUBLICATION:
THE CITY OF WAUKEE, IOWA
RESOLUTION 2022-
APPROVING THE FINAL PLAT FOR MORGAN PLAT 2
IN THE NAME AND BY THE AUTHORITY OF THE CITY OF WAUKEE, IOWA
WHEREAS, the City of Waukee, Dallas County, State of Iowa, is a duly organized Municipal
Organization; AND,
WHEREAS, Apple Inc., has requested final plat approval of Morgan Plat 2 (the “Plat”); AND,
WHEREAS, the City of Waukee Planning and Zoning Commission recommended approval of the Plat
on February 8, 2022, subject to remaining staff comments and review of the legal documents; AND,
WHEREAS, the Final Plat for Morgan Plat 2 and the documents relating thereto will comply with
section §176 – Subdivision Regulations of the Waukee Municipal Code.
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Waukee, Iowa on this
7th day of March, 2022, that the Final Plat for Morgan Plat 2 be and the same is hereby accepted and
approved by the City Council of the City of Waukee.
BE IT FURTHER RESOLVED that the City of Waukee does hereby accept the following easements
and documents to be filed with the Plat:
1. Warranty Deed;
2. Public Utility Easement;
3. Public Water Main Easement;
4. Public Storm Sewer Easement;
5. Public Storm Water Detention Easement;
6. Storm Water Management Facility Maintenance Covenant and Permanent Easement
Agreement;
7. Offsite Public Sanitary Sewer Easement; and
8. Offsite Public Storm Sewer Easement
____________________________
Courtney Clarke, Mayor
Attest:
___________________________________
Rebecca D. Schuett, City Clerk
RESULTS OF VOTE: AYE NAY ABSENT ABSTAIN
Anna Bergman Pierce
R. Charles Bottenberg
Chris Crone
Larry R. Lyon
Ben Sinclair
PLANNING AND ZONING COMMISSION STAFF REPORT
PROJECT: Morgan Plat 2 / Project Morgan WKE Site –
Preliminary Plat, Final Plat, & Site Plan
PREPARED BY: Andy Kass AICP, Community
Development Director
REPORT DATE: February 4, 2022
MEETING DATE: February 8, 2022
GENERAL INFORMATION
Applicant: Apple, Inc.
Owner:
Apple, Inc.
Owner’s Representative:
Ryan Hardisty, P.E. with Civil Design Advantage
Request: The applicant is requesting approval of a preliminary
plat, final plat, and site plan for a data center project.
Location and Size: Property is generally located north of Hickman Road,
between S Avenue and T Avenue, and containing
approximately 592 acres more or less.
AREA MAP
ABOVE: Aerial of Property identifying the proposed plat (outlined in ORANGE).
February 4, 2022
2 of 3
LAND USES AND ZONING
Location Existing Land Use Comprehensive Plan Current Zoning
Property in
Question
Vacant –
Undeveloped
Neighborhood
Residential
M-1 (Light Industrial District) / PD-1
(Planned Development Overlay)
North Vacant –
Undeveloped
Neighborhood
Residential
N/A (Dallas County)
South Vacant –
Undeveloped
Neighborhood
Residential
M-1 (Light Industrial District) / PD-1
(Planned Development Overlay)
East Vacant –
Undeveloped
Neighborhood
Residential
M-1 (Light Industrial District) / PD-1
(Planned Development Overlay)
West Vacant –
Undeveloped
Neighborhood
Residential
M-1 (Light Industrial District) / PD-1
(Planned Development Overlay)
HISTORY
The subject property is located north of Hickman Road and between T Avenue and S Avenue. The property was
annexed into the City of Waukee and rezoned in 2017. Apple, Inc., purchased the property and much of the
surrounding property with the intent to develop a data center. The applicant has submitted a detailed site plan for the
first phase of the data center project.
PROJECT DESCRIPTION
The site plan identifies the construction of a number of buildings for the data center. Building WKE.01 is 315,773 square
feet in area and is a data center building. Building WKE.01 is 63,349 square feet in area and is an administration building.
A maintenance building (WKE.93) is show shown to be 10,511 square feet in area. Network distribution buildings
(WKE.51, WKE.52, WKE.53, & WKE.54) are shown to be 2,210 square feet in area. A small guard building is shown at
the entrance to the site. Future data center buildings are shown on the site plan as well. The future buildings will require
additional site plan approvals. All proposed buildings meet the requirements of the M-1/PD-1 zoning district.
Table 1: M-1/PD-1 Zoning District Bulk Regulations
Category M-1/PD-1 (minimum)
Lot Area No minimum
Lot Width No minimum
Front Yard Setback 50 feet
Rear Yard Setback 50 feet
Side Yard Setback 25 feet
Setback Between Buildings 25 feet
Building Height 80 feet (maximum)
The final plat identifies one (1) lot and one (1) outlot to be platted. Staff is working with the applicant to address some
remaining comments as it relates to the platting of the site which may increase the number of lots platted. If there are
changes in the number of lots platted, the change would be minimal. The M-1/PD-1 zoning district does not have any
minimum requirements as it relates to lo area or width.
February 4, 2022
3 of 3
STREET IMPROVEMENTS, ACCESS & PARKING
The applicant will be required to pave S Ave as part of the public improvements for the site. Staff has been reviewing the
plans for S Avenue concurrently with the site plan and plats. Access into the site is provided from S Avenue on the west
side of the site. A total of 60 parking spaces are required for the first phase. The site plan identifies that 114 parking
spaces are to be provided.
UTILITIES
The applicant made improvements to the site in 2017 and 2018 when they constructed much of the stormwater
infrastructure on the property. A number of ponds on the site will provided detention for this phase and subsequent
future phases. Similar to the S Avenue road improvements, the applicant will be required to extend sanitary sewer and
water main along their plat boundaries and into their site. Staff has been reviewing the plans for public utilities
concurrently with the site plan and plats. Utilities located within the site will be privately owned and maintained by the
applicant.
LANDSCAPING & OPEN SPACE
As part of the planned development that was approved for the development, a 50-foot landscape buffer and a five-foot
berm along the perimeter of the property are shown on the site plan. In addition, the site plan demonstrates compliance
with all other required open space plantings. The site plan identifies that nearly 72% of the site will be open space.
BUILDING ELEVATIONS
Elevations of the proposed buildings have been provided and included for your review. The proposed materials include
precast concrete panels, architectural metal panels, glazing, fiber cement board. The proposed materials to be utilized on
the buildings are consistent with those identified within the Site Plan Ordinance.
STAFF RECOMMENDATION
The preliminary plat, final plat, and site plan meet the requirements of the Zoning Ordinance and the Planned
Development Agreement. The preliminary plat and final plat are in general conformance with the Subdivision Ordinance
and the Waukee Standard Specifications for Public Improvements. Staff recommends approval of the preliminary plat and
final plat for Morgan Plat 2 and the site plan for Project Morgan WKE Site, subject to remaining staff comments.
OUTLOT 'Z'OUTLOT 'Y'N89°34'43"E743.59'(M&R)N89°34'37"E 1318.18'(M&R)N89°36'38"E 1326.05'(M&R)N89°36'36"E 1224.83'(M&R)S45°01'50"E 35.13'(M&R)S00°19'44"W 2556.81'(M&R)S00°19'21"W 2534.94'(M&R)S45°07'20"W35.48'(M&R)S89°55'20"W2540.56'(M&R)S89°34'55"W 1319.80'(M&R)S89°34'41"W1497.46'(M&R)N45°11'24"W35.21'(M&R)N00°02'31"E 2519.15'(M&R)N00°21'50"E 1518.60'(M&R)N89°34'38"E 781.15'(M&R)N00°21'56"E 1064.81'(M&R)N89°55'20"E310.00'(M&R)S00°27'11"W350.00'(M&R)S89°55'20"W310.00'(M&R)N89°42'13"E576.00'(M&R)S00°17'47"E 1841.00'(M&R)S89°42'13"W576.00'(M&R)N00°17'47"W 1841.00'(M&R)N00°27'11"E350.00'(M&R)LOT 1MORGAN PLAT 2FINAL PLAT1FINAL PLAT LEGENDPLAT DESCRIPTIONNOTES(NOT IN PLAT)(NOT INPLAT)HICKMAN ROAD / HWY 6(ROW WIDTH VARIES)(PUBLIC STREET)280TH PLACE(PUBLIC STREET)T AVENUE
(PUBLIC STREET)
S AVENUE(PUBLIC STREET)
CIVIL DESIGN ADVANTAGE2104.260MORGAN PLAT 2
ENGINEER:TECH:
REVISIONS DATE
WAUKEE, IOWA1 FIRST SUBMITTAL 01/04/2022
PHONE: (515) 369-4400
3405 S.E. CROSSROADS DRIVE, SUITE G
GRIMES, IOWA 50111
REVIEW:ENGINEER / SURVEYOROWNER / DEVELOPERZONINGBULK REGULATIONSVICINITY MAPN 10TH STREETRACCOON RIVERVALLEY TRAIL270TH STREETCITY OF WAUKEECORPORATE LIMITS6PROJECT280TH PLACEHICKMAN RD / HWY 6S AVENUE
T AVENUE DATE OF SURVEYINDEX LEGEND