Loading...
HomeMy WebLinkAbout2022-05-16 I01H_05 Public Work Site Expansion Phase 1_Change Order 1AGENDA ITEM: CITY OF WAUKEE, IOWA CITY COUNCIL MEETING COMMUNICATION MEETING DATE: May 16, 2022 AGENDA ITEM:Consideration of approval of Change Order No. 1 to Core Construction Services for the Waukee Public Works Site Expansion– Phase 1 project increasing the contract amount by $15,712.16. FORMAT:Consent Agenda SYNOPSIS INCLUDING PRO & CON: Change Order No. 1 is to increase the depth of underslab drainage piping to reduce potential frost heave and add additional piping to connect to deeper storm sewer. FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS: The net result of this Change Order increases the contract price in the amount of $15,712.16. COMMISSION/BOARD/COMMITTEE COMMENT: STAFF REVIEW AND COMMENT: RECOMMENDATION: Approve the change order. ATTACHMENTS: I. Change Order No. 1 II. Letter of Recommendation PREPARED BY:Beth Richardson REVIEWED BY:Sara Kappos SKK PUBLIC NOTICE INFORMATION – NAME OF PUBLICATION: DATE OF PUBLICATION: I1H5 ENGINEERS | ARCHITECTS | SURVEYORS | SCIENTISTS 14225 University Avenue, Suite 110 Waukee, Iowa 50263 p 515.225.3469 www.f-w.com May 11, 2022 City of Waukee 805 University Avenue Waukee, Iowa 50263 Attn: Rudy Koester, Public Works Director Re: Change Order #001 Waukee Public Works Site Expansion Phase 1 Dear Mr. Koester: Attached please find a detailed Change Order for City Council approval on May 16, 2022. Change Description: 1. Sheet S1.1 – OVERALL FOUNDATION PLAN a. Revise Underslab Drainage Plan, by increasing depth of 670 LF of piping, 2’-3”, to lower the water table and therefore reduce the potential frost heave of the subgrade within the unheated building. b. Adjust routing of piping and add 112 LF of underslab drainage pipe to connect to deeper storm sewer piping. We have reviewed the submitted quotes from Core Construction and they appear to be in line with current industry pricing. If City Staff concurs with this proposed additional pricing, we recommend the City of Waukee Increase the contract price in the amount of $15,712.16 to complete the additional work associated with Change Order Number 001. If you have any questions, please contact me. Sincerely, FARNSWORTH GROUP, INC. Kristofer J. Orth, AIA Architecture Principal Enclosures: Change Order #001, dated 05/10/2022 Brad Deets, City Administrator COR #001 3093 NW Prairie Lane Des Moines, IA 50313 (515) 264-5156 Office (515) 257-4311 Fax TO: Farnsworth Group PROJECT NAME: 14225 University Ave Suite 110 PROJECT NUMBER: Waukee IA 50263 SUBJECT: FROM: ATTN: Kristofer Orth DATE: Unit Cost Total Unit Cost Total Unit Cost Total Unit Cost Total 1 2 Deepen and extend drain tile Prime $ 1.00 $ 14,753.20 $ 14,753.20 3 4 5 6 7 8 91 92 93 94 95 96 97 98 99 100 Subtotal -$ -$ -$ 14,753.20$ 14,753.20$ Small Tools Allowance 0.00% Warranty 0.00% 0.00% 0.00% 0.00% Overhead & Profit 10.00% 10.00% 10.00% 5.00% $ 737.66 $ 737.66 Bond 1.50% 1.50% 1.50% 1.50% $ 221.30 $ 221.30 The Contract Schedule will Increase / Decrease by:0 days TOTAL COR: Clarifications & Exclusions: Item #/ Cost Code Description Sub/Vendor Quantity Unit 15,712.16$ Labor Material Subcontractor TOTALEquipment WPW Site Expansion Phase1 21114 Drain Tile Depth Jeremy Roush 3/16/22 JobNo.COR-Log.JobName REV 7-17-19.xlsx 1 of 1 3/17/2022 PRIME EXCAVATING, INC CHAD LUNNING 641-590-7694 CLUNNING@PRIMEEXCAVATINGINC.COM GARY GRAF 515-210-7337 GGRAF@PRIMEEXCAVATINGINC.COM GRANT ARNDORFER 515-341-6881 GARNDORFER@PRIMEEXCAVATINGINC.COM ADDRESS 2136 MAMIE EISENHOWER AVE, BOONE, IA 50036 CHANGE ORDER REASON FOR CHANGE ORDER CHANGE IN QUANTITY AND DEPTH OF UNDERSLAB DRAINAGE PLAN. ORIGINAL PLAN CALLED FOR APPROXIMATELY 670 LF OF 4" UNDERSLAB DRAIN ASSUMED TO BE 3' DEEP. NEW PLAN CALLS FOR APPROXIMATELY 782 LF OF 4" UNDERSLAB DRAIN AT 5-6 FEET DEEP. THIS CHANGE ORDER WILL ADD AN ADDITION LINEAR FOOTAGE COST TO THE ORIGINAL QUANTITY FOR DEPTH & BACKFILL, ALONG WITH ADDITIONAL LINEAR FOOTAGE COST OF ADDED PIPE. OUR ORIGINAL UNIT PRICE FOR THE 4" UNDERSLAB DRAINAGE PLAN WAS $22/LF. CHANGE ORDER NUMBER 1001 BILL TO OWNER OF PROJECT PROJECT NAME & LOCATION GENERAL CONTRACTOR CHANGE ORDER DATE PREPARED BY CITY OF WAUKEE CITY OF WAUKEE WAUKEE PUBLIC WORKS SITE EXPANSION PHASE 1 - WAUKEE, IA CORE CONSTRUCTION 03/03/2022 GRANT ARNDORFER QUANTITY UNIT TYPE DESCRIPTION UNIT PRICE TOTAL 670 LF ADDITIONAL 2-3' DEPTH TO ORIGINAL UNDERSLAB DRAINAGE PLAN $14.00 $9,380.00 112 LF ADDITIONAL LENGTH OF UNDERSLAB DRAINAGE PLAN $36.00 $4,032.00 $0.00 $0.00 $0.00 $0.00 NOTES $0.00 $0.00 THE UNIT PRICE FOR ADDITIONAL DEPTH TRANSLATES INTO $5/FT FOR EQUIPMENT, $5/FT FOR LABOR, AND $4/FT FOR BACKFILL MATERIAL, TOTALING $14/FT. $0.00 $0.00 $0.00 $0.00 THE UNIT PRICE FOR ADDITIONAL LENGTH TRANSLATES INTO $10/FT FOR EQUIPMENT, $20/FT FOR LABOR, AND $6/FT FOR MATERIAL, TOTALING $36/FT. $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 10.00%PERCENT OVERHEAD AND PROFIT $13,412.00 $1,341.20 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 THIS CHANGE ORDER INCLUDES ALL LABOR, EQUIPMENT, MATERIALS, SHORING, AND DEWATERING TO INSTALL ABOVE ITEMS.TOTAL $14,753.20 SIGNATURE OF ACCEPTANCE:DATE: Proposal Request 14225 University Avenue, Suite 110 | Waukee, IA 50263 | p 515.225.3469 | www.f-w.com ENGINEERS | ARCHITECTS | SURVEYORS | SCIENTISTS Proposal Request Number: 01 Issue Date: February 9, 2022 Owner: City of Waukee, Iowa Project Name: Waukee Public Works Site Expansion Ph1 Project Number: 0201440.00 To: Core Construction Services, LLC Contract for: General Construction Contract Dated: December 17, 2021 Please submit an itemized quotation for changes in the contract sum and time incidental to proposed modifications to the contract documents described above. THIS IS NOT A CHANGE ORDER OR A DIRECTION TO PROCEED WITH THE WORK DESCRIBED BELOW. Description: Sheet S1.1 – OVERALL FOUNDATION PLAN 1. REVISE Underslab Drainage Plan per attached Supplementary Drawing S1.1-2. Issued By: FARNSWORTH GROUP, INC. Kristofer J. Orth, AIA Architecture Principal Attachments: S1.1-2 Underslab Drainage Plan PR-01 CONNECT TO STORM SEWER-SEE CIVIL DWGS 4"⌀PERFORATED DRAIN PIPE-TYP CONNECT TO STORM SEWER-SEE CIVIL DWGS STORM SEWER PIPE & STRUCTURES -SEE CIVIL DWGS STORM SEWER PIPE & STRUCTURES -SEE CIVIL DWGS STORM SEWER PIPE & STRUCTURES -SEE CIVIL DWGS IE 1018.00' IE 1016.0' CONTRACTOR OPTION: CONNECT TO EAST SW PIPE IN LIEU OF NORTH PIPEIE 1018.00'IE 1017.50'IE 1016.25'IE 1016.00' IE 1018.00' IE 1016.50' IE 1016.25' IE 1016.00' IE 1016.25' BUILDING FFE 1021.50' PROVIDE 8' LENGTH OF SOLID PIPE BELOW FTG PROVIDE 8' LENGTH OF SOLID PIPE BELOW FTG 4" ⌀ PE R F O R A T E D DR A I N P I P E -TY P REVIEWED: DATE: DRAWN: PROJECT NO.: 2/ 9 / 2 0 2 2 1 0 : 5 7 : 2 0 A M 02/09/22 PR-01 S1.1-2 NTK NTK 0201440.00 UNDERSLAB DRAINAGE PLAN Waukee Public Works Site Expansion Phase 1 City of Waukee, Iowa 1" = 40'-0"3 UNDERSLAB DRAINAGE PLAN PR-01