HomeMy WebLinkAbout2022-07-18 H01B NW Douglas Pkwy Grade, Partial Pave, JUT_Award ContractAGENDA ITEM:
CITY OF WAUKEE, IOWA
CITY COUNCIL MEETING COMMUNICATION
MEETING DATE: July 18, 2022
AGENDA ITEM:Consideration of approval of resolution awarding contract [NW Douglas
Parkway Project – Grade, Partial Pave and Joint Utility Trench]
FORMAT:Resolution
SYNOPSIS INCLUDING PRO & CON: The bids are for furnishing all materials, labor and
equipment necessary for the construction of the NW Douglas Parkway – Grade, Partial Pave and
JUT Project located from 1,200-feet west of N Warrior Lane to N. Warrior Lane, 3/4 -mile North
of U.S. Highway 6 (Hickman Rd). Work includes grading, PCC paving, storm sewer, water main,
subdrain, pavement markings, signing, and associated work. The project also includes installation
of a Joint Utility Trench (JUT) along NW Douglas Parkway between NW 2nd Street and N.
Warrior Lane and along NW 2nd Street from NW Douglas Parkway to approximately 850-feet
south.
Bids were received on July 13, 2022, with four general contractors submitting bids. The
engineer’s estimate for the project was $1,503,337.00, The apparent low bid was submitted by
Concrete Technologies Incorporated of Grimes, Iowa for $1,386,940.85. Snyder and Associates
recommends award of the contract to Concrete Technologies Incorporated of Grimes, Iowa for
$1,386,940.85. This bid is approximately 7.7% below the engineer’s estimate.
FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS: $1,386,940.85
COMMISSION/BOARD/COMMITTEE COMMENT:
STAFF REVIEW AND COMMENT: Staff recommend approval of the resolution awarding
the contract to Concrete Technologies Incorporated of Grimes, Iowa for $1,386,940.85
RECOMMENDATION: Approve the resolution.
ATTACHMENTS: I. Bid Summary
II. Letter of Recommendation
PREPARED BY:Beth Richardson
REVIEWED BY:Rudy Koester RK
H1B
RESOLUTION 2022-
RESOLUTION MAKING AWARD OF CONSTRUCTION
CONTRACT FOR THE NW DOUGLAS PARKWAY - GRADE,
PARTIAL PAVE AND JUT
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF WAUKEE, STATE
OF IOWA:
Section 1.That the following bid for the construction of certain public improvements
described in general as the NW Douglas Parkway - Grade, Partial Pave and JUT, described in the
plans and specifications heretofore adopted by this Council on July 18, 2022, be and is hereby
accepted, the same being the lowest responsive, responsible bid received for such work, as follows:
Contractor:Concrete Technologies, Inc.,of Grimes, IA
Amount of bid:$1,386,940.85
Portion of project:All construction work
Section 2.That the Mayor and Clerk are hereby directed to execute the contract with the
contractor for the construction of the public improvements, such contract not to be binding on the
City until approved by this Council.
PASSED AND APPROVED this 18th day of July, 2022.
Mayor
ATTEST:
City Clerk
V:\Projects\2022\122.0091.01\AdvertisingLetting\LTR_2022-07-14_AwardRecommendation.docx
July 14, 2021
Mr. Rudy Koester
Public Works Director
City of Waukee
805 University Avenue
Waukee, IA 50263
RE: RECEIPT OF BIDS AND RECOMMENDATION OF AWARD
NW DOUGLAS PARKWAY – GRADE, PARTIAL PAVE AND JUT
Dear Rudy:
Bids were received for the NW Douglas Parkway – Grade, Partial Pave and JUT project at 2:00
p.m. on Wednesday, July 13, 2022. Four bids were received and opened ranging from
$1,386,940.85 to $1,541,869.00. Our opinion of probable construction cost was $1,504,000. The
low bid was submitted by Concrete Technologies, Inc. of Grimes, Iowa. We were pleased with
the interest from contractors and the number of bids received.
Upon further inspection of the bids, Absolute Concrete did not submit the second page of the
bidder status form, however, this does not affect the outcome of the bid.
The low bidder is primarily a paving contractor and therefore able to self-perform a large
component of the work. They also own a ready-mix concrete company, CTI Ready Mix, LLC
and have experience with similar sized projects in the area and for the City of Waukee.
We recommend award of the contract to the low bidder, Concrete Technologies, Inc. They have
a long history of successful projects and are fully capable of successfully carrying out the
requirements of the contract.
Sincerely,
SNYDER & ASSOCIATES, INC.
Nathan Carhoff, P.E.
Project Manager
TABULATION OF BIDS
NW Douglas Parkway - Grade, Partial Pave and JUT
City of Waukee
S&A Project No. 122.0091.01
Bid Date/Time: July 13, 2022 at 2:00 PM
ITEM DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL PRICE TOTAL PRICE TOTAL PRICE TOTAL PRICE TOTAL PRICE
EARTHWORK
2.1 TOPSOIL, ON SITE CY 3,101 15.00$ 46,515.00$ 10.90$ 33,800.90$ 7.75$ 24,032.75$ 10.50$ 32,560.50$ 15.25$ 47,290.25$
2.2 EXCAVATION, CLASS 10 CY 3,025 12.00$ 36,300.00$ 5.95$ 17,998.75$ 9.75$ 29,493.75$ 5.75$ 17,393.75$ 14.50$ 43,862.50$
2.3 SUBGRADE PREPARATION SY 5,188 4.00$ 20,752.00$ 2.85$ 14,785.80$ 2.75$ 14,267.00$ 2.75$ 14,267.00$ 3.75$ 19,455.00$
2.4 SUBGRADE TREATMENT (CEMENT OR FLY ASH)SY 519 12.00$ 6,228.00$ 14.75$ 7,655.25$ 32.25$ 16,737.75$ 14.25$ 7,395.75$ 62.00$ 32,178.00$
2.5 SUBBASE, GRANULAR, 6 INCH DEPTH SY 4,594 10.00$ 45,940.00$ 12.50$ 57,425.00$ 11.00$ 50,534.00$ 12.00$ 55,128.00$ 15.00$ 68,910.00$
2.6 SUBBASE, GRANULAR, 9 INCH DEPTH SY 595 15.00$ 8,925.00$ 21.75$ 12,941.25$ 14.50$ 8,627.50$ 21.00$ 12,495.00$ 22.00$ 13,090.00$
TRENCH AND TRENCHLESS CONSTRUCTION
3.1 TRENCH FOUNDATION TON 62 40.00$ 2,480.00$ 47.75$ 2,960.50$ 44.00$ 2,728.00$ 50.00$ 3,100.00$ 48.00$ 2,976.00$
SEWERS AND DRAINS
4.1 STORM SEWER, TRENCHED, CLASS III RCP, 15 INCH LF 556 95.00$ 52,820.00$ 78.25$ 43,507.00$ 69.00$ 38,364.00$ 99.00$ 55,044.00$ 77.00$ 42,812.00$
4.2 STORM SEWER, TRENCHED, CLASS III RCP, 24 INCH LF 60 120.00$ 7,200.00$ 111.75$ 6,705.00$ 98.00$ 5,880.00$ 125.00$ 7,500.00$ 110.00$ 6,600.00$
4.3 STORM SEWER, TRENCHED, UNCLASSIFIED, 15 INCH LF 16 70.00$ 1,120.00$ 124.25$ 1,988.00$ 82.00$ 1,312.00$ 107.00$ 1,712.00$ 125.00$ 2,000.00$
4.4 PIPE CULVERT, TRENCHED, UNCLASSIFIED, 12 INCH LF 164 70.00$ 11,480.00$ 69.00$ 11,316.00$ 62.00$ 10,168.00$ 99.00$ 16,236.00$ 68.00$ 11,152.00$
4.5 PIPE APRON, RCP, 24 INCH EA 1 2,500.00$ 2,500.00$ 3,690.00$ 3,690.00$ 3,575.00$ 3,575.00$ 3,800.00$ 3,800.00$ 3,700.00$ 3,700.00$
4.6 FOOTING FOR CONCRETE PIPE APRON, RCP, 24 INCH EA 1 2,000.00$ 2,000.00$ 1,080.00$ 1,080.00$ 745.00$ 745.00$ 570.00$ 570.00$ 1,100.00$ 1,100.00$
4.7 SUBDRAIN, TYPE 1, 6 INCH LF 1,253 18.00$ 22,554.00$ 14.00$ 17,542.00$ 22.00$ 27,566.00$ 35.00$ 43,855.00$ 25.00$ 31,325.00$
4.8 SUBDRAIN CLEANOUT, TYPE A1, 6 INCH EA 2 750.00$ 1,500.00$ 415.00$ 830.00$ 1,075.00$ 2,150.00$ 1,500.00$ 3,000.00$ 800.00$ 1,600.00$
4.9 SUBDRAIN CLEANOUT, TYPE B EA 1 1,000.00$ 1,000.00$ 1,245.00$ 1,245.00$ 2,400.00$ 2,400.00$ 3,200.00$ 3,200.00$ 700.00$ 700.00$
4.10 SUBDRAIN OUTLETS AND CONNECTIONS, OUTLET INTO STRUCTURE, 6 INCHEA 6 500.00$ 3,000.00$ 365.00$ 2,190.00$ 465.00$ 2,790.00$ 2,600.00$ 15,600.00$ 325.00$ 1,950.00$
WATER MAIN AND APPURTENANCES
5.1 WATER MAIN, TRENCHED, PVC, 8 INCH LF 126 70.00$ 8,820.00$ 70.50$ 8,883.00$ 85.25$ 10,741.50$ 91.00$ 11,466.00$ 70.00$ 8,820.00$
5.2 WATER MAIN, TRENCHED, PVC, 12 INCH LF 884 90.00$ 79,560.00$ 77.75$ 68,731.00$ 83.25$ 73,593.00$ 122.00$ 107,848.00$ 76.00$ 67,184.00$
5.3 WATER MAIN, TRENCHLESS, PVC, 12 INCH LF 44 250.00$ 11,000.00$ 590.00$ 25,960.00$ 357.25$ 15,719.00$ 660.00$ 29,040.00$ 600.00$ 26,400.00$
5.4 FITTING, 8 INCH x 6 INCH REDUCER EA 1 1,500.00$ 1,500.00$ 540.00$ 540.00$ 575.00$ 575.00$ 540.00$ 540.00$ 550.00$ 550.00$
5.5 FITTING, 12 INCH x 6 INCH TEE EA 3 2,000.00$ 6,000.00$ 1,365.00$ 4,095.00$ 1,345.00$ 4,035.00$ 1,300.00$ 3,900.00$ 1,400.00$ 4,200.00$
5.6 FITTING, 12 INCH x 8 INCH TEE EA 1 3,000.00$ 3,000.00$ 1,565.00$ 1,565.00$ 1,475.00$ 1,475.00$ 1,300.00$ 1,300.00$ 1,600.00$ 1,600.00$
5.7 VALVE, GATE, 8 INCH EA 1 3,000.00$ 3,000.00$ 2,600.00$ 2,600.00$ 2,795.00$ 2,795.00$ 2,300.00$ 2,300.00$ 2,700.00$ 2,700.00$
5.8 VALVE, GATE, 12 INCH EA 3 6,000.00$ 18,000.00$ 4,315.00$ 12,945.00$ 4,425.00$ 13,275.00$ 3,800.00$ 11,400.00$ 4,300.00$ 12,900.00$
5.9 FIRE HYDRANT ASSEMBLY EA 3 9,000.00$ 27,000.00$ 7,595.00$ 22,785.00$ 6,650.00$ 19,950.00$ 7,200.00$ 21,600.00$ 7,600.00$ 22,800.00$
5.1 FIRE HYDRANT ASSEMBLY, REMOVE, SALVAGE AND REINSTALL EA 1 1,000.00$ 1,000.00$ 2,275.00$ 2,275.00$ 2,275.00$ 2,275.00$ 4,600.00$ 4,600.00$ 2,300.00$ 2,300.00$
STRUCTURES FOR SANITARY AND STORM
6.1 MANHOLE, SW-401, 48 INCH EA 3 5,000.00$ 15,000.00$ 3,720.00$ 11,160.00$ 4,515.00$ 13,545.00$ 4,700.00$ 14,100.00$ 3,700.00$ 11,100.00$
6.2 INTAKE, SW-505 EA 3 4,500.00$ 13,500.00$ 5,205.00$ 15,615.00$ 4,485.00$ 13,455.00$ 6,400.00$ 19,200.00$ 5,300.00$ 15,900.00$
STREETS AND RELATED WORK
7.1 PAVEMENT, PCC, 6 INCH SY 520 70.00$ 36,400.00$ 68.00$ 35,360.00$ 80.50$ 41,860.00$ 71.06$ 36,951.20$ 77.00$ 40,040.00$
7.2 PAVEMENT, PCC, 9 INCH SY 3,737 85.00$ 317,645.00$ 80.00$ 298,960.00$ 90.00$ 336,330.00$ 83.60$ 312,413.20$ 85.00$ 317,645.00$
7.3 PAVEMENT, PCC, 9 INCH, REINFORCED SY 130 110.00$ 14,300.00$ 85.00$ 11,050.00$ 190.00$ 24,700.00$ 88.83$ 11,547.90$ 125.00$ 16,250.00$
7.4 PCC PAVEMENT SAMPLES AND TESTING LS 1 10,000.00$ 10,000.00$ 3,500.00$ 3,500.00$ 5,000.00$ 5,000.00$ 3,657.50$ 3,657.50$ 7,500.00$ 7,500.00$
7.5 SHARED USE PATH, PCC, 6 INCH SY 2,129 50.00$ 106,450.00$ 49.00$ 104,321.00$ 50.00$ 106,450.00$ 51.21$ 109,026.09$ 52.00$ 110,708.00$
7.6 SPECIAL SUBGRADE PREPARATION FOR SHARED USE PATH SY 2,553 5.00$ 12,765.00$ 3.65$ 9,318.45$ 2.75$ 7,020.75$ 3.50$ 8,935.50$ 4.25$ 10,850.25$
7.7 DETECTABLE WARNINGS, CAST IRON, NATURAL FINISH SF 70 60.00$ 4,200.00$ 47.00$ 3,290.00$ 100.00$ 7,000.00$ 49.12$ 3,438.40$ 65.00$ 4,550.00$
7.8 PAVEMENT REMOVAL SY 21 75.00$ 1,575.00$ 81.75$ 1,716.75$ 87.00$ 1,827.00$ 79.00$ 1,659.00$ 85.00$ 1,785.00$
TRAFFIC CONTROL
8.1 PAINTED PAVEMENT MARKINGS, DURABLE STA 53 125.00$ 6,625.00$ 171.00$ 9,063.00$ 180.00$ 9,540.00$ 172.43$ 9,138.79$ 210.00$ 11,130.00$
8.2 PAINTED SYMBOLS AND LEGENDS, DURABLE EA 4 600.00$ 2,400.00$ 415.00$ 1,660.00$ 200.00$ 800.00$ 418.00$ 1,672.00$ 225.00$ 900.00$
8.3 GROOVES CUT FOR PAVEMENT MARKINGS STA 53 50.00$ 2,650.00$ 88.00$ 4,664.00$ 95.00$ 5,035.00$ 88.83$ 4,707.99$ 100.00$ 5,300.00$
8.4 GROOVED CUT FOR SYMBOLS AND LEGENDS EA 4 300.00$ 1,200.00$ 181.25$ 725.00$ 100.00$ 400.00$ 182.88$ 731.52$ 110.00$ 440.00$
8.5 TEMPORARY TRAFFIC CONTROL LS 1 20,000.00$ 20,000.00$ 6,210.00$ 6,210.00$ 15,000.00$ 15,000.00$ 6,270.00$ 6,270.00$ 11,000.00$ 11,000.00$
8.6 SIGN ASSEMBLY, FURNISH AND INSTALL, TYPE A EA 8 1,500.00$ 12,000.00$ 415.00$ 3,320.00$ 400.00$ 3,200.00$ 418.00$ 3,344.00$ 425.00$ 3,400.00$
8.7 JOINT UTILITY TRENCH, TRENCHED, 6-CELL LF 493 45.00$ 22,185.00$ 46.60$ 22,973.80$ 45.00$ 22,185.00$ 47.03$ 23,185.79$ 47.00$ 23,171.00$
8.8 JOINT UTILITY TRENCH, TRENCHED, 12-CELL LF 2,096 90.00$ 188,640.00$ 69.50$ 145,672.00$ 67.00$ 140,432.00$ 70.02$ 146,761.92$ 69.00$ 144,624.00$
8.9 JOINT UTILITY TRENCH, TRENCHLESS, 6-CELL LF 348 90.00$ 31,320.00$ 69.00$ 24,012.00$ 66.75$ 23,229.00$ 69.75$ 24,273.00$ 70.00$ 24,360.00$
8.1 JOINT UTILITY TRENCH, TRENCHLESS, 12-CELL LF 366 180.00$ 65,880.00$ 91.00$ 33,306.00$ 88.00$ 32,208.00$ 91.96$ 33,657.36$ 90.00$ 32,940.00$
8.11 HANDHOLE, TYPE IV, FURNISH AND INSTALL EA 22 1,250.00$ 27,500.00$ 3,210.00$ 70,620.00$ 3,100.00$ 68,200.00$ 3,239.50$ 71,269.00$ 3,300.00$ 72,600.00$
ENGINEER'S ESTIMATE CONCRETE TECHNOLOGIES
GRIMES, IA
UNIT PRICE
ELDER CORPORATION
DES MOINES, IA
UNIT PRICE
ABSOLUTE CONCRETE
SLATER, IA
UNIT PRICE
21 3 4
ALLIANCE CONST GROUP
URBANDALE, IA
UNIT PRICE
V:\Projects\2022\122.0091.01\AdvertisingLetting\BIDTAB_2022-07-13_NWDouglasPkwy.xlsxBIDTAB_2022-07-13_NWDouglasPkwy.xlsx
TABULATION OF BIDS
NW Douglas Parkway - Grade, Partial Pave and JUT
City of Waukee
S&A Project No. 122.0091.01
Bid Date/Time: July 13, 2022 at 2:00 PM
ITEM DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL PRICE TOTAL PRICE TOTAL PRICE TOTAL PRICE TOTAL PRICE
ENGINEER'S ESTIMATE CONCRETE TECHNOLOGIES
GRIMES, IA
UNIT PRICE
ELDER CORPORATION
DES MOINES, IA
UNIT PRICE
ABSOLUTE CONCRETE
SLATER, IA
UNIT PRICE
21 3 4
ALLIANCE CONST GROUP
URBANDALE, IA
UNIT PRICE
SITE WORK AND LANDSCAPING
9.1 HYDRAULIC SEEDING, SEEDING, FERTILIZING AND MULCHING, TYPE 1ACRE 2.7 3,500.00$ 9,450.00$ 5,280.00$ 14,256.00$ 6,500.00$ 17,550.00$ 6,270.00$ 16,929.00$ 5,300.00$ 14,310.00$
9.2 HYDRAULIC SEEDING, SEEDING, FERTILIZING AND MULCHING, TYPE 4ACRE 4 1,000.00$ 4,000.00$ 3,520.00$ 14,080.00$ 4,000.00$ 16,000.00$ 4,180.00$ 16,720.00$ 3,700.00$ 14,800.00$
9.3 SWPPP PREPARATION LS 1 2,000.00$ 2,000.00$ 2,070.00$ 2,070.00$ 1,500.00$ 1,500.00$ 1,567.50$ 1,567.50$ 2,200.00$ 2,200.00$
9.4 SWPPP MANAGEMENT LS 1 3,000.00$ 3,000.00$ 3,415.00$ 3,415.00$ 6,000.00$ 6,000.00$ 5,225.00$ 5,225.00$ 3,500.00$ 3,500.00$
9.5 FILTER SOCK, 12 INCH LF 4,654 3.00$ 13,962.00$ 2.10$ 9,773.40$ 3.50$ 16,289.00$ 3.14$ 14,613.56$ 2.25$ 10,471.50$
9.6 FILTER SOCK REMOVAL LF 4,654 0.50$ 2,327.00$ 0.55$ 2,559.70$ 1.00$ 4,654.00$ 0.78$ 3,630.12$ 0.75$ 3,490.50$
9.7 TEMPORARY RECP, TYPE 3A (EXTENDED TERM)SY 709 2.00$ 1,418.00$ 5.70$ 4,041.30$ 4.00$ 2,836.00$ 4.18$ 2,963.62$ 6.00$ 4,254.00$
9.8 RIP RAP, CLASS E TON 30 80.00$ 2,400.00$ 120.00$ 3,600.00$ 85.00$ 2,550.00$ 76.00$ 2,280.00$ 125.00$ 3,750.00$
9.9 SILT FENCE OR SILT FENCE DITCH CHECK LF 4,200 3.00$ 12,600.00$ 1.80$ 7,560.00$ 1.80$ 7,560.00$ 1.88$ 7,896.00$ 2.00$ 8,400.00$
9.1 SILT FENCE OR SILT FENCE DITCH CHECK REMOVAL OF SEDIMENT LF 4,200 0.50$ 2,100.00$ 0.30$ 1,260.00$ 0.05$ 210.00$ 0.05$ 210.00$ 0.50$ 2,100.00$
9.11 SILT FENCE OR SILT FENCE DITCH CHECK REMOVAL OF DEVICE LF 4,200 0.50$ 2,100.00$ 0.30$ 1,260.00$ 0.05$ 210.00$ 0.05$ 210.00$ 0.50$ 2,100.00$
9.12 STABILIZED CONSTRUCTION ENTRANCE SY 245 50.00$ 12,250.00$ 12.00$ 2,940.00$ 18.50$ 4,532.50$ 11.50$ 2,817.50$ 23.00$ 5,635.00$
9.13 INLET PROTECTION DEVICE, DROP-IN EA 4 250.00$ 1,000.00$ 210.00$ 840.00$ 250.00$ 1,000.00$ 261.25$ 1,045.00$ 225.00$ 900.00$
9.14 INLET PROTECTION DEVICE, MAINTENANCE AND REMOVAL EA 4 75.00$ 300.00$ 26.00$ 104.00$ 50.00$ 200.00$ 52.25$ 209.00$ 27.50$ 110.00$
MISCELLANEOUS
11.1 MOBILIZATION LS 1 86,000.00$ 86,000.00$ 112,000.00$ 112,000.00$ 150,000.00$ 150,000.00$ 90,042.54$ 90,042.54$ 115,000.00$ 115,000.00$
11.2 CONCRETE WASHOUT LS 1 5,000.00$ 5,000.00$ 2,625.00$ 2,625.00$ 4,000.00$ 4,000.00$ 2,750.00$ 2,750.00$ 4,500.00$ 4,500.00$
TOTAL BID:1,504,000.00$ 1,386,940.85$ 1,498,312.50$ 1,501,900.00$ 1,541,869.00$
BID SECURITY:10%10%10%10%
Notes
- -
V:\Projects\2022\122.0091.01\AdvertisingLetting\BIDTAB_2022-07-13_NWDouglasPkwy.xlsxBIDTAB_2022-07-13_NWDouglasPkwy.xlsx