HomeMy WebLinkAbout2022-08-01 J01F_03 Public Works Site Expansion Phase 1_Change Order 1AGENDA ITEM:
CITY OF WAUKEE, IOWA
CITY COUNCIL MEETING COMMUNICATION
MEETING DATE: August 1, 2022
AGENDA ITEM:Consideration of approval of Change Order No. 2 to Core Construction
Services for the Waukee Public Works Site Expansion– Phase 1 project
increasing the contract amount by $9,154.89.
FORMAT:Consent Agenda
SYNOPSIS INCLUDING PRO & CON: Change Order No. 2 is for additional grading work,
replacing handicap sign and post, structural engineering changes to the salt storage roof, isolation
of fire sprinkler thrust block from footing, and cold weather protection for concrete paving work.
FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS: The net result of this
Change Order increases the contract price in the amount of $9,154.89.
COMMISSION/BOARD/COMMITTEE COMMENT:
STAFF REVIEW AND COMMENT:
RECOMMENDATION: Approve the change order.
ATTACHMENTS: I. Change Order No. 2
II. Letter of Recommendation
PREPARED BY:Beth Richardson
REVIEWED BY:Sara Kappos SKK
PUBLIC NOTICE INFORMATION –
NAME OF PUBLICATION:
DATE OF PUBLICATION:
J1F3
ENGINEERS | ARCHITECTS | SURVEYORS | SCIENTISTS
14225 University Avenue, Suite 110
Waukee, Iowa 50263
p 515.225.3469
www.f-w.com
July 21, 2022
City of Waukee
805 University Avenue
Waukee, Iowa 50263
Attn: Rudy Koester, Public Works Director
Re: Change Order #002
Waukee Public Works Site Expansion Phase 1
Dear Mr. Koester:
Attached please find a detailed Change Order for City Council approval on August 1, 2022.
Change Description:
1. COR-004:
Sheet C201 – GRADING PLAN
a. Additional grading work was required to slope grade evenly from above existing footing
to edge of new concrete sidewalk. Contractors completed 7 additional hours of grading
with dump truck and track skid loader.
2. COR-005:
Sheet C101 – SITE PLAN
a. Replace (2) Existing Handicapped Parking Signs and Posts to match the (3) New Signs
provided in the project.
3. COR-006:
Sheet S2.3 – SALT STORAGE ROOF FRAMING PLAN
a. Add 120’-0” of HSS 5x3x3/16 on top of W30x90 Beams to support metal roof deck
between the roof joist seats. The Structural Engineer did not include a detail of this
condition in the bid document drawings, so it is additional work for the contractors.
4. COR-008:
Sheet S1.2 – WEST WING FOUNDATION PLAN
a. Fire Marshal required concrete thrust block at 6” fire sprinkler service entrance be
isolated from the structural concrete footing. This required contractors to bulkhead and
isolate the footing and thrust block pours, an additional void form and additional rebar
were provided to accommodate this request.
5. COR-009:
Sheet C101 – SITE PLAN
a. City Staff requested the concrete paving work at the front of the existing building be
completed prior to when the contractor originally scheduled the work. This request was
City of Waukee
July 20, 2022
Page 2 of 2
to accommodate seasonal staff parking and Park & Recreation’s increased customer
traffic in early May. This required the work to be accomplished during the last week of
April when cold temperatures required hot water be added to the concrete and blanket
protection be provided during curing.
We have reviewed the submitted Change Order Requests (CORs) from Core Construction, and the
Design Team considers them to be in line with current industry pricing. If City Staff concurs with these
proposed additional costs, then we recommend the City of Waukee Increase the contract price in the
amount of $9,154.89 to complete the additional work associated with Change Order Number 002. If you
have any questions, please contact me.
Sincerely,
FARNSWORTH GROUP, INC.
Kristofer J. Orth, AIA
Architecture Principal
Enclosures: Change Order #002, dated July 14, 2022
Brad Deets, City Administrator
CHANGE ORDER NO. 2 - SUMMARY
Waukee Public Works - Site Expansion Phase 1
Date:07/14/22
Original Contract Price:$5,922,700.00
Change Orders approved to date:$15,712.16
CHANGE ORDER ITEMS
1)COR-004 Grading at Existing Building by New Paving $2,497.43
2)COR-005 Add (2) Handicapped Accessible Parking Signs $585.75
3)COR-006 Add Galvanized Angles at Bearing Locations in Salt Storage $4,040.61
4)COR-008 Added work at the Sprinkler Room Footing $376.60
5)COR-009 Winter Concrete @ Main Building Concrete Paving $1,654.50
TOTAL Changes:$9,154.89
Amount of this change order:$9,154.89
Adjusted contract price including this change order:$5,947,567.05
14225 University Avenue, Suite 110 | Waukee, IA 50263 | p 515.225.3469 | www.f-w.com
ENGINEERS | ARCHITECTS | SURVEYORS | SCIENTISTS
5.16.2022
Kristofer Orth
14225 University Ave, Suite 110
Waukee IA 50263
RE: 21114 Waukee Public Works-Site Expansion Phase 1 COR-004
Added Grading @ New Paving @ Existing Building
Dear Kristofer:
Core proposes the following as a change in the Work:
Elder Charge for Extra Grading
Proposed change in contract sum ADD $2497.43 if approved by 5.30.22.
Proposed change in schedule 00 days if approved by 5.30.22. Should approval be granted after this deadline, the
schedule shall be extended further beyond the proposed change the same number of days.
An estimate and back up is attached. Please review and authorize one of the actions below. If you have any questions,
please contact me at your earliest convenience. Thank you.
Sincerely,
Jeremy Roush
Project Manager
Cc: Sasha Daljevic
Rudy Koester
Sara Kappos
□ Approved, incorporate change immediately
□ Pending, continue work per current contract
□ Pending, stop affected work until action taken (hold time past deadline above will be added to the proposed
change in schedule)
□ Rejected
The above action is authorized below by a duly authorized representative of the Owner and Architect:
Owner: Architect:
Signature ___________________________________ Signature ___________________________________
Name ______________________________________ Name ______________________________________
Title ________________________________________ Title ________________________________________
Date _______________________________________ Date _______________________________________
COR #004 Core Structural Services, LLC
3093 NW Prairie Lane
Des Moines, IA 50313
(515) 987-6830 Office
(515) 987-6830 Fax
TO: Farnsworth Group PROJECT NAME:
14225 University Ave Suite 110 PROJECT NUMBER:
Waukee IA 50263 SUBJECT:
FROM:
ATTN: Kristofer Orth DATE:
Unit Cost Total Unit Cost Total Unit Cost Total Unit Cost Total
310000.01 Add Site Grading at new paving Elder 7.00 hr $ 1.00 $ 2,345.00 $ 2,345.00
Subtotal -$ -$ -$ 2,345.00$ 2,345.00$
Small Tools Allowance 10.00%
Warranty 2.00% 2.00% 2.00% 0.00%
Overhead & Profit 10.00% 10.00% 10.00% 5.00% $ 117.25 $ 117.25
Bond 1.50% 1.50% 1.50% 1.50% $ 35.18 $ 35.18
The Contract Schedule will Increase / Decrease by:0 days TOTAL COR:
Clarifications & Exclusions:
Waukee Public Works
21114
Grading @ Paving
Jeremy Roush
2,497.43$
5/16/22
Item #/
Cost Code Description Sub/Vendor Quantity Unit
Labor Material Equipment Subcontractor TOTAL
21114.COR-Log.Waukee Public Works.xlsx Page 1
x
5.17.2022
Kristofer Orth
14225 University Ave, Suite 110
Waukee IA 50263
RE: 21114 Waukee Public Works-Site Expansion Phase 1 COR-005
Add 2 new post and handi-cap signs at front of existing building
Dear Kristofer:
Core proposes the following as a change in the Work:
Added Handi-cap signs
Proposed change in contract sum ADD $585.75 if approved by 5.20.22.
Proposed change in schedule 00 days if approved by 5.20.22. Should approval be granted after this deadline, the
schedule shall be extended further beyond the proposed change the same number of days.
An estimate and back up is attached. Please review and authorize one of the actions below. If you have any questions,
please contact me at your earliest convenience. Thank you.
Sincerely,
Jeremy Roush
Project Manager
Cc: Sasha Daljevic
Rudy Koester
Sara Kappos
□ Approved, incorporate change immediately
□ Pending, continue work per current contract
□ Pending, stop affected work until action taken (hold time past deadline above will be added to the proposed
change in schedule)
□ Rejected
The above action is authorized below by a duly authorized representative of the Owner and Architect:
Owner: Architect:
Signature ___________________________________ Signature ___________________________________
Name ______________________________________ Name ______________________________________
Title ________________________________________ Title ________________________________________
Date _______________________________________ Date _______________________________________
COR #005 Core Structural Services, LLC
3093 NW Prairie Lane
Des Moines, IA 50313
(515) 987-6830 Office
(515) 987-6830 Fax
TO: Farnsworth Group PROJECT NAME:
14225 University Ave Suite 110 PROJECT NUMBER:
Waukee IA 50263 SUBJECT:
FROM:
ATTN: Kristofer Orth DATE:
Unit Cost Total Unit Cost Total Unit Cost Total Unit Cost Total
Added Handi Cap Signs 2.00 ea $ 275.00 $ 550.00 $ 550.00
Subtotal -$ -$ -$ 550.00$ 550.00$
Small Tools Allowance 0.00%
Warranty 0.00% 0.00% 0.00% 0.00%
Overhead & Profit 10.00% 10.00% 10.00% 5.00% $ 27.50 $ 27.50
Bond 1.50% 1.50% 1.50% 1.50% $ 8.25 $ 8.25
The Contract Schedule will Increase / Decrease by: days TOTAL COR:
Clarifications & Exclusions:
Waukee Public Works
21114
Add Handi-cap Signs
Jeremy Roush
585.75$
5/17/22
Item #/
Cost Code Description Sub/Vendor Quantity Unit
Labor Material Equipment Subcontractor TOTAL
21114.COR-Log.Waukee Public Works.xlsx Page 1
Parking Lot Specialties, LLC
3040 Gateway Drive
Carlisle, IA 50047
(515) 262-1155
http://www.parkinglotspecialties.com
INVOICE
BILL TO
Core Structural Services
3093 NW Prairie Ln
Des Moines, Iowa 50313
INVOICE #17268
DATE 05/17/2022
TERMS Net 30
JOB NAME/ADDRESS
Waukee Pubic Works
DATE ACTIVITY QTY AMOUNT
05/12/2022 HC Sign
Chop off two existing ada poles with signs and
dispose. Install ADA signs on round galvanized
black powder coated posts
2 550.00
SUBTOTAL 550.00
TAX 0.00
TOTAL 550.00
BALANCE DUE $550.00
5.20.2022
Kristofer Orth
14225 University Ave, Suite 110
Waukee IA 50263
RE: 21114 Waukee Public Works-Site Expansion Phase 1 COR-006
Add Galvanized Angles at Bearing Locations in Salt Storage
Dear Kristofer:
Core proposes the following as a change in the Work:
Add Galvanized Angles at Bearing Locations in Salt Storage
Proposed change in contract sum ADD $4040.61 if approved by 5.30.22.
Proposed change in schedule 00 days if approved by 5.30.22. Should approval be granted after this deadline, the
schedule shall be extended further beyond the proposed change the same number of days.
An estimate and back up is attached. Please review and authorize one of the actions below. If you have any questions,
please contact me at your earliest convenience. Thank you.
Sincerely,
Jeremy Roush
Project Manager
Cc: Sasha Daljevic
Rudy Koester
Sara Kappos
□ Approved, incorporate change immediately
□ Pending, continue work per current contract
□ Pending, stop affected work until action taken (hold time past deadline above will be added to the proposed
change in schedule)
□ Rejected
The above action is authorized below by a duly authorized representative of the Owner and Architect:
Owner: Architect:
Signature ___________________________________ Signature ___________________________________
Name ______________________________________ Name ______________________________________
Title ________________________________________ Title ________________________________________
Date _______________________________________ Date _______________________________________
COR #006 Core Structural Services, LLC
3093 NW Prairie Lane
Des Moines, IA 50313
(515) 987-6830 Office
(515) 987-6830 Fax
TO: Farnsworth Group PROJECT NAME:
14225 University Ave Suite 110 PROJECT NUMBER:
Waukee IA 50263 SUBJECT:
FROM:
ATTN: Kristofer Orth DATE:
Unit Cost Total Unit Cost Total Unit Cost Total Unit Cost Total
51223 Material JMW $ 1.00 $ 3,086.00 $ 3,086.00
51223 Labor to Install Ace $ 1.00 $ 708.00 $ 708.00
Subtotal -$ 3,086.00$ -$ 708.00$ 3,794.00$
Small Tools Allowance 0.00%
Warranty 0.00% 0.00% 0.00% 0.00%
Overhead & Profit 5.00% 5.00% $ 154.30 0.00% 5.00% $ 35.40 $ 189.70
Bond 1.50% 1.50% $ 46.29 1.50% 1.50% $ 10.62 $ 56.91
The Contract Schedule will Increase / Decrease by: days TOTAL COR:
Clarifications & Exclusions:
Labor Material Equipment Subcontractor TOTALItem #/
Cost Code Description Sub/Vendor Quantity Unit
Waukee Public Works
21114
Added Galvanized Angle
Jeremy Roush
4,040.61$
5/20/22
21114.COR-Log.Waukee Public Works.xlsx Page 1
To: Jeremy Roush
From Scott See
Date:March 24, 2022
Project Waukee Public Works
JMW SO 21-4223-01
Contract 21114.02
Item - ADD Cost
The addition of 120'-0 of galvanized HSS 5x3x3/16 for deck 3,086.00$
bearing on top of beams at salt room-not shown in contract drawings
2 - continous 3/8 bearing plates in top of mezzanine walls - not shown
not shown in contract drawings
SubTotal 3,086.00$
Sales Tax
Grand Total 3,086.00$
Price valid for 30 days
This is a notification only, a separate invoice will follow
I hereby authorize Johnson Machine Works to perform the work indicated above
I acknowledge that the work indicated above has been performed.
Company Name:
Signature:Date:
Scope of Work Deviation No X002
318 North Eleventh Street, Chariton, Iowa 50049-0251
(641) 774-2191 www.jmworks.com
1
jeremyr@coreconstructionia.com
From:Acey Jr Haroldson <acejr@acesteelconstructioninc.com>
Sent:Thursday, May 19, 2022 9:17 AM
To:Jeremy Roush
Subject:Re: urbandale
We would add $558 for labor to install and $150 for half day boom lift for a total of $708 for the added tube steel install.
Acey Haroldson, Jr.
Ace Construction, Inc.
4305 SE Grimes Blvd.
Grimes, Iowa 50111
Phone: 515-986-4479
Fax: 515-986-3703
On Thu, May 19, 2022 at 8:33 AM <jeremyr@coreconstructionia.com> wrote:
Here you go.
Note my email address has changed please update my contact info
Jeremy Roush
Project Manager / Estimator
3093 NW Prairie Ln, Des Moines IA 50313
Office 515/264-5156 x204 Cell 515/419-3700
Fax 515/257-4311
From: Acey Jr Haroldson <acejr@acesteelconstructioninc.com>
Sent: Thursday, May 19, 2022 7:31 AM
2
To: Jeremy Roush <jeremyr@coreconstructionia.com>
Subject: urbandale
Jeremy, I thought I printed off sheet E2 but it was actually E1 and then deleted. could you resend the mail with the
drawings and ill review the ledge angle situation this morning, thanks
Acey Haroldson, Jr.
Ace Construction, Inc.
4305 SE Grimes Blvd.
Grimes, Iowa 50111
Phone: 515-986-4479
Fax: 515-986-3703
7.05.2022
Kristofer Orth
14225 University Ave, Suite 110
Waukee IA 50263
RE: 21114 Waukee Public Works-Site Expansion Phase 1 COR-008
Added work at the Sprinkler Room Footing
Dear Kristofer:
Core proposes the following as a change in the Work:
Provide labor and material to isolate the Sprinkler Main
Proposed change in contract sum ADD $376.60 if approved by 7.15.22.
Proposed change in schedule 00 days if approved by 7.15.22. Should approval be granted after this deadline, the
schedule shall be extended further beyond the proposed change the same number of days.
An estimate and back up is attached. Please review and authorize one of the actions below. If you have any questions,
please contact me at your earliest convenience. Thank you.
Sincerely,
Jeremy Roush
Project Manager
Cc: Sasha Daljevic
Rudy Koester
Sara Kappos
□ Approved, incorporate change immediately
□ Pending, continue work per current contract
□ Pending, stop affected work until action taken (hold time past deadline above will be added to the proposed
change in schedule)
□ Rejected
The above action is authorized below by a duly authorized representative of the Owner and Architect:
Owner: Architect:
Signature ___________________________________ Signature ___________________________________
Name ______________________________________ Name ______________________________________
Title ________________________________________ Title ________________________________________
Date _______________________________________ Date _______________________________________
1
jeremyr@coreconstructionia.com
From:genes@coreconstructionia.com
Sent:Friday, June 24, 2022 11:14 AM
To:jeremyr@coreconstructionia.com; stevek@coreconstructionia.com
Subject:RE: Sprinkler ordeal
Flag Status:Flagged
Jeremy
Setting extra and stripping the two bulkheads, estimate 4.5 hours, cutting and replacing the bar per engineer 1 hour
total of 5.5 hours.
Not My Email Address Has Changed Please Update My Contact Info
Gene Schmitz
Superintendent
3093 NW Prairie Ln, Des Moines IA 50313
Office 515/264-5156 Cell 515/205-8001 FAX 515/257-4311
From: jeremyr@coreconstructionia.com <jeremyr@coreconstructionia.com>
Sent: Friday, June 24, 2022 10:01 AM
To: 'Gene Schmitz' <genes@coreconstructionia.com>; stevek@coreconstructionia.com
Subject: Sprinkler ordeal
How many extra hours did we having dicking with this? Form time? I have the materials from Logan and Carroll.
Note my email address has changed please update my contact info
Jeremy Roush
Project Manager / Estimator
3093 NW Prairie Ln, Des Moines IA 50313
Office 515/264-5156 x204 Cell 515/419-3700
Fax 515/257-4311
COR #008 Core Structural Services, LLC
3093 NW Prairie Lane
Des Moines, IA 50313
(515) 987-6830 Office
(515) 987-6830 Fax
TO: Farnsworth Group PROJECT NAME:
14225 University Ave Suite 110 PROJECT NUMBER:
Waukee IA 50263 SUBJECT:
FROM:
ATTN: Kristofer Orth DATE:
Unit Cost Total Unit Cost Total Unit Cost Total Unit Cost Total
Footing change at sprinkler room
30000.002 Rebar Logans 30 $ 0.79 $ 23.70 $ 23.70
30000.002 Void form per Waukee Fire Marshall Carroll 1 $ 33.56 $ 33.56
30000.002 Labor to install Core 6 $ 51.00 $ 280.50 $ 280.50
Subtotal 280.50$ 57.26$ -$ -$ 337.76$
Small Tools Allowance 0.00%
Warranty 0.00% 0.00% 2.00% 2.00%
Overhead & Profit 10.00% $ 28.05 10.00% $ 5.73 10.00% 5.00% $ 33.78
Bond 1.50% $ 4.21 1.50% $ 0.86 1.50% 1.50% $ 5.07
The Contract Schedule will Increase / Decrease by: days TOTAL COR:
Clarifications & Exclusions:
Labor Material Equipment Subcontractor TOTALItem #/
Cost Code Description Sub/Vendor Quantity Unit
Waukee Public Works
21114
Footing @ Sprinkler
Jeremy Roush
376.60$
7/5/22
21114.COR-Log.Waukee Public Works.xlsx Page 1
7.06.2022
Kristofer Orth
14225 University Ave, Suite 110
Waukee IA 50263
RE: 21114 Waukee Public Works-Site Expansion Phase 1 COR-009
Winter Concrete @ Main Building
Dear Kristofer:
Core proposes the following as a change in the Work:
Provide labor and material for concrete paving
Proposed change in contract sum ADD $1654.50 if approved by 7.20.22.
Proposed change in schedule 00 days if approved by 7.20.22. Should approval be granted after this deadline, the
schedule shall be extended further beyond the proposed change the same number of days.
An estimate and back up is attached. Please review and authorize one of the actions below. If you have any questions,
please contact me at your earliest convenience. Thank you.
Sincerely,
Jeremy Roush
Project Manager
Cc: Sasha Daljevic
Rudy Koester
Sara Kappos
□ Approved, incorporate change immediately
□ Pending, continue work per current contract
□ Pending, stop affected work until action taken (hold time past deadline above will be added to the proposed
change in schedule)
□ Rejected
The above action is authorized below by a duly authorized representative of the Owner and Architect:
Owner: Architect:
Signature ___________________________________ Signature ___________________________________
Name ______________________________________ Name ______________________________________
Title ________________________________________ Title ________________________________________
Date _______________________________________ Date _______________________________________
COR #009 Core Structural Services, LLC
3093 NW Prairie Lane
Des Moines, IA 50313
(515) 987-6830 Office
(515) 987-6830 Fax
TO: Farnsworth Group PROJECT NAME:
14225 University Ave Suite 110 PROJECT NUMBER:
Waukee IA 50263 SUBJECT:
FROM:
ATTN: Kristofer Orth DATE:
Unit Cost Total Unit Cost Total Unit Cost Total Unit Cost Total
Winter Concrete @ Main Building
320013 Concrete Charges / Blanket Concrete Jordison $ 1.00 $ 1,654.50 $ 1,654.50
Subtotal -$ -$ -$ 1,654.50$ 1,654.50$
Small Tools Allowance 0.00%
Warranty 0.00% 0.00% 0.00% 0.00%
Overhead & Profit 0.00% 0.00% 0.00% 5.00% $ 82.73 $ 82.73
Bond 1.50% 1.50% 1.50% 1.50% $ 24.82 $ 24.82
The Contract Schedule will Increase / Decrease by: days TOTAL COR:
Clarifications & Exclusions:
Waukee Public Works
21114
Winter Concrete
Jeremy Roush
1,762.04$
7/6/22
Item #/
Cost Code Description Sub/Vendor Quantity Unit
Labor Material Equipment Subcontractor TOTAL
21114.COR-Log.Waukee Public Works.xlsx Page 1