HomeMy WebLinkAbout2022-09-06 J01G_01 NW Meredith Dr Overlay, NW 10th St to N Warrior Ln_Change Order 1AGENDA ITEM: CITY OF WAUKEE, IOWA CITY COUNCIL MEETING COMMUNICATION MEETING DATE: September 6, 2022 AGENDA ITEM:Consideration of approval of Change Order No. 1 to InRoads Paving for the NW Meredith Dr Overlay, NW 10th Street to N. Warrior Lane Project increasing the contract amount by $5,958.41. FORMAT:Consent Agenda SYNOPSIS INCLUDING PRO & CON: Change Order No. 1 is for field tile repair and adjustments to final bid values to match actual as-built quantities installed in the field. FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS: The net result of this Change Order increases the contract price in the amount of $5,958.41. COMMISSION/BOARD/COMMITTEE COMMENT: STAFF REVIEW AND COMMENT: RECOMMENDATION: Approve the change order. ATTACHMENTS: I. Change Order No. 1 II. Letter of Recommendation PREPARED BY:Beth Richardson REVIEWED BY:Rudy Koester RK PUBLIC NOTICE INFORMATION – NAME OF PUBLICATION: DATE OF PUBLICATION: J1G1 8191 Birchwood Court, Suite L Johnston, IA 50131 Phone: (515) 254-1393 August 31, 2022 Sara Kappos, P.E. Assistant Public Works Director 805 University Avenue Waukee, IA 50263 RE: Change Order #1 NW Meredith Dr Overlay – NW 10th Street to N. Warrior Lane Dear Ms. Kappos: Attached please find a detailed Change Order for City Council approval on September 19, 2022 Change Description: • Item CO 4.3 T&M for Field Tile Repair o A field tile was encountered while digging the culvert under Meredith at Sta 352+90 Rt. T&M tracked for the repair of the 12" tile. • Adjustments to final bid values to match a ctual as-built quantities installed in the field. We have reviewed the submitted quotes from InRoads and they appear to be in order with current industry pricing. If City Staff concurs with this pricing, we recommend the City of Waukee Increase the contract price in the amount of $5,958.41to complete the additional work associated with Change Order #1. If you have any questions, please contact me. Sincerely, Foth Infrastructure & Environment, LLC Rob Kline, P.E. Lead Civil Engineer Encl: Change Order #1 dated 8/31/2022 CHANGE ORDER 01 Distribution: Owner - Finance ____ Owner - Public Works ____ Engineer ____ Contractor ____ Contractor:InRoads Paving 4224 Hubbell Avenue Des Moines, Iowa 50317 $638,555.30 May 19, 2022 2.3 TON $160.00 -17.12 ($2,739.20) CO 4.3 LS $5,354.04 1.00 $5,354.04 7.1 TON $81.00 -35.89 ($2,907.09) 7.2 TON $85.00 -111.83 ($9,505.55) 7.3 TON $89.00 106.07 $9,440.23 7.5 TON $50.00 1.52 $76.00 7.7 TON $32.50 28.44 $924.30 8.1 STA $60.00 -7.04 ($422.40) 8.2 STA $23.00 -7.04 ($161.92) 8.4 CDAY $125.00 22.00 $2,750.00 9.1 AC $15,500.00 0.10 $1,550.00 9.2 TON $100.00 30.00 $3,000.00 9.3 LF $4.00 -200.00 ($800.00) 9.4 LF $1.00 -200.00 ($200.00) 9.5 LF $2.00 -200.00 ($400.00) $5,958.41 $638,555.30 $0.00 $638,555.30 $5,958.41 $644,513.71 0 Days Recommended By: InRoads Paving Signature: Name: Bill Rosener Title: Project Manager Date: Owner:City of Waukee □ ≤$500 Department Director X_______________________________________Date___________________ □ $501 to $2,500 City Administrator X_______________________________________Date___________________ □ Date___________________ □ >$2,501 City Council approved or ratified at Council meeting on Date___________________ 9010-A-1100 CONVENTIONAL SEEDING & FERTILIZING, TYPE 2 (PERMANENT COOL-SEASON MIX) 9040-N-2000 HMA PAVEMENT, STANDARD TRAFFIC, SURFACE COURSE, 1/2" MIX DRIVEWAY, GRANULAR, CLASS A CRUSHED STONE GRANULAR SHOULDERS, TYPE B PAINTED PAVEMENT MARKINGS, DURABLE SILT FENCE OR SILT FENCE DITCH CHECK, REMOVAL OF SEDIMENT 9040-J-1000 SILT FENCE OR SILT FENCE DITCH CHECK9040-N-1000 RIP RAP Project Title THE CONTRACT IS CHANGED AS FOLLOWS: A field tile was encountered while digging the culvert under Meredith at Sta 352+90 Rt. T&M tracked for the repair of the 12" tile. Also included is the final adjustment change order to match as-built quantities. Item Code NW Meredith Drive Overlay NW 10th Street to N. Warrior Lane 1 21W028.01 Waukee Project File Number Item No. August 31, 2022 Department of Public Works 805 University Avenue Waukee, IA 50263 (515) 987-7920 Fax (515) 987-3979 Unit Foth Project File Number Orig. Contract Amount & Date Date Change Order Number Date: Name: Brad Deets Checked By: Prepared By: Date: The Contract Time will be increased by CHANGE ORDER SUMMARY NOT VALID UNTIL SIGNED BY THE CONTRACTOR, OWNER'S REPRESENTATIVE (if applicable) AND OWNER The Original Contract Sum was Value Adjustment The new Contract Sum including this Change Order will be Signature: Quantity AdjustmentUnit Price Name: Rob Kline, P.E. City of Waukee 9040-N-3000 Description SILT FENCE OR SILT FENCE DITCH CHECK, REMOVAL OF DEVICE Title: Lead Civil Engineer Signature: The Contract Sum will be increased by this Change Order in the amount of Net Change by previously authorized Change Orders Title: City Administrator Foth Infrastructure & Environment, LLC The Contract Sum prior to This Change Order was T&M FOR FIELD TILE REPAIR 8020-M-1000 GROOVES CUT FOR PAVEMENT MARKINGS 7020-A-1010 HMA PAVEMENT, STANDARD TRAFFIC, INTERMEDIATE COURSE, 1/2" MIX 7020-A-1020 2010-I-1008 SUBGRADE TREATMENT, 6% CEMENT 7020-A-1000 HMA PAVEMENT, STANDARD TRAFFIC, BASE COURSE, 3/4" MIX SPECIAL PORTABLE DYNAMIC MESSAGE SIGNS 7030-A-1020 SPECIAL 8020-C-1000 SPECIAL CO#01-2022-0810- Waukee Meredith Dr Overlay.xls Change Order 1 Page 1 of 1