AGENDA ITEM:Consideration of approval of Payment Estimate No. 2 (Final) to NPL
Construction Co. for the 170th Street Transmission Line Relocation
Phase 2, in the amount of $87,904.82.
FORMAT:Consent Agenda
SYNOPSIS INCLUDING PRO & CON: NPL Construction Co. requested Payment Estimate
No. 2 (Final) for the work completed on the 170th Street Transmission Line Relocation Phase 2
Project, in the amount of $87,904.82. USDI has reviewed the payment estimate and recommends
payment.
The partial payment is for the pay period ending July 29, 2022. This pay estimate is for lowering
of remaining gas main pipe as part of this project.
FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS: $87,904.82
COMMISSION/BOARD/COMMITTEE COMMENT:
STAFF REVIEW AND COMMENT:
RECOMMENDATION: Approve Payment Estimate No. 2 (Final)
ATTACHMENTS: I. Payment Estimate No. 2 (Final)
II. Letter of Recommendation
PREPARED BY:Beth Richardson
REVIEWED BY:Tim Royer TLR
PUBLIC NOTICE INFORMATION –
NAME OF PUBLICATION:
DATE OF PUBLICATION:
J1G3
OLNEY, ILLINOIS
1927 Miller Drive
Olney, IL 62450
(618) 392-5502
BELLEVILLE, IL
9 Executive Woods Ct.
Belleville, IL 62226
(618) 277-1520
SHELBYVILLE, KY
1018 Mt. Vernon Dr.
Shelbyville, KY 40065
(502) 513-5127
WICHITA, KS
9540 W. Harry St.
Wichita, KS 67209
(316) 239-7313
PITTSBORO, IN
7421 N. Co Rd. 225 E.
Pittsboro, IN 46167
(317) 892-7662
Utility Safety & Design, Inc.
28847 US HWY 136
Unionville, MO 63565
P (660) 947-3316 Fax (660) 947-3146
www.usdi.us
August 22, 2022
Mr. Tim Royer, Assistant Dir. of Public Works
City of Waukee
805 University Avenue
Waukee, IA 50263
troyer@waukee.org
RE: 170th Street Transmission Line Relocation Phase 2 – Final Pay App
Dear Mr. Royer,
Please find attached hereto one copy of the final pay application from NPL Construction
Company for the above referenced project. The amount requested is $87,904.82 and the
accepted quotation for the project including Change Order #1 & #2 is $170,855.40. A previous
payment of $82,950.58 was made on August 16, 2021. The project was completed July 29, 2022
as requested by the City of Waukee.
I recommend the payment of $87,904.82, leaving no remaining balance owed. Please feel free
to contact me anytime if you have any questions or require additional information.
Respectfully Submitted,
Anthony Everette, P.E.
Senior Vice-President
USDI
Attach: As noted
Cc: NPL Construction Co.
City of Waukee, IA Page 2 of 3
170th Transmission Line Relocation Phase 2
Final Payment Estimate #2
Item
No.Description Unit Bid Price
Bid
Quantity Bid Total Cost Change
Order + or -
Adjusted
Quantity
Adjusted Total
Cost Quantity Total Cost Quantity Total Cost Percent
Complete
1 Pipe Lowering LS $ 129,583.00 1 $ 129,583.00 - 1 129,583.00$ 0.58 75,404.82$ 1 129,583.00$ 100%
2 CO1 Additional Footage Lowered EA $ 77.60 - $ - - 324 25,142.40$ - -$ 324 25,142.40$ 100%
3 CO1 Coating Repairs & Misc.EA $ 3,630.00 - $ - - 1 3,630.00$ - -$ 1 3,630.00$ 100%
4 CO2 Mobilization & Demobilization LS $ 12,500.00 - $ - - 1 12,500.00$ 1 12,500.00$ 1 12,500.00$ 100%
$ 129,583.00 $ 170,855.40 $ 87,904.82 $ 170,855.40
This Period Total to Date
Page 3 of 3
1.
2.
NO. DATE AMOUNT
1 7/23/2021 $28,772.40
2 6/1/2022 $12,500.00
3.
4.
5.PREVIOUS PAY ESTIMATES
NO. DATE AMOUNT
1 8/16/2021 82,950.58$
6.$0.00BALANCE TO FINISH INC. RETAINAGE (3-4-5)……………….
PARTIAL PAYMENT ESTIMATE NO. 2
CONTRACT SUMMARY
ORIGINAL CONTRACT AMOUNT……………………….
CHANGE ORDERS
TOTAL PREVIOUS PAY ESTIMATES………………………………….
TOTAL THIS PAY ESTIMATE……………..……………………………..
REVISED CONTRACT AMOUNT (2+3)……………………………..
NET CHANGE BY CHANGE ORDERS………………………………..
$129,583.00
$41,272.40
$170,855.40
$87,904.82
$82,950.58