HomeMy WebLinkAbout2022-09-06 J09 Little Walnut Creek Sanitary Sewer Extension Phase 5_Change Order 1AGENDA ITEM: CITY OF WAUKEE, IOWA CITY COUNCIL MEETING COMMUNICATION MEETING DATE: September 6, 2022 AGENDA ITEM:Consideration of approval of Change Order No. 1 to J&K Contracting, LLC for Little Walnut Creek Trunk Sewer Extension – Phase 5 Project increasing the contract amount by $133,952.00. FORMAT:Motion SYNOPSIS INCLUDING PRO & CON: Change Order No. 1 is for the use of trenchless sanitary sewer installation methods in an area with limited space for open cut. The reasons for the change order is to ensure NW 10th St street pavement is protected, safety for the general public and the contractor and to ensure the project remains on schedule. While excavating at nearly 35- ft deep, the underlying soil conditions quickly deteriorated and the original intentions to open trench this section of sanitary sewer on the East side of NW 10th St could not be done safety and efficiently. The City is taking on approximately 45% of the cost and the Contractor is taking on the remaining 55% of the total change order amount (approximately $470K). FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS: The net result of this Change Order increases the contract price in the amount of $133,952.00. COMMISSION/BOARD/COMMITTEE COMMENT: STAFF REVIEW AND COMMENT: RECOMMENDATION: Approve the change order. ATTACHMENTS: I. Change Order No. 1 II. Letter of Recommendation PREPARED BY:Beth Richardson REVIEWED BY:Rudy Koester RK PUBLIC NOTICE INFORMATION – NAME OF PUBLICATION: DATE OF PUBLICATION: J9 August 29, 2022 Rudy Koester Director of Public Works City of Waukee 805 University Avenue Waukee, Iowa 50263 WAUKEE, IOWA LITTLE WALNUT CREEK TRUNK SEWER EXTENSION – PHASE 5 CHANGE ORDER NO. 1 Enclosed are three copies of executed Change Order No. 1 for work on the Little Walnut Creek Trunk Sewer Extension – Phase 5 project, under the contract between the City of Waukee and J&K Contracting, LLC. Please sign all copies of Change Order No. 1 in the space provided and return one signed copy of the change order to our office. Please forward one signed copy of Change Order No. 1 to J&K Contracting, LLC. Change Order No. 1 is for the use of trenchless sanitary sewer installation methods in an area with limited space for open cut. If you have any questions, please contact us at 515-225-8000. VEENSTRA & KIMM, INC. Andy Willcuts ARW:paj 275348 Enclosures cc: J&K Contracting, LLC Sara Kappos, City of Waukee – w/enclosure (email) Becky Schuett, City of Waukee – w/enclosure (email) Beth Richardson, City of Waukee – w/enclosure (email) Rachel Bruns, City of Waukee – w/enclosure (email) Tracy Lovetinsky, City of Waukee – w/enclosure (email) 275348 Page 1 of 1 August 29, 2022 CHANGE ORDER NO. 1 WAUKEE, IOWA LITTLE WALNUT CREEK TRUNK SEWER EXTENSION – PHASE 5 Change Order No. 1 is to document modifications to the construction contract for the Little Walnut Creek Trunk Sewer Extension – Phase 5 project. Item Description Unit Quantity Unit Price Total Price 1.12 24” Sanitary Sewer in Place LF -416 $185.00 ($76,960.00) 2.1 24” Sanitary Sewer Augered in Place in Steel Casing LF +416 $507.00 $210,912.00 $133,952.00 Change Order No. 1 increases the contract price by a total of $133,952.00. J&K Contracting, LLC CITY OF WAUKEE, IOWA By By Title Title Date Date VEENSTRA & KIMM, INC. ATTEST: By By Title Project Engineer Title Date Date Your Company Name Change Request Your Company Slogan DATE:8/1/2022 10703 Justin Drive Urbandale, IA 50322 CR #1 Phone 515-233-5500 FOR: Fax 515-278-2351 Bill To: City of Waukee Attn: Sara Kappos AMOUNT 210,912.00 DEDUCT 416 LF of 24" Santiary Sewer Open Cut @ $185/LF (76,960.00) TOTAL 133,952.00$ If you have any questions concerning this request, please contact us directly at 515-233-5500. Little Walnut Phase 5 ADD 416 LF of 24" Sanitary Sewer in 36" Steel Casing @ $507/LF DESCRIPTION Change request to replace 416 Lf of open cut 24" Sanitary Sewer with 416 LF of auger bore 24" Sanitary Sewer in 36" steel casing THANK YOU FOR YOUR BUSINESS!