CITY OF WAUKEE, IOWA
CITY COUNCIL MEETING COMMUNICATION
MEETING DATE: September 6, 2022
AGENDA ITEM:Consideration of approval of Change Order No. 1 to J&K Contracting,
LLC for Little Walnut Creek Trunk Sewer Extension – Phase 5 Project
increasing the contract amount by $133,952.00.
FORMAT:Motion
SYNOPSIS INCLUDING PRO & CON: Change Order No. 1 is for the use of trenchless
sanitary sewer installation methods in an area with limited space for open cut. The reasons for the
change order is to ensure NW 10th St street pavement is protected, safety for the general public
and the contractor and to ensure the project remains on schedule. While excavating at nearly 35-
ft deep, the underlying soil conditions quickly deteriorated and the original intentions to open
trench this section of sanitary sewer on the East side of NW 10th St could not be done safety and
efficiently. The City is taking on approximately 45% of the cost and the Contractor is taking on
the remaining 55% of the total change order amount (approximately $470K).
FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS: The net result of this
Change Order increases the contract price in the amount of $133,952.00.
COMMISSION/BOARD/COMMITTEE COMMENT:
STAFF REVIEW AND COMMENT:
RECOMMENDATION: Approve the change order.
ATTACHMENTS: I. Change Order No. 1
II. Letter of Recommendation
PREPARED BY:Beth Richardson
REVIEWED BY:Rudy Koester RK
PUBLIC NOTICE INFORMATION –
NAME OF PUBLICATION:
DATE OF PUBLICATION:
J9
August 29, 2022
Rudy Koester
Director of Public Works
City of Waukee
805 University Avenue
Waukee, Iowa 50263
WAUKEE, IOWA
LITTLE WALNUT CREEK TRUNK SEWER EXTENSION – PHASE 5
CHANGE ORDER NO. 1
Enclosed are three copies of executed Change Order No. 1 for work on the Little Walnut Creek Trunk
Sewer Extension – Phase 5 project, under the contract between the City of Waukee and J&K
Contracting, LLC.
Please sign all copies of Change Order No. 1 in the space provided and return one signed copy of the
change order to our office. Please forward one signed copy of Change Order No. 1 to J&K Contracting,
LLC.
Change Order No. 1 is for the use of trenchless sanitary sewer installation methods in an area with
limited space for open cut.
If you have any questions, please contact us at 515-225-8000.
VEENSTRA & KIMM, INC.
Andy Willcuts
ARW:paj
275348
Enclosures
cc: J&K Contracting, LLC
Sara Kappos, City of Waukee – w/enclosure (email)
Becky Schuett, City of Waukee – w/enclosure (email)
Beth Richardson, City of Waukee – w/enclosure (email)
Rachel Bruns, City of Waukee – w/enclosure (email)
Tracy Lovetinsky, City of Waukee – w/enclosure (email)
275348 Page 1 of 1
August 29, 2022 CHANGE ORDER NO. 1
WAUKEE, IOWA
LITTLE WALNUT CREEK TRUNK SEWER EXTENSION – PHASE 5
Change Order No. 1 is to document modifications to the construction contract for the Little
Walnut Creek Trunk Sewer Extension – Phase 5 project.
Item Description Unit Quantity Unit Price Total Price
1.12 24” Sanitary Sewer in Place LF -416 $185.00 ($76,960.00)
2.1 24” Sanitary Sewer Augered
in Place in Steel Casing
LF
+416
$507.00
$210,912.00
$133,952.00
Change Order No. 1 increases the contract price by a total of $133,952.00.
J&K Contracting, LLC CITY OF WAUKEE, IOWA
By By
Title Title
Date Date
VEENSTRA & KIMM, INC. ATTEST:
By By
Title Project Engineer Title
Date Date
Your Company Name Change Request
Your Company Slogan
DATE:8/1/2022
10703 Justin Drive
Urbandale, IA 50322 CR #1
Phone 515-233-5500 FOR:
Fax 515-278-2351
Bill To: City of Waukee Attn: Sara Kappos
AMOUNT
210,912.00
DEDUCT 416 LF of 24" Santiary Sewer Open Cut @ $185/LF (76,960.00)
TOTAL 133,952.00$
If you have any questions concerning this request, please contact us directly at 515-233-5500.
Little Walnut Phase
5
ADD 416 LF of 24" Sanitary Sewer in 36" Steel Casing @ $507/LF
DESCRIPTION
Change request to replace 416 Lf of open cut 24" Sanitary Sewer with 416 LF of
auger bore 24" Sanitary Sewer in 36" steel casing
THANK YOU FOR YOUR BUSINESS!