CITY OF WAUKEE, IOWA
CITY COUNCIL MEETING COMMUNICATION
MEETING DATE: September 19, 2022
AGENDA ITEM:Consideration of approval of Change Order No. 2 to Absolute Concrete
Construction, Inc. for the Warrior Lane Improvements – Phase 2 project
increasing the contract amount by $2,024.00.
FORMAT:Consent Agenda
SYNOPSIS INCLUDING PRO & CON: Change Order No. 2 is for the crosswalk signal
concrete base. The existing rectangular rapid-flashing beacon crosswalk signals on Warrior Lane
were salvaged to be reinstalled between Waukee Middle School and Waukee Public Library at
the new crosswalk location. The existing screw-in base could not be used due to an obstruction
underground, so a new cast-in-place concrete footing will be utilized instead.
FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS: The net result of this
Change Order increases the contract price in the amount of $2,024.00.
COMMISSION/BOARD/COMMITTEE COMMENT:
STAFF REVIEW AND COMMENT:
RECOMMENDATION: Approve the change order.
ATTACHMENTS: I. Change Order No. 2
II. Letter of Recommendation
PREPARED BY:Beth Richardson
REVIEWED BY:Sara Kappos SKK
PUBLIC NOTICE INFORMATION –
NAME OF PUBLICATION:
DATE OF PUBLICATION:
I1F5
S-H Project No.: 4203290
September 13, 2022
Rudy Koester, Public Works Director
City of Waukee
805 University Avenue
Waukee, IA 50263
RE: Change Order #2 – Review and Recommendation to Approve
Warrior Lane Improvements - Phase 2
Dear Mr. Koester:
Please find attached Change Order #1 for the Warrior Lane Improvements - Phase 2 project. The
change order includes the following items:
• Crosswalk Signal Concrete Base
The existing rectangular rapid-flashing beacon crosswalk signals on Warrior Lane were salvaged to be
reinstalled between Waukee Middle School and Waukee Public Library at the new crosswalk location.
The existing screw-in base could not be used due to an obstruction underground, so a ne w cast-in-
place concrete footing will be utilized instead.
We have reviewed the change order items and unit prices, and both are in line with anticipated
amounts. If City staff concurs with this change, we recommend the City of Waukee approve this change
order in the amount of $2,024.00 to the construction contract for the Warrior Lane Improvements –
Phase 2 with Absolute Concrete Construction, Inc. of Slater, IA.
Sincerely,
SHIVE-HATTERY, INC.
Blake T. Peterson, PE
Civil Engineer
Enc. Change Order #2
CITY OF WAUKEE
230 W HICKMAN ROAD
WAUKEE, IOWA 50263
Contractor:
1000 W. 6th Avenue
Slater, IA 50244 $2,536,969.55 02/22/22
CO-2.1 EA $ 2,024.00 1.00 $ 2,024.00
$ 2,024.00
$2,536,969.55
$12,630.58
$2,549,600.13
$2,024.00
$2,551,624.13
0.58%
0 Days
0 Days
0 Days
August 12, 2022
November 18, 2022
May 31, 2023
Date:
Approved By:
City of Waukee
Signature:
Name:
Title:
Date:
Recommended By:
Shive-Hattery Inc.
Signature:
Name:
Title: Title:
Date:
Warrior Lane Improvements - Phase 2
4203290
Net Change by previously authorized Change Orders
The Contract Sum prior to This Change Order was
The Contract Sum will be increased by this Change Order in the amount of
The new Contract Sum including this Change Order will be
Description
THE CONTRACT IS CHANGED AS FOLLOWS:
Change Order Item CO-2.1 is to add a 24-inch by 24-inch cast-in-place concrete footing for the reinstallation of the western existing rectangular rapid-flashing beacon signal due to
an underground obstruction preventing use of the existing screw-in type base.
Item Value Adjustment
CHANGE ORDER SUMMARY
Quantity AdjustmentUnit Price
Contractor:
Absolute Concrete Construction, Inc.
Absolute Concrete Construction, Inc.
Signature:
Name:
The date of Stages 1 & 2 Completion as of the date of this Change Order therefore is
The Landscaping/Site Restoration/Final Completion Contract Time will be changed by
The Grading/Utility/Paving Contract Time will be changed by
The date of Grading/Utility/Paving Completion as of the date of this Change Order therefore is
CHANGE ORDER
Aggregate Change Order as a percent of Original Contract
The date of Landscaping/Site Restoration/Final Completion as of the date of this Change Order therefore is
NOT VALID UNTIL SIGNED BY THE CONTRACTOR, OWNER'S REPRESENTATIVE (if applicable) AND OWNER
Project Title
S-H Project File Number
Orig. Contract Amount & Date
Change Order Number
Date
2
The Stages 1 & 2 Contract Time will be changed by
TOTAL
The Original Contract Sum was
Unit
August 15, 2022
CROSSWALK SIGNAL CONCRETE BASE
P:\Projects\DM\4203290\Construction\_Warrior Lane Phase 2\CASupport\Change Orders\02\ChangeOrder02_Warrior Lane Phase 2.xlsx
1 of 1