HomeMy WebLinkAbout2022-10-03 J01H_03 Public Works 2nd Floor Expansion_Change Order 1AGENDA ITEM:
CITY OF WAUKEE, IOWA
CITY COUNCIL MEETING COMMUNICATION
MEETING DATE: October 3, 2022
AGENDA ITEM:Consideration of approval of Change Order No. 1 to Core Construction
Services for the Waukee Public Works 2nd Floor Expansion project
increasing the contract amount by $2,611.11.
FORMAT:Consent Agenda
SYNOPSIS INCLUDING PRO & CON: Change Order No. 1 is for sealing vinyl composition
tile, provide & install expansion cover at existing floor joint, and white maple doors in lieu of oak
to match existing doors.
FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS: The net result of this
Change Order increases the contract price in the amount of $2,611.11.
COMMISSION/BOARD/COMMITTEE COMMENT:
STAFF REVIEW AND COMMENT:
RECOMMENDATION: Approve the change order.
ATTACHMENTS: I. Change Order No. 1
II. Letter of Recommendation
PREPARED BY:Beth Richardson
REVIEWED BY:Sara Kappos SKK
PUBLIC NOTICE INFORMATION –
NAME OF PUBLICATION:
DATE OF PUBLICATION:
J1H3
ENGINEERS | ARCHITECTS | SURVEYORS | SCIENTISTS
14225 University Avenue, Suite 110
Waukee, Iowa 50263
p 515.225.3469
www.f-w.com
September 16, 2022
City of Waukee
805 University Avenue
Waukee, Iowa 50263
Attn: Rudy Koester, Public Works Director
Re: Change Order #001
Waukee Public Works 2nd Floor Expansion
Dear Mr. Koester:
Attached please find a detailed Change Order for City Council approval on October 3, 2022.
Change Description:
1. COR-003
a. Seal new Vinyl Composition Tile (VCT) flooring with the product used by the owner on
their existing VCT floors. This additional work was requested by city staff so it could be
accomplished during the construction sequence and prior to furniture installation.
2. COR-004
a. Provide & Install Expansion Cover at existing floor joint. Following removal of carpet the
Vinyl Composition Tile flooring installer expressed concerns about spanning over an
existing expansion joint in the concrete floor system as it will likely result in cracking and
reduced life expectancy of the new VCT flooring. This existing expansion joint was
concealed by the existing carpet and is considered an unforeseen condition. The
proposed cover will provide a durable solution to the concerns expressed by the
installer, and it is considered additional work, so we recommend approval.
3. COR-005
a. Provide White Maple Doors in lieu of Oak to match existing. The existing building project
specifications, which we used for reference on this project, had Red Oak doors specified.
Upon review of the submitted samples from the supplier, it was determined the
installed doors were White Maple. The White Maple doors to match the existing
installed doors are slightly more expensive than the specified Red Oak doors. We
recommend approving this change order request, so the new doors match the existing.
City of Waukee
September 16, 2022
Page 2 of 2
We have reviewed the submitted quotes from Core Construction, and they appear to be in line with
current industry pricing. If City Staff concurs with this proposed additional pricing, we recommend the
City of Waukee Increase the contract price in the amount of $2,611.11 to complete the additional work
associated with Change Order Number 001. If you have any questions, please contact me.
Sincerely,
FARNSWORTH GROUP, INC.
Kristofer J. Orth, AIA
Architecture Principal
Enclosures: Change Order #001, dated 09/14/2022
CHANGE ORDER NO. 1 - SUMMARY
Waukee Public Works - 2nd Floor Expansion
Date:09/14/22
Original Contract Price:$389,550.00
Change Orders approved to date:$0.00
CHANGE ORDER ITEMS
1)COR-003 Seal new VCT flooring wih product used by owner $1,384.50
2)COR-004 Provide & Install Expansion Cover at existing floor joint $554.26
3)COR-005 Provide White Maple Doors in lieu of Oak to match existing $672.35
TOTAL Changes:$2,611.11
Amount of this change order:$2,611.11
Adjusted contract price including this change order:$392,161.11
14225 University Avenue, Suite 110 | Waukee, IA 50263 | p 515.225.3469 | www.f-w.com
ENGINEERS | ARCHITECTS | SURVEYORS | SCIENTISTS
09-02-22
Kristofer Orth
RE: 22113 Waukee Public Works 2nd Floor Remodel
Dear Kristofer
Core proposes the following as a change in the Work:
Seal new VCT with product used by the owner on existing VCT
Proposed change in contract sum ADD $1384.50 if approved by 9-9-22
Proposed change in schedule 00 days if approved by 9-9-22. Should approval be granted after this deadline, the
schedule shall be extended further beyond the proposed change the same number of days.
An estimate and back up is attached. Please review and authorize one of the actions below. If you have any questions,
please contact me at your earliest convenience. Thank you.
Sincerely,
Jeremy Roush
Project Manager
Cc: Sasha Daljevic
Rudy Koester
Sara Kappos
□ Approved, incorporate change immediately
□ Pending, continue work per current contract
□ Pending, stop affected work until action taken (hold time past deadline above will be added to the proposed
change in schedule)
□ Rejected
The above action is authorized below by a duly authorized representative of the Owner and Architect:
Owner: Architect:
Signature ___________________________________ Signature ___________________________________
Name ______________________________________ Name ______________________________________
Title ________________________________________ Title ________________________________________
Date _______________________________________ Date _______________________________________
COR #003 Core Structural Services, LLC
3093 NW Prairie Lane
Des Moines, IA 50313
(515) 987-6830 Office
(515) 987-6830 Fax
TO: Farnsworth Group PROJECT NAME:
14225 University Ave Suite 110 PROJECT NUMBER:
Waukee IA 50263 SUBJECT:
FROM:
ATTN: Kristofer Farnsworth DATE:
Unit Cost Total Unit Cost Total Unit Cost Total Unit Cost Total
Seal VCT 515 $ 1.00 $ 1,300.00 $ 1,300.00
7
8
9
10
92
93
94
95
96
97
98
99
100
Subtotal -$ -$ -$ 1,300.00$ 1,300.00$
Small Tools Allowance 10.00%
Warranty 2.00% 2.00% 10.00% 0.00%
Overhead & Profit 10.00% 10.00% 2.00% 5.00% $ 65.00 $ 65.00
Bond 1.50% 1.50% 1.50% 1.50% $ 19.50 $ 19.50
The Contract Schedule will Increase / Decrease by:0 days TOTAL COR:
Clarifications & Exclusions:
WPW 2nd Fl Expansion
22113
Seal new VCT
Jeremy Roush
1,384.50$
9/2/22
Item #/
Cost Code Description Sub/Vendor Quantity Unit
Labor Material Equipment Subcontractor TOTAL
JobNo.COR-Log.JobName REV 1-11-223.xlsx Page 1
1
jeremyr@coreconstructionia.com
From:stevek@coreconstructionia.com
Sent:Friday, September 2, 2022 11:58 AM
To:otonielmayorga1979@gmail.com; 515cleaningservicehollc@gmail.com
Cc:jeremyr@coreconstructionia.com
Subject:RE: WPW 2nd floor wax floors
Price received based upon product 515 normally uses
$1200.00 labor
$100.00 material (5 gallon container )
Total price of$1300. Unless Rudy comes up with a product that is drastically more expensive.
Steve Koester
Project Superintendent
3093 NW Prairie Ln, Des Moines IA 50313
Office 515/264-5156 Cell 515/943-1372 FAX 515/257-4311
Coreconstructionia.com
From: stevek@coreconstructionia.com <stevek@coreconstructionia.com>
Sent: Friday, September 2, 2022 11:48 AM
To: otonielmayorga1979@gmail.com; 515cleaningservicehollc@gmail.com
Cc: jeremyr@coreconstructionia.com
Subject: WPW 2nd floor wax floors
Please price seal & wax floor.
You supply product to be identified by Rudy Koester.
Please reply to all to copy Jeremy in
2
Steve Koester
09-02-22
Kristofer Orth
RE: 22113 Waukee Public Works 2nd Floor Remodel
Dear Kristofer
Core proposes the following as a change in the Work:
Provide and Install Expansion Cover at Existing Joint
Proposed change in contract sum ADD $554.26 if approved by 9-9-22
Proposed change in schedule 00 days if approved by 9-9-22. Should approval be granted after this deadline, the
schedule shall be extended further beyond the proposed change the same number of days.
An estimate and back up is attached. Please review and authorize one of the actions below. If you have any questions,
please contact me at your earliest convenience. Thank you.
Sincerely,
Jeremy Roush
Project Manager
Cc: Sasha Daljevic
Rudy Koester
Sara Kappos
□ Approved, incorporate change immediately
□ Pending, continue work per current contract
□ Pending, stop affected work until action taken (hold time past deadline above will be added to the proposed
change in schedule)
□ Rejected
The above action is authorized below by a duly authorized representative of the Owner and Architect:
Owner: Architect:
Signature ___________________________________ Signature ___________________________________
Name ______________________________________ Name ______________________________________
Title ________________________________________ Title ________________________________________
Date _______________________________________ Date _______________________________________
COR #004 Core Structural Services, LLC
3093 NW Prairie Lane
Des Moines, IA 50313
(515) 987-6830 Office
(515) 987-6830 Fax
TO: Farnsworth Group PROJECT NAME:
14225 University Ave Suite 110 PROJECT NUMBER:
Waukee IA 50263 SUBJECT:
FROM:
ATTN: Kristofer Farnsworth DATE:
Unit Cost Total Unit Cost Total Unit Cost Total Unit Cost Total
Add 3" Aluminum Plate over Expansion joint $ 1.00 $ 353.10 $ 353.10
Labor to install 2.00 $ 65.00 $ 130.00 $ 130.00
Subtotal 130.00$ 353.10$ -$ -$ 483.10$
Small Tools Allowance 10.00% $ 13.00 $ 13.00
Warranty 2.00% $ 2.60 0.00% 2.00% 2.00% $ 2.60
Overhead & Profit 10.00% $ 13.00 10.00% $ 35.31 10.00% 5.00% $ 48.31
Bond 1.50% $ 1.95 1.50% $ 5.30 1.50% 1.50% $ 7.25
The Contract Schedule will Increase / Decrease by:0 days TOTAL COR:
Clarifications & Exclusions:
Labor Material Equipment Subcontractor TOTALItem #/
Cost Code Description Sub/Vendor Quantity Unit
WPW 2nd Fl Expansion
22113
Expansion Joint Cover
Jeremy Roush
554.26$
9/2/22
JobNo.COR-Log.JobName REV 1-11-223.xlsx Page 1
Quote
Date
8/30/2022
Quote #
12302
Name / Address
Core Construction
3093 NW Prairie Ln
Des Moines IA 50313
ACKELSON SHEET METAL, INC
120 1ST AVENUE N
PO BOX 164
ALTOONA, IA 50009
Rep
SS
Project
** NOTE - AS OF NOVEMBER 1, 2017, ALL CREDIT CARD PAYMENTS ARE
SUBJECT TO 4% SURCHARGE FEE **
Phone #
515-967-4674
Fax #
515-967-1199
Total
Description Qty Total
ATTN: JEREMY ROUSH
PHONE: (515) 264-5156 x204
CELL: (515) 419-3700
EMAIL: jeremyr@coreconstructionia.com
APPROX 3" x 120" - 1/8 ALUMINUM SADDLE PLATE WITH BEVELED
EDGES; PLATE WILL NOT HAVE MACHINED GROOVES FOR V24, AS
CALLED FOR IN PRINT
4 330.00T
** 1 - 2 WEEKS LEAD TIME **
Sales Tax 23.10
$353.10
09-12-22
Kristofer Orth
RE: 22113 Waukee Public Works 2nd Floor Remodel
Dear Kristofer
Core proposes the following as a change in the Work:
Provide White Maple Doors per returned submittal
Proposed change in contract sum ADD $672.35 if approved by 9-16-22
Proposed change in schedule 16 weeks if approved by 9-16-22. Should approval be granted after this deadline, the
schedule shall be extended further beyond the proposed change the same number of days.
An estimate and back up is attached. Please review and authorize one of the actions below. If you have any questions,
please contact me at your earliest convenience. Thank you.
Sincerely,
Jeremy Roush
Project Manager
Cc: Sasha Daljevic
□ Approved, incorporate change immediately
□ Pending, continue work per current contract
□ Pending, stop affected work until action taken (hold time past deadline above will be added to the proposed
change in schedule)
□ Rejected
The above action is authorized below by a duly authorized representative of the Owner and Architect:
Owner: Architect:
Signature ___________________________________ Signature ___________________________________
Name ______________________________________ Name ______________________________________
Title ________________________________________ Title ________________________________________
Date _______________________________________ Date _______________________________________
COR #005 Core Structural Services, LLC
3093 NW Prairie Lane
Des Moines, IA 50313
(515) 987-6830 Office
(515) 987-6830 Fax
TO: Farnsworth Group PROJECT NAME:
14225 University Ave Suite 110 PROJECT NUMBER:
Waukee IA 50263 SUBJECT:
FROM:
ATTN: Kristofer Farnsworth DATE:
Unit Cost Total Unit Cost Total Unit Cost Total Unit Cost Total
81100 Change from oak to white maple Doors Inc 9.00 $ 1.00 $ 603.00 $ 603.00
Subtotal -$ 603.00$ -$ -$ 603.00$
Small Tools Allowance 0.00%
Warranty 0.00% 0.00% 0.00% 10.00%
Overhead & Profit 10.00% 10.00% $ 60.30 10.00% 5.00% $ 60.30
Bond 1.50% 1.50% $ 9.05 1.50% 1.50% $ 9.05
The Contract Schedule will Increase / Decrease by: days TOTAL COR:
Clarifications & Exclusions:
WPW 2nd Fl Expansion
22113
White Maple Doors
Jeremy Roush
672.35$
9/12/22
Item #/
Cost Code Description Sub/Vendor Quantity Unit
Labor Material Equipment Subcontractor TOTAL
JobNo.COR-Log.JobName REV 1-11-223.xlsx Page 1
1
jeremyr@coreconstructionia.com
From:Everett Kruger <ekruger@doorsinciowa.com>
Sent:Friday, September 9, 2022 1:03 PM
To:jeremyr@coreconstructionia.com
Cc:stevek@coreconstructionia.com
Subject:Re: 1.pdf
Jeremy,
To have changed wood doors at any point to white maple, would come with an added cost of $603.00 for all 9
doors. So that would need approved for me to place a new door order. I discussed this with my supervisor and
I can offer the owner a deduct of $900.00 if they would want to consider keeping the doors as is.
Thank you,
Everett
From: jeremyr@coreconstructionia.com <jeremyr@coreconstructionia.com>
Sent: Friday, September 9, 2022 8:45 AM
To: Everett Kruger <ekruger@doorsinciowa.com>
Cc: stevek@coreconstructionia.com <stevek@coreconstructionia.com>
Subject: RE: 1.pdf
I understand there is a long lead time on doors. The doors they have function well and will get them in the space. Get
me this upcharge soon so I can start the discussion with Farnsworth and the owner.
Note my email address has changed please update my contact info
Jeremy Roush
Project Manager / Estimator
3093 NW Prairie Ln, Des Moines IA 50313
Office 515/264-5156 x204 Cell 515/419-3700
Fax 515/257-4311
From: Everett Kruger <ekruger@doorsinciowa.com>
Sent: Friday, September 9, 2022 8:35 AM
To: jeremyr@coreconstructionia.com
Cc: stevek@coreconstructionia.com
Subject: Re: 1.pdf
Jeremy,
I understand and yes this should've been priced then. But it would be different no matter when priced. I don't
know how this got missed, but it's on me to make the change. That said, there is no one in the industry that
can do doors even anything close to 3 weeks. Lead times of 15-16 weeks are most common anymore. So doors
would have to be replaced after the project is open. I apologize, but now can only do what's needed to
correct, unless the owner wants to consider a deduct to keep the doors they have??
2
Everett
From: jeremyr@coreconstructionia.com <jeremyr@coreconstructionia.com>
Sent: Friday, September 9, 2022 8:27 AM
To: Everett Kruger <ekruger@doorsinciowa.com>
Cc: stevek@coreconstructionia.com <stevek@coreconstructionia.com>
Subject: RE: 1.pdf
I cant argue that the spec says oak, the issue I have is when the submittal came back why I didn’t get made aware of an
upcharge, and how these got ordered wrong? I am 3 weeks from substantial completion.
Note my email address has changed please update my contact info
Jeremy Roush
Project Manager / Estimator
3093 NW Prairie Ln, Des Moines IA 50313
Office 515/264-5156 x204 Cell 515/419-3700
Fax 515/257-4311
From: Everett Kruger <ekruger@doorsinciowa.com>
Sent: Friday, September 9, 2022 8:17 AM
To: jeremyr@coreconstructionia.com
Subject: Re: 1.pdf
New ones will take a good 15-16 weeks anyway. I will also need to price the difference between the bid red
oak and white maple.
From: jeremyr@coreconstructionia.com <jeremyr@coreconstructionia.com>
Sent: Thursday, September 8, 2022 9:50 AM
To: Everett Kruger <ekruger@doorsinciowa.com>
Subject: 1.pdf
Everett see attached. It looks like the wrong door veneer got ordered. How long will it take to get new ones onsite?