Loading...
HomeMy WebLinkAbout2022-10-17 I01F_04 West Area Trunk Sewer Extension Phase 2_Pmt Est 1AGENDA ITEM: CITY OF WAUKEE, IOWA CITY COUNCIL MEETING COMMUNICATION MEETING DATE: October 17, 2022 AGENDA ITEM:Consideration of approval of Payment Estimate No. 1 to Rognes Corporation for the West Area Trunk Sewer Extension – Phase 2 Project, in the amount of $576,979.84. FORMAT:Consent Agenda SYNOPSIS INCLUDING PRO & CON: Rognes Corporation requested Payment Estimate No. 1 for the work completed on the West Area Trunk Sewer Extension – Phase 2 project, in the amount of $576,979.84. Veenstra & Kimm has reviewed the payment estimate and recommends payment. The partial payment is for the pay period September 26, 2022 to October 7, 2022. This payment estimate is for mobilization, erosion control & SWPPP, and clearing and grubbing as well as stored materials. FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS: $576,979.84 COMMISSION/BOARD/COMMITTEE COMMENT: STAFF REVIEW AND COMMENT: RECOMMENDATION: Approve Payment Estimate No. 1 ATTACHMENTS: I. Payment Estimate No. 1 II. Letter of Recommendation PREPARED BY:Beth Richardson REVIEWED BY:Sara Kappos SKK PUBLIC NOTICE INFORMATION – NAME OF PUBLICATION: DATE OF PUBLICATION: I1F4 October 12, 2022 Rudy Koester Director of Public Works City of Waukee 805 University Avenue Waukee, Iowa 50263 CITY OF WAUKEE, IOWA WEST AREA TRUNK SEWER EXTENSION – PHASE 2 PAY ESTIMATE NO. 1 Enclosed are three signed copies of Pay Estimate No. 1 in accordance with the contract between the City of Waukee and Rognes Corporation for the West Area Trunk Sewer Extension – Phase 2 Project. The partial payment estimate is for the period of September 26, 2022 to October 7, 2022. We have checked and recommend approval of Pay Estimate No 1. We recommended payment to Rognes Corporation in the amount of $576,979.84. Pay Estimate No. 1 is for tree clearing and stored materials. Please sign all copies of Pay Estimate No. 1 in the spaces provided. Please return one set of signed copies to Veenstra & Kimm, Inc. and forward one set of copies to Rognes Corporation with payment. If you have any questions or comments, please contact us at 515-225-8000. VEENSTRA & KIMM, INC. Andy Willcuts ARW:rsb 275352 Enclosures cc: Rognes Corporation Sara Kappos, City of Waukee – w/enclosure (email) Becky Schuett, City of Waukee – w/enclosure (email) Beth Richardson, City of Waukee – w/enclosure (email) Rachel Bruns, City of Waukee – w/enclosure (email) Tracy Lovetinsky, City of Waukee – w/enclosure (email) Original Contract Amount: QUANTITY VALUE ESTIMATED AUTHORIZED COMPLETED COMPLETED ITEM NO.DESCRIPTION UNIT (ORIG. CONT.)(INCL. C.O.'S)TO DATE UNIT PRICE TO DATE 1.1 Mobilization LS 1.00 1.00 0.25 $450,000.00 $112,500.00 1.2 Erosion Control & SWPPP LS 1.00 1.00 0.25 $40,000.00 $10,000.00 1.3 Traffic Control LS 1.00 1.00 0.00 $6,500.00 $0.00 1.4 Clearing and Grubbing LS 1.00 1.00 0.50 $500,000.00 $250,000.00 1.5 Granular Surfacing SY 205.00 205.00 0.00 $20.00 $0.00 1.6 Seeding LS 1.00 1.00 0.00 $45,000.00 $0.00 1.7 Tree EA 56.00 56.00 0.00 $300.00 $0.00 1.8 Shrub EA 224.00 224.00 0.00 $45.00 $0.00 1.9 Rock Excavation CY 500.00 500.00 0.00 $115.00 $0.00 1.10 Stabilizing Material TONS 415.00 415.00 0.00 $55.00 $0.00 1.11 Steel Sheeting Left in Place SF 4,370.00 4,370.00 0.00 $60.00 $0.00 1.12 Rip-Rap TONS 435.00 435.00 0.00 $95.00 $0.00 1.13 Field Drain Lines LF 100.00 100.00 0.00 $75.00 $0.00 1.14 Turf Reinforcement Mats, Type 4 SY 115.00 115.00 0.00 $24.00 $0.00 1.15 Bank Stabilization LS 1.00 1.00 0.00 $24,000.00 $0.00 1.16 12" Sanitary Sewer in Place LF 705.00 705.00 0.00 $180.00 $0.00 1.17 24" Sanitary Sewer in Place LF 7,722.00 7,722.00 0.00 $309.00 $0.00 1.18 48" Standard Manholes EA 29.00 29.00 0.00 $8,200.00 $0.00 1.19 48" Manhole Extra Depth VF 170.00 170.00 0.00 $140.00 $0.00 1.20 Connection to Existing Manhole EA 1.00 1.00 0.00 $24,500.00 $0.00 $372,500.00Total Value Completed - Bid Items BID ITEMS PROJECT TITLE: West Area Trunk Sewer Extension - Phase 2 Contractor: Rognes Corporation Pay Period: September 26, 2022 to October 7, 2022 ESTIMATE OF CONSTRUCTION COMPLETED PARTIAL PAYMENT NO. 1 Date: 10/11/22 $4,289,688.00 275352 Page 1 of 3 Item No.Description Unit Quantity Unit Price Extended Cost 1.17 Sanitary Sewer Pipe (Municipal Suppy Inc. Invoice No. 0851015-IN LS 1 $234,847.20 $234,847.20 $234,847.20 MATERIALS STORED SUMMARY Total Materials Stored 275352 Page 2 of 3 Total Completed $372,500.00 Total Completed $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Completed $372,500.00 Total Completed $234,847.20 $607,347.20 $30,367.36 $576,979.84 $0.00 $576,979.84 $576,979.84 is recommended for approval for payment in accordance with the terms of the Contract. $4,289,688.00 $4,289,688.00 $576,979.84 $576,979.84 $3,712,708.16 14.2% Rognes Corporation Signature Signature Signature Name Name Name Title Project Engineer Title Title Date Date Date $0.00 SUMMARY Bid Item Subtotal $4,289,688.00 Original Contract 1 Description/Notes 2 3 6 7 $0.00 Total Approved Veenstra & Kimm, Inc. 9 10 Total Previously Approved City of Waukee Approved by: CONTRACT SUMMARY $0.00 BALANCE ORIGINAL CONTRACT AMOUNT TOTAL PARTIAL PAYMENTS INCL THIS PAYMENT PERCENT COMPLETE TOTAL CONTRACT AMOUNT PLUS CHANGE ORDERS THIS PARTIAL PAYMENT $0.00 Amount Due This Request $0.00 $0.00 $0.00 $0.00 $0.00 Recommended By:Contractor: Note: The amount 6 7 4 5 8 2 3 $0.00 $0.00 Period $0.00 Total Completed Plus Materials Stored Total Change Orders APPROVED CHANGE ORDERS $0.00 $0.00 $0.00 $0.00 $0.00 4 5 Change Order No. 1 Total Approved $0.00 9 10 Partial Payment No. APPROVED PARTIAL PAYMENTS Revised Contract Price $0.00 8 $0.00 $0.00 Total Approved $4,289,688.00 Total Materials Stored Retainage (5%) Total Earned Less Retainage 275352 Page 3 of 3 Invoice SOLD TO:SHIP TO: ROGNES CORPORATION JOBSITE Waukee, IA 50263 ROGNES CORPORATION 1609 N. ANKENY BLVD, STE # 210 ANKENY, IA 50023 10-ROGNCOR 10/10/2022 0851015-IN 0123430 7/14/2022 Page 1 of 1 MUNICIPAL SUPPLY, INC. Municipal, Contractor, and Industrial Supplies 1550 N.E. 51st Avenue Des Moines, Iowa 50313 PH: (515) 262-1300 FAX: (515) 262-6662 WATS (800) 747-2025 CUSTOMER NO: SALESPERSON: SHIP DATE: ORDER DATE: ORDER NUMBER: INVOICE NUMBER: INVOICE DATE: 10/10/2022 PETE SETTIMI DIRECT NET 30 DAYS JOB NAME WEST AREA TRUNK SEWER EXT P2 CUSTOMER P.O.TERMSSHIP VIA ITEM NO.UNIT ORDERED SHIPPED BACK ORD PRICE AMOUNT BUYER: *121-01 12" TRUSS PIPE EACH 0.00 29.21 712.50 0.00 712.50 *121-01 24" A-2000 SOLID PIPE EACH 234,847.20 59.91 7,630.00 3,920.00 3,710.00 *121-01 24" A-2000 X 24" DIP ADAPTER EACH 0.00 2,037.00 6.00 0.00 6.00 *121-01 24" MANHOLE ADAPTOR EACH 0.00 231.00 54.00 0.00 54.00 ORDER# 123430 Net Invoice:234,847.20 Freight:0.00 Sales Tax:0.00 234,847.20 Invoice Total: A SERVICE CHARGE OF 1 1/2% WITH A MINIMUM OF $1.00 PER MONTH WILL BE CHARGED ON ALL PAST DUE ACCOUNTS.