HomeMy WebLinkAbout2022-10-17 I01F_10 Ute Ave-Ashworth Rd Intersection_Change Order 5AGENDA ITEM:
CITY OF WAUKEE, IOWA
CITY COUNCIL MEETING COMMUNICATION
MEETING DATE: October 17, 2022
AGENDA ITEM:Consideration of approval of Change Order No. 5 to Concrete
Technologies, Inc. for the Ute Avenue and Ashworth Road Intersection
Project increasing the contract amount by $18,860.00.
FORMAT:Consent Agenda
SYNOPSIS INCLUDING PRO & CON: Change Order No. 5 includes work associated with
trenchless vs trenched water main construction east of Sugar Creek and removal of a temporary
fire hydrant that is no longer needed.
FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS: The net result of this
Change Order increases the contract price in the amount of $18,860.00.
COMMISSION/BOARD/COMMITTEE COMMENT:
STAFF REVIEW AND COMMENT:
RECOMMENDATION: Approve Change Order No. 5
ATTACHMENTS: I. Change Order No. 5
II. Letter of Recommendation
PREPARED BY:Beth Richardson
REVIEWED BY:Sara Kappos SKK
PUBLIC NOTICE INFORMATION –
NAME OF PUBLICATION:
DATE OF PUBLICATION:
I1F10
2727 SW SNYDER BOULEVARD | P.O. BOX 1159 | ANKENY, IA 50023-0974
autofill
v:\projects\2020\120.0783.01\construction\co_2022-10-12_letterco05.docm
October 12, 2022
Mr. Rudy Koester, P.E.
City of Waukee
805 University Avenue
Waukee, IA 50263
RE: CHANGE ORDER NO. 05
UTE AVENUE AND ASHWORTH ROAD INTERSECTION PROJECT
Dear Rudy:
Enclosed is change order 05 for the Ute Avenue and Ashworth Road Intersection project. This
change order includes work associated trenchless vs. trenched water main construction east of
Sugar Creek and removal of a temporary fire hydrant that is no longer needed.
We recommend approval of change order 05 in the amount of $18,860.00 to the prime
contractor, Concrete Technologies, Inc. of Grimes, Iowa. Substantial completion date remains
unchanged with this change order. Please place this change order on the next available city
council meeting agenda for approval.
Sincerely,
SNYDER & ASSOCIATES, INC.
Nathan Carhoff, P.E.
Project Manager
Enclosure
CO_2022-10-12_ChangeOrder05.xlsx
CHANGE ORDER NO. 5
OWNER: City of Waukee PROJECT: Ute Avenue & Ashworth Road Intersection
S&A PROJECT #: 120.0783.01
To:Concrete Technologies, Inc.
Contractor
1001 SE 37th Street
Address
Grimes, IA 50111
City, State, Zip
You are directed to make the following changes in this contract:
1.Description of change to be made:
Remove temporary installation of fire hydrant that was added via change order no. 2.
Install water main crossing at Sugar Creek per original as-bid design.
Install water main from Ashworth Road station 144+00 to station 149+44.67 by trenchless methods.
2.Reason for Change:
Temporary installation of fire hydrant to facilitate Xenia water main abandonment is no longer needed.
Based on subcontractor request, water main alignment/profile was revised at the Sugar Creek crossing, this was conveyed with design
revision 4. Prior to water main installation, storm sewer and street construction was completed for the Timber Ridge subdivision.
Trenched installation of water main would result in removal/replacement of newly constructed subdivision infrastructure. Further
coordination resulted in a request from the subcontractor to install water main per the original as-bid alignment/profile and continue
trenchless methods from the creek crossing to the end of the project. It is agreed to allow this change for a price that does not exceed
the cost for replacement of subdivision infrastructure.
3.Settlement for the cost of making the change shall be as follows:
Item No. Item Description Quantity Unit Unit Price Total Price
12.2 Fire Hydrant Assembly, Temporary Installation -1 EACH $8,140.00 $(8,140.00)
12.12 Trenchless Water Main East of Sugar Creek 1 LS $27,000.00 $27,000.00
$-
TOTAL $18,860.00
4.This change order will result in a net change in the contract completion time of 0 days and a net change
in the cost of the project of $18860.00 divided as follows:
Contract Contract
Amount Completion Date
Approved funds and contract completion date as per (Engineer's
Estimate, Contract or last approved C.O.)$4,937,842.14 August 6, 2022
Change due to this C.O. (+ or -)$18,860.00 0
Totals including this C.O.:$4,956,702.14 August 6, 2022
The change described herein is understood, and the terms of settlement are hereby agreed to:
Concrete Technologies, Inc.
CONTRACTOR
By DATE:October 12, 2022
Snyder & Associates, Inc.
ENGINEER
By DATE:October 12, 2022
City of Waukee
OWNER
By DATE: