HomeMy WebLinkAbout2022-10-17 I01F_15 Little Walnut Creek North Trunk Sewer Extension Phase 2_Change Order 2AGENDA ITEM: CITY OF WAUKEE, IOWA CITY COUNCIL MEETING COMMUNICATION MEETING DATE: October 17, 2022 AGENDA ITEM:Consideration of approval of Change Order No. 2 to J & K Contracting, LLC. for the Little Walnut Creek North Trunk Sewer Extension – Phase 2 Project increasing the contract amount by $1,274.90. FORMAT:Consent Agenda SYNOPSIS INCLUDING PRO & CON: Change Order No. 2 is for the installation of an additional manhole riser to raise a manhole to final grade. FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS: The net result of this Change Order increases the contract price in the amount of $1,274.90. COMMISSION/BOARD/COMMITTEE COMMENT: STAFF REVIEW AND COMMENT: RECOMMENDATION: Approve Change Order No. 2 ATTACHMENTS: I. Change Order No. 2 II. Letter of Recommendation PREPARED BY:Beth Richardson REVIEWED BY:Sara Kappos SKK PUBLIC NOTICE INFORMATION – NAME OF PUBLICATION: DATE OF PUBLICATION: I1F15 October 12, 2022 Rudy Koester Director of Public Works City of Waukee 805 University Avenue Waukee, Iowa 50263 WAUKEE, IOWA LITTLE WALNUT CREEK NORTH TRUNK SEWER EXTENSION – PHASE 2 CHANGE ORDER NO. 2 PAY ESTIMATE NO. 7 (FINAL) Enclosed are three copies of Change Order No. 2 and Pay Estimate No. 7 (Final) for work on the Little Walnut Creek North Trunk Sewer Extension – Phase 2 project, under the contract between the City of Waukee and J&K Contracting, LLC dated May 3, 2021. The partial payment estimate is for the period May 3, 2022 to October 6, 2022. Change Order No. 2 is for the installation of an additional manhole riser. We have checked the estimate and recommend payment to J&K Contracting, LLC in the amount of $1,211.15. Please sign all copies of Change Order No. 2 and Pay Estimate No. 7 (Final) in the space provided and return one signed copy of the change order and the pay estimate to our office. Please forward one signed copy of Change Order No. 2 and Pay Estimate No. 7 (Final) with payment to J&K Contracting, LLC. Rudy Koester October 12, 2022 Page 2 If you have any questions, please contact us at 515-225-8000. VEENSTRA & KIMM, INC. Andy Willcuts ARW:rsb 275334 Enclosures cc: J&K Contracting, LLC Sara Kappos, City of Waukee – w/enclosure (email) Becky Schuett, City of Waukee – w/enclosure (email) Beth Richardson, City of Waukee – w/enclosure (email) Rachel Bruns, City of Waukee – w/enclosure (email) Tracy Loveinksy, City of Waukee – w/enclosure (email) 275334 Page 1 of 2 October 11, 2022 CHANGE ORDER NO. 2 WAUKEE, IOWA LITTLE WALNUT CREEK NORTH TRUNK SEWER EXTENSION – PHASE 2 Change Order No. 2 is to document modifications to the construction contract for the Little Walnut Creek North Trunk Sewer Extension – Phase 2 project as shown below: Item Description Unit Quantity Unit Price Total Price 2.1 Manhole 9 Additional Riser EA 1 $599.90 $599.90 $599.90 Change Order No. 2 is also to adjust the plan quantities to the as-constructed quantities as shown below: Item Description Unit Quantity Unit Price Total Price 1.9 48” Manhole Extra Depth VF 3 $225.00 $675.00 $675.00 Change Order No. 2 increases the contract price by a total of $1,274.90. 275334 Page 2 of 2 J&K CONTRACTING, LLC CITY OF WAUKEE, IOWA By By Title Title Date Date VEENSTRA & KIMM, INC. ATTEST: By By Title Project Engineer Title Date Date