HomeMy WebLinkAbout2022-11-07 J01H_01 Douglas Pkwy Extension_Change Order 2AGENDA ITEM: CITY OF WAUKEE, IOWA CITY COUNCIL MEETING COMMUNICATION MEETING DATE: November 7, 2022 AGENDA ITEM:Consideration of approval of Change Order No. 2 to Absolute Concrete for the Douglas Parkway Extension project increasing the contract amount by $6,283.78. FORMAT:Consent Agenda SYNOPSIS INCLUDING PRO & CON: Change Order No. 2 includes additional modified subbase and fill material to adjust grade to accommodate the HMA overlay on N. Warrior Lane. FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS: The net result of this Change Order increases the contract price in the amount of $6,283.78. COMMISSION/BOARD/COMMITTEE COMMENT: STAFF REVIEW AND COMMENT: RECOMMENDATION: Approve the change order. ATTACHMENTS: I. Change Order No. 2 II. Letter of Recommendation PREPARED BY:Beth Richardson REVIEWED BY:Sara Kappos SKK PUBLIC NOTICE INFORMATION – NAME OF PUBLICATION: DATE OF PUBLICATION: J1H1 H:\WAUKEE_CI_IA\0A1124531\7_Construction\D_Pay Applications October 18, 2022 Mr. Rudy Koester Public Works Director City of Waukee, Iowa RE: Douglas Parkway Extension Change Order 2 Dear Mr. Koester: Submitted for your approval is Change Order 2 for the above-mentioned project. Change Order 2 includes the additional modified subbase and fill material to adjust grade to accommodate the HMA overlay on N. Warrior Lane. The approved contract value of $971,552.10 will be increased by $6,283.78 for a total contract value of $977,835.88. Please see the Change Order 2 for a full summary of the change items. Bolton & Menk, Inc. recommends the approval of Change Order 2. Please let me know if you have any questions. Sincerely, Bolton & Menk, Inc. Justin Ernst, P.E. Project Manager Owner: Contractor: City of Waukee Absolute Concrete 805 University Ave 1000 W. 6th Avenue Waukee, IA 50263 Slater, IA 50244 CO2.1 LS $ 6,283.78 1.00 $ 6,283.78 $ - $ - $ 6,283.78 $ 919,069.00 52,483.10$ $ 52,483.10 -$ $ 971,552.10 -$ $ 6,283.78 -$ $ 977,835.88 $ 52,483.10 0.65% 0 8/12/2022 Orig. Contract Date Douglas Parkway ExtensionProject Title 6/21/2021 Unit PriceUnit 10/11/22 Completion Date Date: Absolute Concrete The Original Contract Sum was Net Change by previously authorized Change Orders The Contract Sum prior to This Change Order was The Contract Sum will be revised by this Change Order in the amount of The new Contract Sum including this Change Order will be Aggregate Change Order as a percent of Original Contract The Contract Time will be changed by The date of Final Completion as of the date of this Change Order therefore is Previously Approved Change Orders Change Order 1 Change Order 2 Change Order 3 Date: Signature: CHANGE ORDER 2 Date: Signature: Name: Justin Ernst, P.E. Title: Project Manager NOT VALID UNTIL SIGNED BY THE CONTRACTOR, OWNER'S REPRESENTATIVE (if applicable) AND OWNER Bolton & Menk, Inc. Approved By: City of Waukee Signature: Name: Brad Deets Orig. Contract Amount Title: City Administrator Contractor: Name: Eli Hartog Title: Project Manager Change Order 4 TOTAL 8/12/2022 $919,069.00 Recommended By: 2Change Order Number CHANGE ORDER SUMMARY TOTAL GRADE MODIFICATIONS Description Date THE CONTRACT IS CHANGED AS FOLLOWS: This item is additon to the project to provide extra modified subbase and fill material to adjust the grade to accommodate the HMA overlay on N. Warrior Lane. Item Value AdjustmentQuantity Adjustment 1 of 1H:\WAUKEE_CI_IA\A13114815_Sugar Creek GC Irrigation Well\7_Construction\E_Pay Applications\Sugar Creek Water Supply Change Order 1.xlsx DocuSign Envelope ID: 4FD3BC22-0862-4039-BE5E-D7A1BD66BEE5 October 11, 2022 October 11, 2022