CITY OF WAUKEE, IOWA
CITY COUNCIL MEETING COMMUNICATION
MEETING DATE: November 21, 2022
AGENDA ITEM:Consideration of approval of Release of Retainage to Elder Corporation for the
NW 2nd Street Project, NW Venture Drive to NW Douglas Parkway, in the amount
of $248,702.58.
FORMAT:Consent Agenda
SYNOPSIS INCLUDING PRO & CON: Elder Corporation has completed the project and is requesting
the release of retainage. Foth recommends release of the retainage. Lien waivers have been received.
FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS:$248,702.58
COMMISSION/BOARD/COMMITTEE COMMENT:
STAFF REVIEW AND COMMENT:
RECOMMENDATION: Approve the remaining release of retainage to Elder Corporation for the NW 2nd
Street Construction – NW Venture Drive to NW Douglas Parkway Project in the
amount of $248,702.58
ATTACHMENTS: I. Letter of Recommendation
PREPARED BY:Beth Richardson
REVIEWED BY:Sara Kappos SKK
PUBLIC NOTICE INFORMATION –
NAME OF PUBLICATION:
DATE OF PUBLICATION:
I1I13
8191 Birchwood Court, Suite L Johnston, IA 50131 Phone: (515) 254-1393 Fax: (515) 254-1642
November 1, 2022
Sara Kappos, P.E.
Assistant Public Works Director
805 University Avenue
Waukee, IA 50263
RE: Pay Request #15 – RETAINAGE RELEASE
NW 2nd Street Construction
NW Venture Drive to NW Douglas Parkway
Dear Ms. Kappos:
Attached please find a detailed Pay Request for City Council approval on November 21, 2022.
Submitted Quantity
• Release of 5% retainage
Pending submittal and review of the project lien waivers and consent of Surety from the bonding
company. If City Staff concurs with this payment, we recommend the City of Waukee pay Elder
Corporation of Pleasant Hill, Iowa in the amount of $248,702.58 for the work completed.
Please let me know if you have any questions or need additional information.
Sincerely,
Foth Infrastructure and Environment, LLC
Andy Floy, P.E.
Lead Civil Engineer
Encl: Pay Request #15 dated 10/27/2022