CITY OF WAUKEE, IOWA
CITY COUNCIL MEETING COMMUNICATION
MEETING DATE: November 21, 2022
AGENDA ITEM:Consideration of approval of Change Order No. 3 to Elder Corporation
for NW Douglas Parkway Culvert and Pond Improvements project
increasing the contract amount by $144,850.00.
FORMAT:Consent Agenda
SYNOPSIS INCLUDING PRO & CON: Change Order No. 3 is for the addition dredging of
the pond to maximize depth and reduce the likelihood of future dredging.
FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS: The net result of this
Change Order increases the contract price in the amount of $144,850.00.
COMMISSION/BOARD/COMMITTEE COMMENT:
STAFF REVIEW AND COMMENT:
RECOMMENDATION: Approve change order no. 3
ATTACHMENTS: I. Change Order No. 3
II. Letter of Recommendation
PREPARED BY:Beth Richardson
REVIEWED BY:Sara Kappos SKK
PUBLIC NOTICE INFORMATION –
NAME OF PUBLICATION:
DATE OF PUBLICATION:
I12A
November 16, 2022
Rudy Koester
Public Works Director
City of Waukee
805 University Avenue
Waukee, Iowa 50263
WAUKEE, IOWA
NW DOUGLAS PARKWAY CULVERT AND POND IMPROVEMENTS
CHANGE ORDER NO. 3 AND PARTIAL PAYMENT ESTIMATE NO. 7
Enclosed are three copies of Change Order No. 3 for the above-mentioned project under the
contract between the City of Waukee and Elder Corporation. Change Order No. 3 is for
additional dredging of the pond to maximize depth and reduce the likelihood of future
dredging. Change Order No. 3 increases the contract price by a total of $144,850.00. Veenstra
& Kimm, Inc. recommends approval of Change Order No. 3.
Also enclosed are three copies of Partial Payment Estimate No. 7 for the period between
October 1, 2022 and October 31, 2022. Partial Payment Estimate No. 7 is for grading and pond
dredging. We have checked the estimate and recommend payment to Elder Corporation in the
amount of $209,828.16
Please sign all three copies of Change Order No. 3 and Partial Payment Estimate No. 7 in the
spaces provided. Return one signed copy of each to our office and one signed copy of each
with payment to Elder Corporation. The remaining copy of each should be kept for your files.
Rudy Koester
November 16, 2022
Page 2
If you have any questions or comments, please contact us at 515-225-8000.
VEENSTRA & KIMM, INC.
Jordan Kappos
JDK
292292
Enclosures
cc: Becky Schuett, City of Waukee (via e-mail)
Sara Kappos, City of Waukee (via e-mail)
Beth Richardson, City of Waukee (via e-mail)
Tracy Lovetinsky, City of Waukee (via e-mail)
Elder Corporation (via e-mail)
292292 Page 1 of 1
November 16, 2022 CHANGE ORDER NO. 3
WAUKEE, IOWA
NW DOUGLAS PARKWAY CULVERT AND POND IMPROVEMENTS
Change Order No. 3 is for additional dredging of the pond to maximize depth and reduce the
likelihood of future dredging with the forebay being present at the inlet to the pond. It includes
the following item:
Description Unit Quantity Unit Price Extended
Price
Additional Pond Dredging CY 14,485 $10.00 $144,850.00
Total
$144,850.00
Change Order No. 3 increases the contract price by a total of $144,850.00.
ELDER CORPORATION CITY OF WAUKEE
By By
Title Title
Date Date
VEENSTRA & KIMM, INC. ATTEST:
By By
Title Project Engineer Title
Date Date