AGENDA ITEM:Consideration of approval of Payment Estimate No. 9 to Absolute
Concrete Construction, Inc. for the Warrior Lane Improvements - Phase
2 project, in the amount of $212,095.29.
FORMAT:Consent Agenda
SYNOPSIS INCLUDING PRO & CON: Absolute Concrete Construction Inc. requested
Payment Estimate No. 9 for the work completed on Warrior Lane Improvements - Phase 2 project
in the amount of $212,095.29. Shive-Hattery has reviewed the payment estimate and recommends
payment.
The partial payment is for the pay period ending November 30, 2022. This pay estimate is for
storm sewer and subdrain, sidewalk and driveway pavement, combined concrete sidewalk and
retaining wall, pavement markings, seeding and erosion control, planting soils and landscape
plantings, and unit pavers.
FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS: $212,095.29
COMMISSION/BOARD/COMMITTEE COMMENT:
STAFF REVIEW AND COMMENT:
RECOMMENDATION: Approve Payment Estimate No. 9
ATTACHMENTS: I. Payment Estimate No. 9
II. Letter of Recommendation
PREPARED BY:Beth Richardson
REVIEWED BY:Sara Kappos SKK
PUBLIC NOTICE INFORMATION –
NAME OF PUBLICATION:
DATE OF PUBLICATION:
I1F3
S-H Project No.: 4203290
December 14, 2022
Rudy Koester, Public Works Director
City of Waukee
805 University Avenue
Waukee, IA 50263
RE: Pay Request #9 – Review and Recommendation to Approve
Warrior Lane Improvements - Phase 2
Dear Mr. Koester:
Attached please find a detailed pay request for the Warrior Lane Improvements - Phase 2 project. The
pay request includes the following items:
• Storm Sewer and Subdrain
• Sidewalk and Driveway Pavement
• Combined Concrete Sidewalk and Retaining Wall
• Pavement Markings
• Seeding and Erosion Control
• Planting Soils and Landscape Plantings
• Unit Pavers
We have reviewed the detailed quantities, and they are in line with the work completed. If City staff
concurs with this payment, we recommend the City of Waukee issue payment to Absolute Concrete
Construction, Inc. of Slater, IA in the amount of $212,095.29 for the work completed to date.
Sincerely,
SHIVE-HATTERY, INC.
Blake Peterson, PE
Civil Engineer