HomeMy WebLinkAbout2022-12-19 I01F_08 West Area Trunk Sewer Extension Phase 2_Change Order 1AGENDA ITEM: CITY OF WAUKEE, IOWA CITY COUNCIL MEETING COMMUNICATION MEETING DATE: December 19, 2022 AGENDA ITEM:Consideration of approval of Change Order No. 1 to Rognes Corporation for the West Area Trunk Sewer Extension – Phase 2 Project increasing the contract amount by $7,941.70. FORMAT:Motion SYNOPSIS INCLUDING PRO & CON: Change Order No. 1 is for upsizing of a manhole for a future sewer connection. FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS: The net result of this Change Order increases the contract price in the amount of $7,941.70. COMMISSION/BOARD/COMMITTEE COMMENT: STAFF REVIEW AND COMMENT: RECOMMENDATION: Approve the change order. ATTACHMENTS: I. Change Order No. 1 II. Letter of Recommendation PREPARED BY:Beth Richardson REVIEWED BY:Sara Kappos SKK PUBLIC NOTICE INFORMATION – NAME OF PUBLICATION: DATE OF PUBLICATION: I1F8 December 13, 2022 Rudy Koester Director of Public Works City of Waukee 805 University Avenue Waukee, Iowa 50263 CITY OF WAUKEE, IOWA WEST AREA TRUNK SEWER EXTENSION – PHASE 2 CHANGE ORDER NO. 1 PAY ESTIMATE NO. 3 Enclosed are three signed copies of Change Order No. 1 and Pay Estimate No. 3 in accordance with the contract between the City of Waukee and Rognes Corporation for the West Area Trunk Sewer Extension – Phase 2 Project. The partial payment estimate is for the period of November 1, 2022 to November 30, 2022. Change Order No. 1 is for the upsizing of a manhole for a future sewer connection. We have checked and recommend approval of Pay Estimate No. 3. We recommended payment to Rognes Corporation in the amount of $394,836.70. Pay Estimate No. 3 is for sanitary sewer installation. Please sign all copies of Change Order No. 1 and Pay Estimate No. 3 in the spaces provided. Please return one set of signed copies to Veenstra & Kimm, Inc. and forward one set of copies to Rognes Corporation with payment. Rudy Koester December 13, 2022 Page 2 If you have any questions or comments, please contact us at 515-225-8000. VEENSTRA & KIMM, INC. Andy Willcuts ARW:paj 275352 Enclosures cc: Rognes Corporation Sara Kappos, City of Waukee – w/enclosure (email) Becky Schuett, City of Waukee – w/enclosure (email) Beth Richardson, City of Waukee – w/enclosure (email) Rachel Bruns, City of Waukee – w/enclosure (email) Tracy Lovetinsky, City of Waukee – w/enclosure (email) 275352 Page 1 of 1 December 12, 2022 CHANGE ORDER NO. 1 WAUKEE, IOWA WEST AREA TRUNK SEWER EXTENSION - PHASE 2 Change Order No. 1 is to document modifications to the construction contract for the West Area Trunk Sewer Extension - Phase 2 project. Item Description Unit Quantity Unit Price Total Price 1.18 48” Standard Manhole EA -1 $8,200.00 ($8,200.00) 1.19 48” Manhole Extra Depth VF -14.50 $140.00 ($2,030.00) 2.1 60” Standard Manhole EA 1 $11,600.00 $11,600.00 2.2 60” Manhole Extra Depth VF 14.50 $386.10 $5,598.45 2.3 Precast MH Base EA 1 $973.25 $973.25 Total $7,941.70 Change Order No. 1 increases the contract price by a total of $7,941.70. ROGNES CORPORATION CITY OF WAUKEE, IOWA By By Title Title Date Date VEENSTRA & KIMM, INC. ATTEST: By By Title Project Engineer Title Date Date