HomeMy WebLinkAbout2023-02-06 J01G_06 2021-2022 ADA Sidewalk Improvements_Pmt Est 3 FinalAGENDA ITEM: CITY OF WAUKEE, IOWA CITY COUNCIL MEETING COMMUNICATION MEETING DATE: February 6, 2023 AGENDA ITEM:Consideration of approval of Payment Estimate No. 3 to MNM Concrete Specialists for the 2021/2022 ADA Sidewalk Improvements Project, in the amount of $0.00 FORMAT:Consent Agenda SYNOPSIS INCLUDING PRO & CON: MNM Concrete Specialists requested Payment Estimate No. 3 for the work completed on the 2021/2022 ADA Sidewalk Improvements Project, in the amount of $0. Veenstra & Kimm, Inc. has reviewed the payment estimate and recommends payment. The partial payment is for the pay period June 14, 2022 to January 31, 2023. This pay estimate includes Change Order No. 1 and closes out the project. FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS: $0 COMMISSION/BOARD/COMMITTEE COMMENT: STAFF REVIEW AND COMMENT: RECOMMENDATION: Approve Payment Estimate No. 3 ATTACHMENTS: I. Payment Estimate No. 3 II. Letter of Recommendation PREPARED BY:Sara Kappos REVIEWED BY:Sara Kappos SKK PUBLIC NOTICE INFORMATION – NAME OF PUBLICATION: DATE OF PUBLICATION: J1G6 February 1, 2023 Rudy Koester Public Works Director City of Waukee 805 University Avenue Waukee, Iowa 50263 WAUKEE, IOWA 2021/2022 ADA SIDEWALK IMPROVEMENTS CHANGE ORDER NO. 1 AND PAY ESTIMATE NO. 3 (FINAL) CERTIFICATE OF COMPLETION Enclosed are three copies of Change Order No. 1 for the above-mentioned project under the contract between the City of Waukee and MNM Concrete Specialists. Change Order No. 1 is to adjust the plan quantities to the as-constructed quantities. Change Order No. 1 increases the contract price by a total of $7,316.70. Veenstra & Kimm, Inc. recommends approval of Change Order No. 1. Also enclosed are three copies of Partial Payment Estimate No. 3 (Final) for the period between June 14, 2022 and January 31, 2023 for the above-mentioned project. Partial Pay Estimate No. 3 (Final) provides that 30 days after the acceptance of the project, the retainage in the amount of $4,550.74 will be paid to MNM Concrete Specialists provided it has submitted the necessary documentation. Also enclosed are two copies of the Certificate of Completion. This certificate should be executed after the City Council has approved acceptance of the project. Please sign both certificates and return one signed copy to our office. Please sign Change Order No. 1 and Partial Payment Estimate No. 3 (Final) in the spaces provided. Return one signed copy of each to our office and one signed copy of each to MNM Concrete Specialists. The remaining copy is for the City of Waukee’s records. Rudy Koester February 1, 2023 Page 2 If you have any questions or comments, please contact us at 515-225-8000. VEENSTRA & KIMM, INC. Jordan Kappos JDK 275340 Enclosures cc: Becky Schuett, City of Waukee (via e-mail) Sara Kappos, City of Waukee (via e-mail) MNM Concrete Specialists (via e-mail) QUANTITY VALUE ESTIMATED AUTHORIZED COMPLETED COMPLETED ITEM NO.DESCRIPTION UNIT (ORIG. CONT.)(INCL. C.O.'S)TO DATE UNIT PRICE TO DATE 1.1 Mobilization LS 1.00 1.00 1.00 $5,500.00 $5,500.00 1.2 Traffic Control LS 1.00 1.00 1.00 $10,500.00 $10,500.00 1.3 Sodding LS 1.00 1.00 1.00 $2,000.00 $2,000.00 1.4 Earthwork LS 1.00 1.00 1.00 $3,000.00 $3,000.00 1.5 Removal of Sidewalk SY 315.00 370.35 370.35 $12.00 $4,444.20 1.6 6" Curb and Gutter LF 19.00 25.00 25.00 $70.00 $1,750.00 1.7 4" PCC Sidewalk SY 181.00 104.80 104.80 $90.00 $9,432.00 1.8 6" PCC Sidewalk SY 135.00 255.10 255.10 $125.00 $31,887.50 1.9 Detectable Warnings, Cast Iron SF 211.00 169.80 169.80 $50.00 $8,490.00 3.1 Traffic Control LS 1.00 1.00 1.00 $2,000.00 $2,000.00 3.2 Sodding LS 1.00 1.00 1.00 $900.00 $900.00 3.3 Earthwork LS 1.00 1.00 1.00 $1,200.00 $1,200.00 3.4 Stop Sign EA 1.00 1.00 1.00 $800.00 $800.00 3.5 Removal of Sidewalk SY 54.00 54.00 54.00 $12.00 $648.00 3.6 6" Curb and Gutter LF 16.00 17.50 17.50 $70.00 $1,225.00 3.7 4" PCC Sidewalk SY 42.00 41.70 41.70 $90.00 $3,753.00 3.8 6" PCC Sidewalk SY 13.00 10.80 10.80 $125.00 $1,350.00 3.9 Detectable Warnings, Cast Iron SF 36.00 42.70 42.70 $50.00 $2,135.00 $91,014.70Total Value Completed - Bid Items BID ITEMS PROJECT TITLE: 2021/2022 ADA Sidewalk Improvements Contractor: MNM Concrete Specialists Original Contract Amount: Pay Period: June 14, 2022 to January 31, 2023 ESTIMATE OF CONSTRUCTION COMPLETED PARTIAL PAYMENT NO. 3 (Final) $83,698.00 Date: February 1, 2023 275340 Page 1 of 2 Total Completed $91,014.70 Total Completed $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Completed $91,014.70 Total Completed $0.00 $91,014.70 $4,550.74 $86,463.96 $86,463.96 $0.00 $0.00 is recommended for approval for payment in accordance with the terms of the Contract. $83,698.00 $91,014.70 $0.00 $86,463.96 $4,550.74 100.0% MNM Concrete Specialists Signature Signature Signature Name Jordan Kappos Name Name Title Project Engineer Title Title Date Date Date $0.00 SUMMARY Bid Item Subtotal $83,698.00 Original Contract 1 Description/Notes Balancing 2 3 6 7 $0.00 Total Approved Veenstra & Kimm, Inc. 9 10 Total Previously Approved City of Waukee Approved: CONTRACT SUMMARY $0.00 FINAL RETAINAGE (to be paid 30 days after final acceptance) ORIGINAL CONTRACT AMOUNT TOTAL PARTIAL PAYMENTS INCL THIS PAYMENT PERCENT COMPLETE TOTAL CONTRACT AMOUNT PLUS CHANGE ORDERS THIS PARTIAL PAYMENT $0.00 Amount Due This Request $0.00 $0.00 $0.00 $0.00 $61,216.95 Recommended By:Contractor: Note: The amount 6 7 4 5 8 2 3 $25,247.01 $0.00 September 20, 2021 to April 30, 2022 Period $0.00 Total Completed Plus Materials Stored Total Change Orders APPROVED CHANGE ORDERS $0.00 $0.00 $0.00 $0.00 $0.00 4 5 Change Order No. 1 Total Approved $7,316.70 May 1, 2022 to June 13, 2022 9 10 Partial Payment No. APPROVED PARTIAL PAYMENTS Revised Contract Price $7,316.70 8 $0.00 $0.00 Total Approved $91,014.70 Total Materials Stored Retainage (5%) Total Earned Less Retainage 275340 Page 2 of 2