MEETING DATE: March 20, 2023
AGENDA ITEM:Consideration of approval of Change Order No. 5 to Alliance
Construction for the SE Ashworth Road Corridor Improvements – SE
Parkview Crossing Drive to SE Glacier Trail Project increasing the
contract amount by $1,650.00.
FORMAT:Motion
SYNOPSIS INCLUDING PRO & CON: Change Order No. 5 is for additional compensation
for the relocation of the streetlight underground electrical in conflict with the Century Link vault
lid at 172+50.
FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS: The net result of this
Change Order increases the contract price in the amount of $1,650.00.
COMMISSION/BOARD/COMMITTEE COMMENT:
STAFF REVIEW AND COMMENT:
RECOMMENDATION: Approve the change order.
ATTACHMENTS: I. Change Order No. 5
II. Letter of Recommendation
PREPARED BY:Beth Richardson
REVIEWED BY:Sara Kappos SKK
PUBLIC NOTICE INFORMATION –
NAME OF PUBLICATION:
DATE OF PUBLICATION:
I1E3
8191 Birchwood Court, Suite L Johnston, IA 50131 Phone: (515) 254-1393
March 6, 2023
Sara Kappos, P.E.
Assistant Public Works Director
805 University Avenue
Waukee, IA 50263
RE: Change Order #5
SE Ashworth Road Corridor Improvements – SE Parkview Crossing Drive to SE Glacier
Trail
Dear Ms. Kappos:
Attached please find a detailed Change Order for City Council approval on March 20, 2023.
Change Description:
• Item CO 11.14 Streetlight Relocation for Century Link Vault
o Additional compensation for the relocation of the streetlight underground
electrical in conflict with the Century Link vault lid at 172+50.
We have reviewed the submitted quotes from Alliance Construction and they appear to be in
order with current industry pricing. If City Staff concurs with this pricing, we recommend the City
of Waukee revise the contract price in the amount of $1,650.00 to complete the additional work
associated with Change Order #5. If you have any questions, please contact me.
Sincerely,
Foth Infrastructure & Environment, LLC
Andy Floy, P.E.
Lead Civil Engineer
Encl: Change Order #5 dated 03/06/2023
CHANGE ORDER 05
Distribution:
Owner - Finance ____
Owner - Public Works ____
Engineer ____
Contractor ____
Contractor:Alliance Construction Group
3000 SE Grimes Blvd, Suite 800
Grimes, Iowa 50111 $4,510,016.01 February 22, 2021
CO 11.14 LS $1,650.00 1.00 $1,650.00
$1,650.00
$4,510,016.01
$31,286.39
$4,541,302.40
$1,650.00
$4,542,952.40
0 Days
Recommended By:
Alliance Construction Group
Signature:
Name: Ryan McKinney
Title: Project Manager
Date:
Owner:City of Waukee
□ ≤$500 Department Director X_______________________________________Date___________________
□ $501 to $2,500 City Administrator X_______________________________________Date___________________
□ Date___________________
□ >$2,501 City Council approved or ratified at Council meeting on Date___________________
SE Ashworth Road Corridor Improvements
SE Parkview Crossing to SE Glacier
5
19W019.01
Waukee Project File Number
Project Title
Streetlight Electrical Relocation for Century Link Vault
Description
Special
Foth Project File Number
Orig. Contract Amount & Date
Value Adjustment
Department of Public Works
805 University Avenue
Waukee, IA 50263
(515) 987-7920 Fax (515) 987-3979
Name: Andy Floy, P.E.
The Contract Sum prior to This Change Order was
Date
Change Order Number
Quantity
AdjustmentUnit Price
THE CONTRACT IS CHANGED AS FOLLOWS: Additional compensation for the relocation of the streetlight underground electrical in conflict with the Century Link vault lid at 172+50.
Item Code
Prepared By:Checked By:
Item No.
March 6, 2023
Unit
Date:
The Contract Time will be increased by
City of Waukee
CHANGE ORDER SUMMARY
NOT VALID UNTIL SIGNED BY THE CONTRACTOR, OWNER'S REPRESENTATIVE (if applicable) AND OWNER
The Original Contract Sum was
The new Contract Sum including this Change Order will be
Signature:
Date:
Name: Brad Deets
Title: Lead Civil Engineer
Signature:
The Contract Sum will be increased by this Change Order in the amount of
Net Change by previously authorized Change Orders
Title: City Administrator
Foth Infrastructure & Environment, LLC
CO#05 - 2023-0306-SE Ashworth Road Corridor Improvents.xlsx Change Order 1 Page 1 of 1
3/6/23