SYNOPSIS INCLUDING PRO & CON: The City has requested Northern Natural Gas (NNG) to
rebuild town border station (TBS) no. 2 from its current configuration as a regulated station to an
unregulated station with an increased delivery capacity of 20,000 Dth/day. This work is necessary to
accommodate the anticipated additional Des Moines A Line capacity Waukee will be making a bid for
during the current open season. The rebuilding of the unregulated station by NNG shall be completed
by November 1, 2023. Waukee will be paying NNG an advance payment for these improvements as
required by the agreement. These improvements are in the draft FY 2024-28 CIP with a total budget
of $1,400,000.00.
FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS: The City will pay NNG $798,675
as set forth in Appendix A of the agreement. If actual costs are different from the estimate of Actual
Costs, Waukee and NNG agree to true-up to the actual costs.
COMMISSION/BOARD/COMMITTEE COMMENT:
STAFF REVIEW AND COMMENT:
RECOMMENDATION: Approve the resolution.
ATTACHMENTS: I. Facilities Reimbursement Agreement
PREPARED BY: Rudy Koester
REVIEWED BY: Rudy Koester RK
PUBLIC NOTICE INFORMATION –
NAME OF PUBLICATION:
DATE OF PUBLICATION:
I1G1
THE CITY OF WAUKEE, IOWA
RESOLUTION 2023-
APPROVING FACILITIES REIMBURSEMENT AGREEMENT,
WAUKEE NO. 2 STATION REBUILD TO UNREGULATED STATION
[NORTHERN NATURAL GAS COMPANY]
IN THE NAME AND BY THE AUTHORITY OF THE CITY OF WAUKEE, IOWA
WHEREAS, the City of Waukee, Iowa is a duly organized municipality within Dallas County;
AND,
WHEREAS, The City has requested Northern Natural Gas (NNG) to rebuild town border station
(TBS) no. 2 from its current configuration as a regulated station to an unregulated station with an
increased delivery capacity of 20,000 Dth/day; AND,
WHEREAS, accommodate the anticipated additional Des Moines A Line capacity Waukee will
be making a bid for during the current open season; AND,
WHEREAS, the rebuilding of the unregulated station by NNG shall be completed by November
1, 2023; AND,
NOW THEREFORE BE IT RESOLVED by the City Council of the City of Waukee that the
Facilities Reimbursement Agreement, Waukee No. 2 Station Rebuild to Unregulated Station
[Northern Natural Gas Company] is hereby approved.
Passed by the City Council of the City of Waukee, Iowa, and approved this the 17th day of April,
2023.
____________________________
Courtney Clarke, Mayor
Attest:
___________________________________
Rebecca D. Schuett, City Clerk
RESULTS OF VOTE: AYE NAY ABSENT ABSTAIN
Anna Bergman Pierce
R. Charles Bottenberg
Chris Crone
Larry R. Lyon
Ben Sinclair
Contract No. 602633-0
FACILITIES REIMBURSEMENT AGREEMENT
Waukee #2 rebuild to unregulated station
BETWEEN
NORTHERN NATURAL GAS COMPANY
AND
CITY OF WAUKEE
This Facilities Reimbursement Agreement (Agreement) is dated as of April 21, 2023. Pursuant
to the request of City of Waukee (Customer), with respect to the Waukee #2 station (POI 78642)
rebuild to unregulated station with deliverability capability of 20,000 Dth/day, Northern Natural
Gas Company (Northern) shall complete the required facility changes. This Agreement is subject
to the following terms and conditions:
1.Northern, or its designee, shall rebuild the Waukee #2 TBS to an unregulated station capable
of delivering 20,000 Dth/day (Facilities), as soon as practicable after execution of this
Agreement. Northern will use commercially reasonable efforts to have the Facilities placed
in service no later than November 1, 2023. However, Northern will have no liability
whatsoever if the Northern Facilities are not placed in service by such date. Northern shall
provide all necessary materials and perform all work to complete the Facilities in a good and
workmanlike manner in accordance with prudent industry practice.
2.The parties acknowledge that supply chain shortages in materials may adversely impact the
planned completion of the Facilities. Northern will endeavor to use commercially reasonable
efforts to timely acquire and install all necessary materials to complete the Facilities.
Notwithstanding these efforts, consistent with other provisions of this Agreement, Northern
shall not be held liable should the Facilities be placed in-service after the targeted in-service
date.
3.Northern does not guarantee any specific pressure for deliveries through its facilities other
than as provided in Northern’s FERC Gas Tariff as revised from time to time (Northern’s
Tariff).
4.As of the date of this Agreement, the estimated cost of actual costs of the Facilities, including
but not limited, (i) design, materials, labor, contract and engineering costs; (ii) abandonment
of facilities; (iii) overheads; (iv) all applicable taxes; (v) income tax gross up, when
applicable; (vi) allowance for funds used during construction (AFUDC), when applicable;
and (vii) associated operation and maintenance costs (Actual Costs), are $798,675 as set forth
in Appendix A. Customer shall pay to Northern on or before April 21, 2023, one half of the
estimate of Actual Costs, or $399,338, and the balance of $399,337 on or before July 6, 2023,
for the construction and abandonment of the Facilities. Upon completion of the work, if
Page 2
Actual Costs are different from the estimate of Actual Costs, Customer and Northern agree to
true-up to the Actual Costs (i.e., Customer agrees to pay Northern the difference if the Actual
Costs are greater than the estimate of Actual Costs, or Northern will reimburse Customer the
difference if the Actual Costs are less than the estimate of Actual Costs).
5. In the event the project is terminated by Customer or due to Customer’s default prior to
completion, Customer shall pay Northern for all costs reasonably incurred and/or committed
to for construction of the Facilities up to the date of termination, including tax gross-up if
applicable.
6. Northern shall indemnify and hold Customer, including its officers, directors, employees and
agents, harmless from and against any and all claims arising out of or in connection with the
design, construction, ownership, operation and maintenance of Northern’s Facilities.
7. Customer will provide, own, operate and maintain all gas service equipment (including
valves, pressure regulators, odorization equipment and other facilities) required downstream
of Northern owned facilities. Customer is responsible for providing over-pressure protection
equipment for its facilities downstream of Northern’s Facilities. Customer shall indemnify
and hold Northern and Northern’s affiliates, including its officers, directors, employees, and
agents, harmless from and against any and all claims arising out of or in connection with the
design, construction, ownership, operation and maintenance of Customer’s facilities.
Customer warrants and represents to Northern that it has the knowledge and expertise, and its
employees, agents and contractors are qualified to design, construct and operate the gas
service equipment required beyond the point of delivery including specifically, but not by
way of limitation, the receipt of gas from Northern at Northern’s pressure.
8. Gas deliveries will be provided pursuant to effective service agreement(s) and Northern’s
Tariff. Except as may otherwise be provided in effective service agreement(s), Northern shall
have no obligation to provide service to Customer as the result of the construction of the
Facilities.
9. Any terms not defined herein shall have the meanings set forth in Northern’s Tariff and any
conflicts between this Agreement and Northern’s Tariff shall be resolved in favor of
Northern’s Tariff.
10. Customer shall not reveal this Agreement or the terms and conditions thereof to any other
parties except as to the interpretation, applicability, or enforcement of this Agreement before
a trier of fact or as may be requested by administrative or judicial action.
11. This Agreement is subject to and conditioned upon receipt by Northern of all approvals
required to construct or abandon the necessary Facilities, all necessary authorizations from
federal, state, local, and/or municipal agencies or other governmental authorities. It is
expressly understood that all such approvals shall be in a form and substance satisfactory to
Northern and shall be final before the respective governmental authority and no longer
subject to appeal or rehearing before such governmental authority unless Northern waives the
requirement that the approval be final.
Page 3
12. This Agreement is subject to Northern’s Tariff, all valid laws, rules, and regulations of duly
constituted authorities having jurisdiction, and is subject to any and all receipts of such
authorization as may be required for the construction of the Facilities.
13. AS TO ALL MATTERS OF CONSTRUCTION AND INTERPRETATION, THIS
AGREEMENT SHALL BE INTERPRETED, CONSTRUED AND GOVERNED BY THE
LAWS OF THE STATE OF NEBRASKA WITHOUT REGARD TO CONFLICT OF LAW
PROVISIONS.
14. TO THE FULLEST EXTENT PERMITTED BY LAW, EACH OF THE PARTIES
HERETO WAIVES ANY RIGHT IT MAY HAVE TO A TRIAL BY JURY WITH
RESPECT TO LITIGATION DIRECTLY OR INDIRECTLY ARISING OUT OF, UNDER
OR IN CONNECTION WITH, THIS AGREEMENT. EACH PARTY FURTHER WAIVES
ANY RIGHT TO CONSOLIDATE ANY ACTION IN WHICH A JURY TRIAL HAS
BEEN WAIVED WITH ANY OTHER ACTION IN WHICH A JURY TRIAL CANNOT
BE OR HAS NOT BEEN WAIVED.
15. This Agreement constitutes the entire agreement between the parties with respect to the
subject matter of this Agreement and shall be binding upon and shall inure to the benefit of
the parties hereto and their respective successors and assigns. No promises, agreements, or
warranties additional to this Agreement other than as may be contained in Northern’s Tariff
will be deemed to be a part of this Agreement, nor will any alteration, amendment, or
modification be effective unless confirmed in writing by the parties.
16. This Agreement may be signed in counterparts, each of which when signed shall be an
original, but all of which shall together constitute one and the same instrument. A signature
delivered by facsimile, e-mail in portable document format (.pdf) or DocuSign electronic
signature system shall be deemed to be an original manual signature and shall be binding and
have the same legal effect as an original manual signature.
17. Any document generated by the parties with respect to this Agreement, including this
Agreement, may be imaged, and stored electronically (Imaged Documents). Imaged
Documents may be introduced as evidence in any proceeding as if such were original
business records and neither party shall contest the admissibility of Imaged Documents as
evidence in any proceeding.
18. This Agreement shall be void and of no effect if not executed and returned to Northern by
April 21, 2023.
Page 4
The parties hereto have executed this Agreement to indicate their acceptance.
Northern Natural Gas Company City of Waukee
By: _________________________ By: _________________________
Title: _______________________ Title: ________________________
Date: _______________________ Date: ________________________
Page 5
FACILITIES REIMBURSEMENT AGREEMENT
Waukee #2 rebuild to unregulated station
BETWEEN
NORTHERN NATURAL GAS COMPANY
AND
CITY OF WAUKEE
APPENDIX A
Facilities and Estimated Costs
Project Name: Waukee #2 rebuild to unregulated station
Facilities Description: By November 1, 2023, Waukee #2 station will be converted to an
unregulated delivery station. All existing equipment will be removed.
The station equipment will be sized to flow 20,000 Dth/day at line
pressure. A temporary regulator skid with a meter will be required
during construction. A building will be installed around the meter. The
driveway will be expanded to 20-feet to allow for pull through of
vehicles. The tie-over line between IAB65002 Des Moines B line and
IAB65001 Des Moines A line will be cut and removed to the edge of the
station where the new take-off valve will be located.
Cost Category Estimated Cost
Contract Labor $302,140
Materials $118,315
Subcontract $13,200
Removal $10,000
Freight and Sales Tax $14,789
Environmental $15,000
Construction Support $52,500
District Labor and Equipment $7,500
Engineering $25,000
Right of Way $7,000
Change order request $56,544
Overheads $13,310
AFUDC $12,942
Escalation $11,818
Subtotal $660,058
Minus AFUDC ($12,942)
Income Tax Gross-Up (18.66%) $118,886
Removal $10,000
O&M (10 years) ($32,973)
Total Estimated Cost $798,675