HomeMy WebLinkAbout2023-05-15 I01G_03 NW Sunrise Dr Culvert_Pmt Est 1AGENDA ITEM:
CITY OF WAUKEE, IOWA
CITY COUNCIL MEETING COMMUNICATION
MEETING DATE: May 15, 2023
AGENDA ITEM:Consideration of approval of Payment Estimate No. 1 to Progressive
Structures, LLC for the NW Sunrise Drive Culvert Project, in the amount
of $285,039.42
FORMAT:Consent Agenda
SYNOPSIS INCLUDING PRO & CON: Progressive Structures, LLC requested Payment
Estimate No. 1 for the work completed on the NW Sunrise Drive Culvert
Project, in the amount of $285,039.42. WHKS & Co. has reviewed the
payment estimate and recommends payment.
The partial payment is for the pay period ending April 30, 2023. This pay estimate is for
excavation, granular material, precast concrete box culvert, temporary stream diversion,
mobilization, and construction survey.
FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS: $285,039.42
COMMISSION/BOARD/COMMITTEE COMMENT:
STAFF REVIEW AND COMMENT:
RECOMMENDATION: Approve Payment Estimate No. 1
ATTACHMENTS: I. Payment Estimate No. 1
II. Letter of Recommendation
PREPARED BY:Beth Richardson
REVIEWED BY:Sara Kappos SKK
PUBLIC NOTICE INFORMATION –
NAME OF PUBLICATION:
DATE OF PUBLICATION:
I1G3
3737 Woodland Avenue, Suite 111
West Des Moines, IA 50266
Phone: 515.226.8859
Email: desmoines@whks.com
Website: www.whks.com
May 9, 2023
Mr. Rudy Koester, P.E.
Public Works Director / City Engineer
City of Waukee
805 University Avenue
Waukee, IA 50263
RE: City of Waukee
NW Sunrise Drive Culvert (STORM 24-01)
Pay Estimate No. 1
Dear Mr. Koester:
Enclosed is Pay Estimate No. 1 for the above reference project. We have coordinated with the
Contractor and City staff performing field observation regarding the actual work completed to date
and recommend the City make payment in the amount of $285,039.42 to:
Progressive Structures, LLC
315 Commercial Ave.
PO Box 170
Luxemburg, IA 52056
5% retainage in the amount of $15,002.08 should be held by the City until 30 days after project
acceptance and completion of any punch list items are completed to the satisfaction of the City.
Please contact us if you have any questions.
Sincerely,
WHKS & CO.
Casey V. Faber, P.E.
Project Manager
cc (w/ enclosures):
Sara Kappos, City of Waukee
Scott Campbell, City of Waukee
Travis Augustyn, Progressive Structures, LLC
Melissa Schilling, Progressive Structures, LLC
3737 Woodland, Suite 111
West Des Moines, IA 50266
363,898.48$
Project:Precast Reinforced Box Culvert Replacment
Project No.:STORM 24-01 Date:5/9/2023
Location:NW Sunrise Drive Culvert Estimate No.:1
Contractor:Progressive Structures, LLC % Complete:82.5%
1 EMBANKMENT-IN-PLACE CY $16.00 515.0 $8,240.00 0.0 0.0 0%-$
2 EXCAVATION, CLASS 10, CHANNEL CY $4.25 378.0 $1,606.50 0.0 0.0 0%-$
3 FLOODED BACKFILL CY $50.00 133.0 $6,650.00 0.0 0.0 0%-$
4 EXCAVATION, CLASS 20 CY $9.00 570.0 $5,130.00 570.0 570.0 100%5,130.00$
5 GRANULAR MATERIAL FOR BLANKET CY $74.50 127.0 $9,461.50 127.0 127.0 100%9,461.50$
6 ORNAMENTAL METAL RAILING LF $200.00 93.2 $18,640.00 0.0 0.0 0%-$
7 PRECAST CONCRETE BOX CULVERT, 12 FT. X 5 FT. LF $1,150.00 162.0 $186,300.00 162.0 162.0 100%186,300.00$
8 PRECAST CONCRETE BOX CULVERT STRAIGHT END SECTION, 12 FT. X 5 FT. EACH $19,250.00 4 $77,000.00 4.0 4.0 100%77,000.00$
9 TEMPORARY STREAM DIVERSION EACH $1,650.00 1 $1,650.00 1.0 1.0 100%1,650.00$
10 ENGINEERING FABRIC SY $4.75 390.1 $1,852.98 0.0 0.0 0%-$
11 REVETMENT, CLASS E TON $75.00 336.3 $25,222.50 0.0 0.0 0%-$
12 MOBILIZATION LS $17,000.00 1.00 $17,000.00 1.0 1.0 100%17,000.00$
13 CONSTRUCTION SURVEY LS $3,000.00 1.00 $3,000.00 1.0 1.0 100%3,000.00$
14 SAFETY CLOSURE EACH $500.00 1 $500.00 1.0 1.0 100%500.00$
15 STABILIZED CONSTRUCTION ENTRANCE, EC-303 LF $9.50 30.0 $285.00 0.0 0.0 0%-$
16 PERIMETER AND SLOPE SEDIMENT CONTROL DEVICE, 12 IN. DIA. LF $4.00 340.0 $1,360.00 0.0 0.0 0%-$
300,041.50$
UnitDescriptionLine No. Unit Price
PARTIAL PAYMENT ESTIMATE
FOR CONSTRUCTION WORK COMPLETED
Contract Cost
Quantity Completed
This Estimate
Contract
Quantity
Total Quantity
Completed to Date
Total Dollars To
Date
Quantity
Completed Previous
Estimate
Contract Bid Price:
Percent
Complete
3737 Woodland, Suite 111
West Des Moines, IA 50266
363,898.48$
Project:Precast Reinforced Box Culvert Replacment
Project No.:STORM 24-01 Date:5/9/2023
Location:NW Sunrise Drive Culvert Estimate No.:1
Contractor:Progressive Structures, LLC % Complete:82.5%
UnitDescriptionLine No. Unit Price
PARTIAL PAYMENT ESTIMATE
FOR CONSTRUCTION WORK COMPLETED
Contract Cost
Quantity Completed
This Estimate
Contract
Quantity
Total Quantity
Completed to Date
Total Dollars To
Date
Quantity
Completed Previous
Estimate
Contract Bid Price:
Percent
Complete
Change Order Items
-$
DIV. 1
Total Contract Dollars 363,898.48$
Contract Complete Dollars 300,041.50$
Change Order Dollars -$
Less Retainage 15,002.08$
Less Previous Estimates -$
Net Payment This Estimate 285,039.42$
Recommended by:________________________________________________________________
Date
Agreed to by:________________________________________________________________
Date
Approved by:________________________________________________________________
Date
5-9-2023
05/09/2023