Loading...
HomeMy WebLinkAbout2023-05-15 I01G_03 NW Sunrise Dr Culvert_Pmt Est 1AGENDA ITEM: CITY OF WAUKEE, IOWA CITY COUNCIL MEETING COMMUNICATION MEETING DATE: May 15, 2023 AGENDA ITEM:Consideration of approval of Payment Estimate No. 1 to Progressive Structures, LLC for the NW Sunrise Drive Culvert Project, in the amount of $285,039.42 FORMAT:Consent Agenda SYNOPSIS INCLUDING PRO & CON: Progressive Structures, LLC requested Payment Estimate No. 1 for the work completed on the NW Sunrise Drive Culvert Project, in the amount of $285,039.42. WHKS & Co. has reviewed the payment estimate and recommends payment. The partial payment is for the pay period ending April 30, 2023. This pay estimate is for excavation, granular material, precast concrete box culvert, temporary stream diversion, mobilization, and construction survey. FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS: $285,039.42 COMMISSION/BOARD/COMMITTEE COMMENT: STAFF REVIEW AND COMMENT: RECOMMENDATION: Approve Payment Estimate No. 1 ATTACHMENTS: I. Payment Estimate No. 1 II. Letter of Recommendation PREPARED BY:Beth Richardson REVIEWED BY:Sara Kappos SKK PUBLIC NOTICE INFORMATION – NAME OF PUBLICATION: DATE OF PUBLICATION: I1G3 3737 Woodland Avenue, Suite 111 West Des Moines, IA 50266 Phone: 515.226.8859 Email: desmoines@whks.com Website: www.whks.com May 9, 2023 Mr. Rudy Koester, P.E. Public Works Director / City Engineer City of Waukee 805 University Avenue Waukee, IA 50263 RE: City of Waukee NW Sunrise Drive Culvert (STORM 24-01) Pay Estimate No. 1 Dear Mr. Koester: Enclosed is Pay Estimate No. 1 for the above reference project. We have coordinated with the Contractor and City staff performing field observation regarding the actual work completed to date and recommend the City make payment in the amount of $285,039.42 to: Progressive Structures, LLC 315 Commercial Ave. PO Box 170 Luxemburg, IA 52056 5% retainage in the amount of $15,002.08 should be held by the City until 30 days after project acceptance and completion of any punch list items are completed to the satisfaction of the City. Please contact us if you have any questions. Sincerely, WHKS & CO. Casey V. Faber, P.E. Project Manager cc (w/ enclosures): Sara Kappos, City of Waukee Scott Campbell, City of Waukee Travis Augustyn, Progressive Structures, LLC Melissa Schilling, Progressive Structures, LLC 3737 Woodland, Suite 111 West Des Moines, IA 50266 363,898.48$ Project:Precast Reinforced Box Culvert Replacment Project No.:STORM 24-01 Date:5/9/2023 Location:NW Sunrise Drive Culvert Estimate No.:1 Contractor:Progressive Structures, LLC % Complete:82.5% 1 EMBANKMENT-IN-PLACE CY $16.00 515.0 $8,240.00 0.0 0.0 0%-$ 2 EXCAVATION, CLASS 10, CHANNEL CY $4.25 378.0 $1,606.50 0.0 0.0 0%-$ 3 FLOODED BACKFILL CY $50.00 133.0 $6,650.00 0.0 0.0 0%-$ 4 EXCAVATION, CLASS 20 CY $9.00 570.0 $5,130.00 570.0 570.0 100%5,130.00$ 5 GRANULAR MATERIAL FOR BLANKET CY $74.50 127.0 $9,461.50 127.0 127.0 100%9,461.50$ 6 ORNAMENTAL METAL RAILING LF $200.00 93.2 $18,640.00 0.0 0.0 0%-$ 7 PRECAST CONCRETE BOX CULVERT, 12 FT. X 5 FT. LF $1,150.00 162.0 $186,300.00 162.0 162.0 100%186,300.00$ 8 PRECAST CONCRETE BOX CULVERT STRAIGHT END SECTION, 12 FT. X 5 FT. EACH $19,250.00 4 $77,000.00 4.0 4.0 100%77,000.00$ 9 TEMPORARY STREAM DIVERSION EACH $1,650.00 1 $1,650.00 1.0 1.0 100%1,650.00$ 10 ENGINEERING FABRIC SY $4.75 390.1 $1,852.98 0.0 0.0 0%-$ 11 REVETMENT, CLASS E TON $75.00 336.3 $25,222.50 0.0 0.0 0%-$ 12 MOBILIZATION LS $17,000.00 1.00 $17,000.00 1.0 1.0 100%17,000.00$ 13 CONSTRUCTION SURVEY LS $3,000.00 1.00 $3,000.00 1.0 1.0 100%3,000.00$ 14 SAFETY CLOSURE EACH $500.00 1 $500.00 1.0 1.0 100%500.00$ 15 STABILIZED CONSTRUCTION ENTRANCE, EC-303 LF $9.50 30.0 $285.00 0.0 0.0 0%-$ 16 PERIMETER AND SLOPE SEDIMENT CONTROL DEVICE, 12 IN. DIA. LF $4.00 340.0 $1,360.00 0.0 0.0 0%-$ 300,041.50$ UnitDescriptionLine No. Unit Price PARTIAL PAYMENT ESTIMATE FOR CONSTRUCTION WORK COMPLETED Contract Cost Quantity Completed This Estimate Contract Quantity Total Quantity Completed to Date Total Dollars To Date Quantity Completed Previous Estimate Contract Bid Price: Percent Complete 3737 Woodland, Suite 111 West Des Moines, IA 50266 363,898.48$ Project:Precast Reinforced Box Culvert Replacment Project No.:STORM 24-01 Date:5/9/2023 Location:NW Sunrise Drive Culvert Estimate No.:1 Contractor:Progressive Structures, LLC % Complete:82.5% UnitDescriptionLine No. Unit Price PARTIAL PAYMENT ESTIMATE FOR CONSTRUCTION WORK COMPLETED Contract Cost Quantity Completed This Estimate Contract Quantity Total Quantity Completed to Date Total Dollars To Date Quantity Completed Previous Estimate Contract Bid Price: Percent Complete Change Order Items -$ DIV. 1 Total Contract Dollars 363,898.48$ Contract Complete Dollars 300,041.50$ Change Order Dollars -$ Less Retainage 15,002.08$ Less Previous Estimates -$ Net Payment This Estimate 285,039.42$ Recommended by:________________________________________________________________ Date Agreed to by:________________________________________________________________ Date Approved by:________________________________________________________________ Date 5-9-2023 05/09/2023