CITY OF WAUKEE, IOWA
CITY COUNCIL MEETING COMMUNICATION
MEETING DATE: June 19, 2023
AGENDA ITEM:Consideration of approval of Payment Estimate No. 1 to Caliber Concrete,
LLC for the Heart of the Warrior Trail West Extension Project in the amount
of $81,083.21.
FORMAT:Consent Agenda
SYNOPSIS INCLUDING PRO & CON: Payment Estimate No. 1 to Caliber Concrete, LLC is for
clearing and grubbing, shared use path PCC, pavement removal, signage,
erosion control, and mobilization. The quantities completed to date have been
reviewed and agreed upon by the contractor, City of Waukee Staff, and Shive-
Hattery.
FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS:
COMMISSION/BOARD/COMMITTEE COMMENT:
STAFF REVIEW AND COMMENT: Approve Payment
RECOMMENDATION: Approve the resolution.
ATTACHMENTS: I. Letter of Recommendation
II. Payment Estimate No. 1
PREPARED BY: Matt Jermier
REVIEWED BY:
PUBLIC NOTICE INFORMATION –
NAME OF PUBLICATION:
DATE OF PUBLICATION:
I1H1
H:\WAUKEE_CI_IA\0A1124531\7_Construction\D_Pay Applications
June 13, 2023
Mr. Matt Jermier
Parks & Recreation Director
City of Waukee, Iowa
RE: Heart of Warrior Trail West Extension Pay Application 1
Dear Mr. Jermier:
Submitted for your approval is Pay Application 1 for the above-mentioned project. Pay Application 1
includes total work completed of $85,350.75 minus 5% retainage of $4,267.54 for a total payment of
$81,083.21. Please see Pay Application 1 for a full summary of the items completed that are included in
this payment.
Bolton & Menk, Inc. recommends the approval of Pay Application 1. Please let me know if you have any
questions.
Sincerely,
Bolton & Menk, Inc.
Justin Ernst, P.E.
Project Manager
6/13/23