HomeMy WebLinkAbout2023-06-19 I01H_15 West Area Trunk Sewer Extension Phase 2_Change Order 2AGENDA ITEM:
CITY OF WAUKEE, IOWA
CITY COUNCIL MEETING COMMUNICATION
MEETING DATE: June 19, 2023
AGENDA ITEM:Consideration of approval of Change Order No. 2 to Rognes Corporation
for the West Area Trunk Sewer Extension Phase 2 Project, in the amount
of $0.00
FORMAT:Consent Agenda
SYNOPSIS INCLUDING PRO & CON: Change Order No. 2 is for trenchless installation of
sanitary sewer across 310th Street.
FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS: The net result of this
Change Order does not change the contract price or completion date.
COMMISSION/BOARD/COMMITTEE COMMENT:
STAFF REVIEW AND COMMENT:
RECOMMENDATION: Approve the change order.
ATTACHMENTS: I. Change Order No. 2
II. Letter of Recommendation
PREPARED BY:Beth Richardson
REVIEWED BY:Sara Kappos SKK
PUBLIC NOTICE INFORMATION –
NAME OF PUBLICATION:
DATE OF PUBLICATION:
I1H15
June 13, 2023
Rudy Koester
Director of Public Works
City of Waukee
805 University Avenue
Waukee, Iowa 50263
CITY OF WAUKEE, IOWA
WEST AREA TRUNK SEWER EXTENSION – PHASE 2
CHANGE ORDER NO. 2
PAY ESTIMATE NO. 9
Enclosed are three signed copies of Change Order No. 2 and Pay Estimate No. 9 in accordance with
the contract between the City of Waukee and Rognes Corporation for the West Area Trunk Sewer
Extension – Phase 2 Project. The partial payment estimate is for the period of May 1, 2023 to May
31, 2023.
Change Order No. 2 is for trenchless installation of sanitary sewer across 310th Street.
We have checked and recommend approval of Pay Estimate No. 9. We recommended payment to
Rognes Corporation in the amount of $66,910.73. Pay Estimate No. 9 is for sanitary sewer
construction and Change Order No. 2
Please sign all copies of Change Order No. 2 and Pay Estimate No. 9 in the spaces provided. Please
return one set of signed copies to Veenstra & Kimm, Inc. and forward one set of copies to Rognes
Corporation with payment.
If you have any questions or comments, please contact us at 515-225-8000.
VEENSTRA & KIMM, INC.
Andy Willcuts
ARW:paj
275352
Enclosures
cc: Rognes Corporation
Sara Kappos, City of Waukee – w/enclosure (email)
Becky Schuett, City of Waukee – w/enclosure (email)
Beth Richardson, City of Waukee – w/enclosure (email)
Rachel Bruns, City of Waukee – w/enclosure (email)
Tracy Lovetinsky, City of Waukee – w/enclosure (email)
275352 Page 1 of 1
June 13, 2023 CHANGE ORDER NO. 2
WAUKEE, IOWA
WEST AREA TRUNK SEWER EXTENSION ‐ PHASE 2
Change Order No. 2 is to document modifications to the construction contract for the West Area
Trunk Sewer Extension ‐ Phase 2 project.
Item Description Unit Quantity Unit Price Total Price
1.5 Granular Surfacing SY ‐205 $20.00 ($4,100.00)
1.17 24" Sanitary Sewer in Place LF ‐60 $309.00 ($18,540.00)
3.1 24" Sanitary Sewer, Trenchless EA
60 $377.33 $22,640.00
Total $0.00
Change Order No. 2 does not change the contract price.
ROGNES CORPORATION CITY OF WAUKEE, IOWA
By By
Title Title
Date Date
VEENSTRA & KIMM, INC. ATTEST:
By By
Title Project Engineer Title
Date Date