Loading...
HomeMy WebLinkAbout2023-07-10 J01G_07 Douglas Pkwy Extension_Change Order 3AGENDA ITEM: CITY OF WAUKEE, IOWA CITY COUNCIL MEETING COMMUNICATION MEETING DATE: July 10, 2023 AGENDA ITEM:Consideration of approval of Change Order No. 3 to Absolute Concrete for the Douglas Parkway Extension project increasing the contract amount by $6,682.50. FORMAT:Consent Agenda SYNOPSIS INCLUDING PRO & CON: Change Order No. 3 includes the final construction quantity adjustment required for contract closeout. FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS: The net result of this Change Order increases the contract price in the amount of $6,682.50. COMMISSION/BOARD/COMMITTEE COMMENT: STAFF REVIEW AND COMMENT: RECOMMENDATION: Approve the change order. ATTACHMENTS: I. Change Order No. 3 II. Letter of Recommendation PREPARED BY:Beth Richardson REVIEWED BY:Sara Kappos SKK PUBLIC NOTICE INFORMATION – NAME OF PUBLICATION: DATE OF PUBLICATION: J1G7 H:\WAUKEE_CI_IA\A13122515_Douglas Parkway Extension\7_Construction\D1_Change Orders\CO 3\LTR-Douglas Parkway Extension-CO 003.docx June 19, 2023 Mr. Rudy Koester Public Works Director City of Waukee, Iowa RE: Douglas Parkway Extension Change Order 3 Dear Mr. Koester: Submitted for your approval is Change Order 3 for the above-mentioned project. Change Order 3 includes the final construction quantity adjustment required for contract closeout. The change order finalizes the total contract amount for the project. The approved contract value of $977,835.88 will be increased $6,682.50 for a total final contract value of $984,518.38. Please see the Change Order 3 for a full summary of the change items. Bolton & Menk, Inc. recommends the approval of Change Order 3. Sincerely, Bolton & Menk, Inc. Justin Ernst, P.E. Project Manager Owner: Contractor: City of Waukee Absolute Concrete 805 University Ave 1000 W. 6th Avenue Waukee, IA 50263 Slater, IA 50244 4 SY $ 7.00 (5,271.00) $ (36,897.00) 32 SY $ 69.50 302.70 $ 21,037.65 33 SY $ 125.00 75.15 $ 9,393.75 34 SY $ 12.50 23.89 $ 298.63 38 SY $ 175.00 15.73 $ 2,752.75 44 SF $ 75.00 48.00 $ 3,600.00 46 AC $ 4,000.00 0.18 $ 720.00 47 AC $ 3,500.00 0.95 $ 3,325.00 50 TON $ 100.00 54.74 $ 5,474.00 51 TON $ 95.00 52.55 $ 4,992.25 52 LF $ 1.70 (11.00) $ (18.70) 53 AC $ 1,600.00 1.88 $ 3,008.00 54 EA $ 160.00 (15.00) $ (2,400.00) CO1.1 LF $ 43.57 (199.00) $ (8,670.43) CO1.3 EA $ 1,548.45 (2.00) $ (3,096.90) CO1.4 EA $ 3,163.50 1.00 $ 3,163.50 $ 6,682.50 $ 919,069.00 52,483.10$ $ 58,766.88 6,283.78$ $ 977,835.88 -$ $ 6,682.50 -$ $ 984,518.38 $ 58,766.88 0.68% 311 6/19/2023 TEMPORARY EROSION CONTROL MULCHING, HYDROMULCHING INLET PROTECTION DEVICE, INSTALL, MAINTAIN, AND REMOVE 6-inch PERFORATED TILE HYDROSEEDING, TYPE 1 URBAN, FERTILIZING, AND MULCHING HYDROSEEDING, TYPE 2 URBAN, FERTILIZING, AND MULCHING CHECK DAM, ROCK RIP RAP, CLASS 'E' SILT FENCE, INSTALL, MAINTAIN, AND REMOVAL PAVEMENT, PCC, 9" FULL DEPTH CONCRETE MEDIAN REMOVAL OF SIDEWALK FULL DEPTH PATCHES TYPE A SIGN, SHEET ALUMINUM 8/12/2022 $919,069.00 Recommended By: 3Change Order Number CHANGE ORDER SUMMARY TOTAL EXISTING STORM SEWER ROCK CHIMNEY SUBGRADE TREATMENT, FLY ASH OR CEMENT 6-inch DRAIN TILE CLEANOUTS Description Date THE CONTRACT IS CHANGED AS FOLLOWS: This change order is reconcilliation of project quantities to obtain final contract amount. Item Value AdjustmentQuantity Adjustment Contractor: Name: Eli Hartog Title: Project Manager Change Order 4 TOTAL Date: Signature: CHANGE ORDER 3 Date: Signature: Name: Justin Ernst, P.E. Title: Project Manager NOT VALID UNTIL SIGNED BY THE CONTRACTOR, OWNER'S REPRESENTATIVE (if applicable) AND OWNER Bolton & Menk, Inc. Approved By: City of Waukee Signature: Name: Brad Deets Orig. Contract Amount Title: City Administrator Date: Absolute Concrete The Original Contract Sum was Net Change by previously authorized Change Orders The Contract Sum prior to This Change Order was The Contract Sum will be revised by this Change Order in the amount of The new Contract Sum including this Change Order will be Aggregate Change Order as a percent of Original Contract The Contract Time will be changed by The date of Final Completion as of the date of this Change Order therefore is Previously Approved Change Orders Change Order 1 Change Order 2 Change Order 3 Orig. Contract Date Douglas Parkway ExtensionProject Title 6/21/2021 Unit PriceUnit 6/19/2023 Completion Date 1 of 1H:\WAUKEE_CI_IA\A13114815_Sugar Creek GC Irrigation Well\7_Construction\E_Pay Applications\Sugar Creek Water Supply Change Order 1.xlsx DocuSign Envelope ID: CC7942D1-2D22-4DD7-ADD8-613EA09BD0B7 June 13, 2023 June 13, 2023