CITY OF WAUKEE, IOWA
CITY COUNCIL MEETING COMMUNICATION
MEETING DATE: August 7, 2023
AGENDA ITEM:Consideration of approval of Payment Estimate No. 3 to Progressive
Structures, LLC for the NW Sunrise Drive Culvert Project, in the amount
of $17,708.00
FORMAT:Consent Agenda
SYNOPSIS INCLUDING PRO & CON: Progressive Structures, LLC requested Payment
Estimate No. 3 for the work completed on the NW Sunrise Drive Culvert
Project, in the amount of $17,708.00. WHKS & Co. has reviewed the
payment estimate and recommends payment.
The partial payment is for the pay period ending July 31, 2023. This pay estimate is for
ornamental metal railing on the culvert headwalls.
FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS: $17,708.00
COMMISSION/BOARD/COMMITTEE COMMENT:
STAFF REVIEW AND COMMENT:
RECOMMENDATION: Approve Payment Estimate No. 3
ATTACHMENTS: I. Payment Estimate No. 3
II. Letter of Recommendation
PREPARED BY:Beth Richardson
REVIEWED BY:Sara Kappos SKK
PUBLIC NOTICE INFORMATION –
NAME OF PUBLICATION:
DATE OF PUBLICATION:
J1F3
3737 Woodland Avenue, Suite 111
West Des Moines, IA 50266
Phone: 515.226.8859
Email: desmoines@whks.com
Website: www.whks.com
August 1, 2023
Mr. Rudy Koester, P.E.
Public Works Director / City Engineer
City of Waukee
805 University Avenue
Waukee, IA 50263
RE: City of Waukee
NW Sunrise Drive Culvert (STORM 24-01)
Pay Estimate No. 3
Dear Mr. Koester:
Enclosed is Pay Estimate No. 3 for the above reference project. We have coordinated with the
Contractor and City staff performing field observation regarding the actual work completed to date
and recommend the City make payment in the amount of $17,708.00 to:
Progressive Structures, LLC
315 Commercial Ave.
PO Box 170
Luxemburg, IA 52056
5% retainage in the amount of $932.00 (for this pay application, $18,116.05 total) should be held
by the City until 30 days after project acceptance and completion of any punch list items are
completed to the satisfaction of the City.
Please contact us if you have any questions.
Sincerely,
WHKS & CO.
Casey V. Faber, P.E.
Project Manager
cc (w/ enclosures):
Sara Kappos, City of Waukee
Scott Campbell, City of Waukee
Travis Augustyn, Progressive Structures, LLC
Melissa Schilling, Progressive Structures, LLC
3737 Woodland, Suite 111
West Des Moines, IA 50266
363,898.48$
Project:Precast Reinforced Box Culvert Replacment
Project No.:STORM 24-01 Date:8/1/2023
Location:NW Sunrise Drive Culvert Estimate No.:3
Contractor:Progressive Structures, LLC % Complete:99.6%
1 EMBANKMENT-IN-PLACE CY $16.00 515.0 $8,240.00 515.0 0.0 515.00 100%8,240.00$
2 EXCAVATION, CLASS 10, CHANNEL CY $4.25 378.0 $1,606.50 378.0 0.0 378.00 100%1,606.50$
3 FLOODED BACKFILL CY $50.00 133.0 $6,650.00 133.0 0.0 133.00 100%6,650.00$
4 EXCAVATION, CLASS 20 CY $9.00 570.0 $5,130.00 570.0 0.0 570.00 100%5,130.00$
5 GRANULAR MATERIAL FOR BLANKET CY $74.50 127.0 $9,461.50 127.0 0.0 127.00 100%9,461.50$
6 ORNAMENTAL METAL RAILING LF $200.00 93.2 $18,640.00 0.0 93.2 93.20 100%18,640.00$
7 PRECAST CONCRETE BOX CULVERT, 12 FT. X 5 FT.LF $1,150.00 162.0 $186,300.00 162.0 0.0 162.00 100%186,300.00$
8 PRECAST CONCRETE BOX CULVERT STRAIGHT END SECTION, 12 FT. X 5 FT.EACH $19,250.00 4 $77,000.00 4.0 0.0 4.00 100%77,000.00$
9 TEMPORARY STREAM DIVERSION EACH $1,650.00 1 $1,650.00 1.0 0.0 1.00 100%1,650.00$
10 ENGINEERING FABRIC SY $4.75 390.1 $1,852.98 390.1 0.0 390.10 100%1,852.98$
11 REVETMENT, CLASS E TON $75.00 336.3 $25,222.50 333.4 0.0 333.40 99%25,005.00$
12 MOBILIZATION LS $17,000.00 1.00 $17,000.00 1.0 0.0 1.00 100%17,000.00$
13 CONSTRUCTION SURVEY LS $3,000.00 1.00 $3,000.00 1.0 0.0 1.00 100%3,000.00$
14 SAFETY CLOSURE EACH $500.00 1 $500.00 1.0 0.0 1.00 100%500.00$
15 STABILIZED CONSTRUCTION ENTRANCE, EC-303 LF $9.50 30.0 $285.00 30.0 0.0 30.00 100%285.00$
16 PERIMETER AND SLOPE SEDIMENT CONTROL DEVICE, 12 IN. DIA.LF $4.00 340.0 $1,360.00 0.0 0.0 0.00 0%-$
362,320.98$
PARTIAL PAYMENT ESTIMATE
FOR CONSTRUCTION WORK COMPLETED
Contract Bid Price:
Line No.Description Unit Unit Price
Contract
Quantity Contract Cost
Quantity
Completed Previous
Estimate
Quantity
Completed This
Estimate
Total Quantity
Completed to Date
Percent
Complete
Total Dollars To
Date
1 of 2
3737 Woodland, Suite 111
West Des Moines, IA 50266
363,898.48$
Project:Precast Reinforced Box Culvert Replacment
Project No.:STORM 24-01 Date:8/1/2023
Location:NW Sunrise Drive Culvert Estimate No.:3
Contractor:Progressive Structures, LLC % Complete:99.6%
PARTIAL PAYMENT ESTIMATE
FOR CONSTRUCTION WORK COMPLETED
Contract Bid Price:
Line No.Description Unit Unit Price
Contract
Quantity Contract Cost
Quantity
Completed Previous
Estimate
Quantity
Completed This
Estimate
Total Quantity
Completed to Date
Percent
Complete
Total Dollars To
Date
Change Order Items
-$
DIV. 1
Total Contract Dollars 363,898.48$
Contract Complete Dollars 362,320.98$
Change Order Dollars -$
Less Retainage 18,116.05$
Less Previous Estimates 326,496.93$
Net Payment This Estimate 17,708.00$
Recommended by:________________________________________________________________
Date
Agreed to by:________________________________________________________________
Date
Approved by:________________________________________________________________
Date