HomeMy WebLinkAbout2023-09-18 I01F_10 NW Sunrise Dr Culvert_Pmt Est 4-FinalAGENDA ITEM:
CITY OF WAUKEE, IOWA
CITY COUNCIL MEETING COMMUNICATION
MEETING DATE: September 18, 2023
AGENDA ITEM:Consideration of approval of Payment Estimate No. 4 to Progressive
Structures, LLC for the NW Sunrise Drive Culvert Project, in the amount
of $684.00
FORMAT:Consent Agenda
SYNOPSIS INCLUDING PRO & CON: Progressive Structures, LLC requested Payment
Estimate No. 4 for the work completed on the NW Sunrise Drive Culvert
Project, in the amount of $684.00. WHKS & Co. has reviewed the
payment estimate and recommends payment.
The partial payment is for the pay period ending August 31, 2023. This pay estimate is for
perimeter and slope sediment control device.
FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS: $684.00
COMMISSION/BOARD/COMMITTEE COMMENT:
STAFF REVIEW AND COMMENT:
RECOMMENDATION: Approve Payment Estimate No. 4
ATTACHMENTS: I. Payment Estimate No. 4
II. Letter of Recommendation
PREPARED BY:Beth Richardson
REVIEWED BY:Sara Kappos SKK
PUBLIC NOTICE INFORMATION –
NAME OF PUBLICATION:
DATE OF PUBLICATION:
I1F10
3737 Woodland Avenue, Suite 111
West Des Moines, IA 50266
Phone: 515.226.8859
Email: desmoines@whks.com
Website: www.whks.com
September 7, 2023
Mr. Rudy Koester, P.E.
Public Works Director / City Engineer
City of Waukee
805 University Avenue
Waukee, IA 50263
RE: City of Waukee
NW Sunrise Drive Culvert (STORM 24-01)
Change Order No. 1 / Pay Estimate No. 4 - Final / Project Acceptance
Dear Mr. Koester:
We have coordinated with the Contractor and City staff performing field observation and find the
above referenced project to be in substantial completion. As such you will find the following
enclosures:
• Change Order No. 1
• Pay Estimate No. 4
• Project Acceptance Certification
Change Order No. 1 is a balancing change order for the above referenced project showing
adjustments to the contract bid quantities and dollars to reflect final constructed amounts. The
original contract amount was $363,898.48 and the final construction cost was $363,040.98. The
$857.50 decrease is due to the adjustment of contract quantities, there were no other change
orders.
Pay Estimate No. 4 is Final and includes Change Order No. 1. We have coordinated with the
Contractor and City staff performing field observation regarding the actual work completed to date
and recommend the City make payment in the amount of $684.00 to:
Progressive Structures, LLC
315 Commercial Ave.
PO Box 170
Luxemburg, IA 52056
5% retainage in the amount of $36.00 (for this pay application, $18,152.05 total) should be held
by the City until 30 days after project acceptance (as City Staff have communicated that all punch
list items have already been satisfactorily completed).
Additionally, we have coordinated with the Contractor and City staff performing field observation
and find the project to be in substantial compliance with the Plans, Specifications, and Change
Orders governing construction of this project as of September 5, 2023. As such, we recommend
the City accept the project which will initiate the start of the four-year maintenance bond as
specified in the contract documents. 30 days after project acceptance, we recommend the City
release the 5% held retainage in the amount of $18,152.05 to:
Mr. Koester
September 7, 2023
Page 2 of 2
Progressive Structures, LLC
315 Commercial Ave.
PO Box 170
Luxemburg, IA 52056
The Project Acceptance Certification should be executed following City Council action to accept
the project.
Please contact us if you have any questions.
Sincerely,
WHKS & CO.
Casey V. Faber, P.E.
Project Manager
cc (w/ enclosures):
Sara Kappos, City of Waukee
Scott Campbell, City of Waukee
Travis Augustyn, Progressive Structures, LLC
Melissa Schilling, Progressive Structures, LLC
3737 Woodland, Suite 111
West Des Moines, IA 50266
363,898.48$
Project:Precast Reinforced Box Culvert Replacment Total Contract Plus Change Orders:363,040.98$
Project No.:STORM 24-01 Date:9/5/2023
Location:NW Sunrise Drive Culvert Estimate No.:4 - Final
Contractor:Progressive Structures, LLC % Complete:100.0%
1 EMBANKMENT-IN-PLACE CY $16.00 515.0 $8,240.00 515.0 0.0 515.00 100%8,240.00$
2 EXCAVATION, CLASS 10, CHANNEL CY $4.25 378.0 $1,606.50 378.0 0.0 378.00 100%1,606.50$
3 FLOODED BACKFILL CY $50.00 133.0 $6,650.00 133.0 0.0 133.00 100%6,650.00$
4 EXCAVATION, CLASS 20 CY $9.00 570.0 $5,130.00 570.0 0.0 570.00 100%5,130.00$
5 GRANULAR MATERIAL FOR BLANKET CY $74.50 127.0 $9,461.50 127.0 0.0 127.00 100%9,461.50$
6 ORNAMENTAL METAL RAILING LF $200.00 93.2 $18,640.00 93.2 0.0 93.20 100%18,640.00$
7 PRECAST CONCRETE BOX CULVERT, 12 FT. X 5 FT.LF $1,150.00 162.0 $186,300.00 162.0 0.0 162.00 100%186,300.00$
8 PRECAST CONCRETE BOX CULVERT STRAIGHT END SECTION, 12 FT. X 5 FT.EACH $19,250.00 4 $77,000.00 4.0 0.0 4.00 100%77,000.00$
9 TEMPORARY STREAM DIVERSION EACH $1,650.00 1 $1,650.00 1.0 0.0 1.00 100%1,650.00$
10 ENGINEERING FABRIC SY $4.75 390.1 $1,852.98 390.1 0.0 390.10 100%1,852.98$
11 REVETMENT, CLASS E TON $75.00 336.3 $25,222.50 333.4 0.0 333.40 99%25,005.00$
12 MOBILIZATION LS $17,000.00 1.00 $17,000.00 1.0 0.0 1.00 100%17,000.00$
13 CONSTRUCTION SURVEY LS $3,000.00 1.00 $3,000.00 1.0 0.0 1.00 100%3,000.00$
14 SAFETY CLOSURE EACH $500.00 1 $500.00 1.0 0.0 1.00 100%500.00$
15 STABILIZED CONSTRUCTION ENTRANCE, EC-303 LF $9.50 30.0 $285.00 30.0 0.0 30.00 100%285.00$
16 PERIMETER AND SLOPE SEDIMENT CONTROL DEVICE, 12 IN. DIA.LF $4.00 340.0 $1,360.00 0.0 180.0 180.00 53%720.00$
363,040.98$
PARTIAL PAYMENT ESTIMATE
FOR CONSTRUCTION WORK COMPLETED
Contract Bid Price:
Line No.Description Unit Unit Price
Contract
Quantity Contract Cost
Quantity
Completed Previous
Estimate
Quantity
Completed This
Estimate
Total Quantity
Completed to Date
Percent
Complete
Total Dollars To
Date
1 of 2
3737 Woodland, Suite 111
West Des Moines, IA 50266
363,898.48$
Project:Precast Reinforced Box Culvert Replacment Total Contract Plus Change Orders:363,040.98$
Project No.:STORM 24-01 Date:9/5/2023
Location:NW Sunrise Drive Culvert Estimate No.:4 - Final
Contractor:Progressive Structures, LLC % Complete:100.0%
PARTIAL PAYMENT ESTIMATE
FOR CONSTRUCTION WORK COMPLETED
Contract Bid Price:
Line No.Description Unit Unit Price
Contract
Quantity Contract Cost
Quantity
Completed Previous
Estimate
Quantity
Completed This
Estimate
Total Quantity
Completed to Date
Percent
Complete
Total Dollars To
Date
Change Order Items
CO #Amount
1 (857.50)$
(857.50)$
DIV. 1
Total Contract Bid Dollars 363,898.48$
Contract Complete Dollars 363,040.98$
Change Order Dollars (857.50)$
Less Retainage 18,152.05$
Less Previous Estimates 344,204.93$
Net Payment This Estimate 684.00$
Recommended by:________________________________________________________________
Date
Agreed to by:________________________________________________________________
Date
Approved by:________________________________________________________________
Date
Description/Notes
Adjustment of contract quantities to actual final constructed quantities
2 of 2
9-6-2023
09/06/2023