HomeMy WebLinkAbout2023-10-16 I08A SE Ashworth Rd, SE Parkview Crossing Dr to SE Glacier Trl_Change Order 6AGENDA ITEM: CITY OF WAUKEE, IOWA CITY COUNCIL MEETING COMMUNICATION MEETING DATE: October 16, 2023 AGENDA ITEM:Consideration of approval of Change Order No. 6 to Alliance Construction for the SE Ashworth Road Corridor Improvements – SE Parkview Crossing Drive to SE Glacier Trail Project decreasing the contract amount by $56,642.67. FORMAT:Motion SYNOPSIS INCLUDING PRO & CON: Change Order No. 6 is to adjust the plan quantities to the as-constructed quantities for the project. FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS: The net result of this Change Order decreases the contract price in the amount of $56,642.67. COMMISSION/BOARD/COMMITTEE COMMENT: STAFF REVIEW AND COMMENT: RECOMMENDATION: Approve the change order. ATTACHMENTS: I. Change Order No. 6 II. Letter of Recommendation PREPARED BY:Beth Richardson REVIEWED BY:Sara Kappos SKK PUBLIC NOTICE INFORMATION – NAME OF PUBLICATION: DATE OF PUBLICATION: I8A 8191 Birchwood Court, Suite L Johnston, IA 50131 Phone: (515) 254-1393 October 6, 2023 Sara Kappos, P.E. Assistant Public Works Director 805 University Avenue Waukee, IA 50263 RE: Change Order #6 SE Ashworth Road Corridor Improvements – SE Parkview Crossing Drive to SE Glacier Trail Dear Ms. Kappos: Attached please find a detailed Change Order for City Council approval on October 16, 2023. Change Description: o Zero-Out change to match contract quantity to as-built quantity. If City Staff concurs with this pricing, we recommend the City of Waukee revise the contract price in the amount of -$56,642.67 to complete the additional work associated with Change Order #6. If you have any questions, please contact me. Sincerely, Foth Infrastructure & Environment, LLC Andy Floy, P.E. Lead Civil Engineer Encl: Change Order #6 dated 10/01/2023 CHANGE ORDER 06 Distribution: Owner - Finance ____ Owner - Public Works ____ Engineer ____ Contractor ____ Contractor:Alliance Construction Group 3000 SE Grimes Blvd, Suite 800 Grimes, Iowa 50111 $4,510,016.01 February 22, 2021 2.4 CY $3.25 0.30 $0.98 2.6 CY $3.50 -5677.00 ($19,869.50) 2.9 EA $2,000.00 1.00 $2,000.00 4.1 LF $900.00 -6.50 ($5,850.00) 4.2 LF $100.00 0.50 $50.00 4.4 LF $91.00 15.00 $1,365.00 4.14 LF $16.35 2619.94 $42,836.02 4.16 EA $235.00 4.00 $940.00 4.19 EA $9.00 -230.00 ($2,070.00) 5.1 LF $48.00 5.00 $240.00 5.4 LF $78.00 -5.00 ($390.00) 5.5 LBS $8.00 -1878.00 ($15,024.00) 5.7 EA $1,100.00 -2.00 ($2,200.00) 5.8 EA $1,500.00 -1.00 ($1,500.00) 5.9 EA $6,400.00 -1.00 ($6,400.00) 5.15 EA $15,500.00 -1.00 ($15,500.00) 7.1 SY $60.00 70.00 $4,200.00 7.2 SY $65.25 125.50 $8,188.88 7.5 TON $30.00 -260.66 ($7,819.80) 7.6 SY $10.00 17.70 $177.00 7.10 SY $66.00 17.70 $1,168.20 7.12 SF $50.00 20.00 $1,000.00 7.15 SY $6.00 834.98 $5,009.88 7.16 SY $53.00 -164.52 ($8,719.56) 8.2 STA $89.00 40.70 $3,622.30 8.3 STA $210.00 -60.80 ($12,768.00) 8.8 EA $200.00 1.00 $200.00 8.12 CDAY $120.00 12.00 $1,440.00 Department of Public Works 805 University Avenue Waukee, IA 50263 (515) 987-7920 Fax (515) 987-3979 Date Change Order Number Quantity AdjustmentUnit Price THE CONTRACT IS CHANGED AS FOLLOWS: Zero out change order to match as-built quantities. Item CodeItem No. September 30, 2023 Unit 4040-D-1000 SPECIAL 5010-A-1016 5010-A-1016 SE Ashworth Road Corridor Improvements SE Parkview Crossing to SE Glacier 6 19W019.01 Waukee Project File Number Project Title BELOW GRADE EXCAVATION (CORE OUT) Description 2010-F-1000 2010-J-1000 4010-A-1018 4010-A-2108 4020-A-1324 4040-A-1106 Foth Project File Number Orig. Contract Amount & Date Value Adjustment WATER MAIN, TRENCHED, RESTRAINED JOINT, PVC C900, DR18, 16 IN. WATER MAIN FITTINGS VALVE, GATE, 6 IN. VALVE, GATE, 8 IN. VALVE, GATE, 16 IN. SPECIAL SPECIAL 7030-G-1000 7040-H-1000 SPECIAL 8020-C-1000 8020-F-1000 7010-A-1108 7010-A-1110 7010-J-1000 7030-A-1020 7030-E-1006 5020-C-1000 5020-C-1000 5020-C-1000 5020-C-1000 5020-C-1000 REMOVAL OF STRUCTURE, CONCRETE FOOTING SANITARY SEWER GRAVITY MAIN, TRENCHED, PVC, 18 IN. SANITARY SEWER GRAVITY MAIN, TRENCHLESS, PVC, 8 IN. STORM SEWER, TRENCHED, RCP, CLASS III, 24 IN. SUBDRAIN, PVC, 6 IN. SUBDRAIN, OUTLET, CONNECTION TO INTAKE OR PIPE CORE DRILL STRUCTURES FOR SUBDRAIN WATER MAIN, TRENCHED, PVC C900, DR18, 16 IN. PAVEMENT REMOVAL TEMPORARY PAVEMENT, HMA OR PCC, 8 IN. PAINTED PAVEMENT MARKINGS, DURABLE HORIZONTAL RELOCATION OF WATER MAIN, 16 IN. PAVEMENT, PCC, CLASS C, 8 IN. PAVEMENT, PCC, CLASS C-SUD, 10 IN. GRANULAR SURFACING, CLASS-A CRUSHED STONE, 6 IN. REMOVAL OF SIDEWALK, SHARED USE PATH OR DRIVEWAY 2010-E-1010 EXCAVATION, CLASS 10, ROADWAY & BORROW WET, RETROREFLECTIVE REMOVABLE TAPE MARKINGS POSTS FOR SIGNS, STEEL PORTABLE DYNAMIC MESSAGE SIGNS SIDEWALK, PCC, 6 IN. DETECTABLE WARNING CO#06 - 2023-0930-SE Ashworth Road Corridor Improvents.xlsx Change Order 1 Page 1 of 2 8.19 EA $1,525.00 4.00 $6,100.00 8.24 LS $20,000.00 -1.00 ($20,000.00) 9.1 AC $925.00 -1.50 ($1,387.50) 9.2 AC $525.00 -1.62 ($850.50) 9.3 AC $250.00 -9.70 ($2,425.00) 9.5 LF $2.25 -4715.00 ($10,608.75) 9.6 LF $0.50 -4715.00 ($2,357.50) 9.7 SY $1.75 -306.00 ($535.50) 9.10 LF $1.50 -2984.00 ($4,476.00) 9.11 LF $0.10 -579.10 ($57.91) 9.12 LF $0.10 -2984.00 ($298.40) 9.13 AC $500.00 -9.70 ($4,850.00) 9.14 AC $2,200.00 3.41 $7,502.00 9.15 EA $175.00 15.00 $2,625.00 9.16 Ea $50.00 13.00 $650.00 $0.00 $0.00 $0.00 ($56,642.67) $4,510,016.01 $32,936.39 $4,542,952.40 ($56,642.67) $4,486,309.73 0 Days Recommended By: Alliance Construction Group Signature: Name: Ryan McKinney Title: Project Manager Date: Owner:City of Waukee □ ≤$500 Department Director X_______________________________________Date___________________ □ $501 to $2,500 City Administrator X_______________________________________Date___________________ □ Date___________________ □ >$2,501 City Council approved or ratified at Council meeting on Date___________________ Date: The Contract Time will be increased by City of Waukee CHANGE ORDER SUMMARY NOT VALID UNTIL SIGNED BY THE CONTRACTOR, OWNER'S REPRESENTATIVE (if applicable) AND OWNER The Original Contract Sum was The new Contract Sum including this Change Order will be Signature: Date: Name: Brad Deets Title: Lead Civil Engineer Signature: The Contract Sum will be increased by this Change Order in the amount of Net Change by previously authorized Change Orders Title: City Administrator Foth Infrastructure & Environment, LLC Name: Andy Floy, P.E. The Contract Sum prior to This Change Order was Prepared By:Checked By: SPECIAL SPECIAL 9010-A-1100 9010-A-1200 9010-A-1400 9040-D-1012 9040-D-2000 9040-E-1000 9040-N-1000 9040-N-2000 CONVENTIONAL SEEDING & FERTILIZING, TYPE 1 (PERMANENT LAWN MIXTURE) CONVENTIONAL SEEDING & FERTILIZING, TYPE 2 (PERMANENT COOL-SEASON MIX) CONVENTIONAL SEEDING, TYPE 4 (URBAN TEMPORARY EROSION CONTROL MIXTURE) SILT FENCE OR SILT FENCE DITCH CHECK, REMOVAL OF DEVICE EROSION CONTROL MULCHING, CONVENTIONAL EROSION CONTROL MULCHING, HYDROMULCHING INLET PROTECTION DEVICE, DROP-IN TYPE INLET PROTECTION DEVICE, MAINTENANCE 9040-N-3000 9040-Q-1000 9040-Q-2000 9040-T-1000 9040-T-2000 FILTER SOCKS, 12 IN. FILTER SOCKS, REMOVAL TEMPORARY ROLLED EROSION CONTROL PRODUCTS (RECP), TYPE 3B SILT FENCE OR SILT FENCE DITCH CHECK SILT FENCE OR SILT FENCE DITCH CHECK, REMOVAL OF SEDIMENT HANDHOLE, TYPE IV, FURNISH AND INSTALL TEMPORARY SIGNAL CO#06 - 2023-0930-SE Ashworth Road Corridor Improvents.xlsx Change Order 1 Page 2 of 2