HomeMy WebLinkAbout2023-11-20 I01D_03 Public Works Site Expansion Phase 1_Change Order 5AGENDA ITEM:
CITY OF WAUKEE, IOWA
CITY COUNCIL MEETING COMMUNICATION
MEETING DATE: November 20, 2023
AGENDA ITEM:Consideration of approval of Change Order No. 5 to Core Construction
Services for the Waukee Public Works Site Expansion– Phase 1 project
increasing the contract amount by $5,655.20
FORMAT:Consent Agenda
SYNOPSIS INCLUDING PRO & CON: Change Order No. 5 is for the (6) specified 24V
lockset bodies be changed to 12V lockset bodies for Hardware Group No. 1 to coordinate with
the power supplies provided under separate contract.
FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS: The net result of this
Change Order increases the contract price in the amount of $5,655.20
COMMISSION/BOARD/COMMITTEE COMMENT:
STAFF REVIEW AND COMMENT:
RECOMMENDATION: Approve the change order.
ATTACHMENTS: I. Change Order No. 5
II. Letter of Recommendation
PREPARED BY:Beth Richardson
REVIEWED BY:Sara Kappos SKK
PUBLIC NOTICE INFORMATION –
NAME OF PUBLICATION:
DATE OF PUBLICATION:
I1D3
ENGINEERS | ARCHITECTS | SURVEYORS | SCIENTISTS
14225 University Avenue, Suite 110
Waukee, Iowa 50263
p 515.225.3469
www.f-w.com
November 15, 2023
City of Waukee
805 University Avenue
Waukee, Iowa 50263
Attn: Rudy Koester, Public Works Director
Re: Change Order #005
Waukee Public Works Site Expansion Phase 1
Dear Mr. Koester:
Attached please find a detailed Change Order for City Council approval on November 20, 2023.
Change Description:
1. COR-021:
Specification Section – 08 7100 Door Hardware
a. City staff requested the (6) specified 24V lockset bodies be changed to 12V lockset
bodies for Hardware Group No. 1 to coordinate with the power supplies provided under
separate contract. Core submitted a price to replace these (6) lockset bodies for an
additional cost of $5,655.20.
We have reviewed the submitted Change Order Requests (CORs) from Core Construction, and the
Design Team considers them to be in line with current industry pricing. If City Staff concurs with these
proposed additional costs, then we recommend the City of Waukee Increase the contract price in the
amount of $5,655.20 to complete the additional work associated with Change Order Number 005. If you
have any questions, please contact me.
Sincerely,
FARNSWORTH GROUP, INC.
Kristofer J. Orth, AIA
Architecture Principal
Enclosures: Change Order #005, dated November 15, 2023
11/15/2023
CHANGE ORDER NO. 5 - SUMMARY
Waukee Public Works - Site Expansion Phase 1
Date:11/15/23
Original Contract Price:$5,922,700.00
Change Orders approved to date:$61,199.31
CHANGE ORDER ITEMS
1)COR-21 Change Door Hardware from 24V to 12V $5,655.20
TOTAL Changes:$5,655.20
Amount of this change order:$5,655.20
Adjusted contract price including this change order:$5,989,554.51
14225 University Avenue, Suite 110 | Waukee, IA 50263 | p 515.225.3469 | www.f-w.com
ENGINEERS | ARCHITECTS | SURVEYORS | SCIENTISTS
11-13-23
Kristofer Orth
14225 University Ave, Suite 110
Waukee IA 50263
RE: 21114 Waukee Public Works-Site Expansion Phase 1 COR-21
Dear Kristofer:
Core proposes the following as a change in the Work:
Change Hardware from 24V to 12V
Proposed change in contract sum add $5655.20 if approved by 11-17-23.
Proposed change in schedule 00 days if approved by 11-17-23 Should approval be granted after this deadline, the
schedule shall be extended further beyond the proposed change the same number of days.
An estimate and back up is attached. Please review and authorize one of the actions below. If you have any questions,
please contact me at your earliest convenience. Thank you.
Sincerely,
Jeremy Roush
Project Manager
Cc: Sasha Daljevic
Rudy Koester
Sara Kappos
□ Approved, incorporate change immediately
□ Pending, continue work per current contract
□ Pending, stop affected work until action taken (hold time past deadline above will be added to the proposed
change in schedule)
□ Rejected
The above action is authorized below by a duly authorized representative of the Owner and Architect:
Owner: Architect:
Signature ___________________________________ Signature ___________________________________
Name ______________________________________ Name ______________________________________
Title ________________________________________ Title ________________________________________
Date _______________________________________ Date _______________________________________
COR #021 Core Structural Services, LLC
3093 NW Prairie Lane
Des Moines, IA 50313
(515) 987-6830 Office
(515) 987-6830 Fax
TO: Farnsworth Group PROJECT NAME:
14225 University Ave Suite 110 PROJECT NUMBER:
Waukee IA 50263 SUBJECT:
FROM:
ATTN:DATE:
Unit Cost Total Unit Cost Total Unit Cost Total Unit Cost Total
81100 Change locks from 24V to 12V Walsh $ 1.00 $ 4,580.00 $ 4,580.00
5 $ 1.00 $ 300.00 $ 300.00
6
7
8
9
10
92
93
94
95
96
97
98
99
Subtotal -$ 4,580.00$ -$ 300.00$ 4,880.00$
Small Tools Allowance 10.00%
Warranty 0.00% 0.00% 0.00% 0.00%
Overhead & Profit 15.00% 15.00% $ 687.00 15.00% 5.00% $ 15.00 $ 702.00
Bond 1.50% 1.50% $ 68.70 1.50% 1.50% $ 4.50 $ 73.20
The Contract Schedule will Increase / Decrease by: days TOTAL COR:
Clarifications & Exclusions:
Waukee Public Works
21114
Door Changes
Jeremy Roush
5,655.20$
11/13/23
Item #/
Cost Code Description Sub/Vendor Quantity Unit
Labor Material Equipment Subcontractor TOTAL
21114.COR-Log.Waukee Public Works.xlsx Page 1
1
jeremyr@coreconstructionia.com
From:Fong Moua <fmoua@walshdoor.com>
Sent:Monday, October 30, 2023 8:23 AM
To:Steve Koester; jeremyr@coreconstructionia.com
Subject:Re: Waukee Public Works - Mortise Lock replacements Quote# 445660
Please add $300 for install
Fong Moua
Sales
Walsh Door and Security
2600 Delaware Avenue
Des Moines, IA 50317
P. 515.262.9822
C. 515.901.4084
Fmoua@walshdoor.com
www.walshdoor.com
From: Steve Koester <stevek@coreconstructionia.com>
Sent: Monday, October 30, 2023 7:49:48 AM
To: Fong Moua <fmoua@walshdoor.com>; jeremyr@coreconstructionia.com <jeremyr@coreconstructionia.com>
Subject: Re: Waukee Public Works - Mortise Lock replacements Quote# 445660
is this the price installed?
If not please provide alternate
Get Outlook for Android
From: Fong Moua <fmoua@walshdoor.com>
Sent: Monday, October 30, 2023 7:15:39 AM
To: jeremyr@coreconstructionia.com <jeremyr@coreconstructionia.com>; stevek@coreconstructionia.com
<stevek@coreconstructionia.com>
Subject: Waukee Public Works - Mortise Lock replacements Quote# 445660
Good morning,
We quote the following materials:
6 each Falcon Mortise lock bodies 12 volt
For a total sum of $4,580.
Quote is good for 30 days.
I should be able to get these within a week.
2
Please let me know if you would like me to get these ordered.
Thank you,
Fong Moua | Sales
Walsh Door & Security
2600 Delaware Avenue, Des Moines, IA 50317
p. 515.262.9822 | c. 515.901.4084
fmoua@WalshDoor.com | WalshDoor.com
1
jeremyr@coreconstructionia.com
From:Son Le <sle@waukee.org>
Sent:Thursday, November 2, 2023 11:59 AM
To:jeremyr@coreconstructionia.com; stevek@coreconstructionia.com; 'Orth, Kristofer'
Cc:Tim Royer; Sara Kappos; Rudy Koester
Subject:RE: Door hardware
Please move forward with changing 24v to 12v for the doors.
Thanks.
Son Le | Director of Information Technology
City of Waukee
805 University Ave, Waukee, IA 50263
O: 515-978-7945
sle@waukee.org | Waukee.org
CONFIDENTIALITY NOTICE: This e-mail message, including any attachments, is for the sole use of the intended
recipient(s) and may contain confidential, proprietary, and/or privileged information protected by law. If you
are not the intended recipient, you may not use, copy, or distribute this e-mail message or its attachments. If
you believe you have received this e-mail message in error, please contact the sender by reply e-mail and
telephone immediately and destroy all copies of the original message.
From: jeremyr@coreconstructionia.com <jeremyr@coreconstructionia.com>
Sent: Wednesday, November 1, 2023 8:28 AM
To: stevek@coreconstructionia.com; Rudy Koester <rkoester@waukee.org>; 'Orth, Kristofer' <korth@F-W.com>
Cc: Tim Royer <troyer@waukee.org>; Sara Kappos <skappos@waukee.org>; Son Le <sle@waukee.org>
Subject: RE: Door hardware
sophospsmartbannerend
I would prefer to keep this outside the contract though so it doesn’t hold up our reten=on. I will help with Walsh and
coordina=on as much as possible.
Note my email address has changed please update my contact info
Jeremy Roush
Project Manager / Estimator
3093 NW Prairie Ln, Des Moines IA 50313
Office 515/264-5156 x204 Cell 515/419-3700
Fax 515/257-4311
2
From: stevek@coreconstructionia.com <stevek@coreconstructionia.com>
Sent: Wednesday, November 1, 2023 8:15 AM
To: 'Rudy Koester' <rkoester@waukee.org>; jeremyr@coreconstructionia.com; 'Orth, Kristofer' <korth@F-W.com>
Cc: 'Tim Royer' <troyer@waukee.org>; 'Sara Kappos' <skappos@waukee.org>; 'Son Le' <sle@waukee.org>
Subject: RE: Door hardware
Thanks
Let me know If we can help with anything
Steve Koester
Project Superintendent
3093 NW Prairie Ln, Des Moines IA 50313
Office 515/264-5156 Cell 515/943-1372 FAX 515/257-4311
Coreconstructionia.com
From: Rudy Koester <rkoester@waukee.org>
Sent: Wednesday, November 1, 2023 7:47 AM
To: stevek@coreconstructionia.com; jeremyr@coreconstructionia.com; 'Orth, Kristofer' <korth@F-W.com>
Cc: Tim Royer <troyer@waukee.org>; Sara Kappos <skappos@waukee.org>; Son Le <sle@waukee.org>
Subject: RE: Door hardware
Steve, this is in Son’s court. He’s evalua=ng leaving them as 24v or having Core swap to the 12v version. He’ll have an
answer this week.
Rudy Koester | Director of Public Works/City Engineer
City of Waukee
805 University Ave, Waukee, Iowa 50263
O: 515-978-7388
rkoester@waukee.org | Waukee.org
CONFIDENTIALITY NOTICE: This e-mail message, including any attachments, is for the sole use of the intended
recipient(s) and may contain confidential, proprietary, and/or privileged information protected by law. If you
are not the intended recipient, you may not use, copy, or distribute this e-mail message or its attachments. If
you believe you have received this e-mail message in error, please contact the sender by reply e-mail and
telephone immediately and destroy all copies of the original message.
3
From: stevek@coreconstructionia.com <stevek@coreconstructionia.com>
Sent: Wednesday, November 1, 2023 7:44 AM
To: jeremyr@coreconstructionia.com; 'Orth, Kristofer' <korth@F-W.com>
Cc: Rudy Koester <rkoester@waukee.org>; Tim Royer <troyer@waukee.org>; Sara Kappos
<skappos@waukee.org>; Son Le <sle@waukee.org>
Subject: RE: Door hardware
sophospsmartbannerend
Where are we with this.
Do I need to follow up with any of the team or look at any other op=ons?
Steve Koester
Project Superintendent
3093 NW Prairie Ln, Des Moines IA 50313
Office 515/264-5156 Cell 515/943-1372 FAX 515/257-4311
Coreconstructionia.com
From: jeremyr@coreconstructionia.com <jeremyr@coreconstructionia.com>
Sent: Monday, October 30, 2023 11:15 AM
To: 'Orth, Kristofer' <korth@F-W.com>; Scarlett Deen <sdeen@sghconcepts.com>
Cc: Rudy Koester <rkoester@waukee.org>; Tim Royer <troyer@waukee.org>; Sara Kappos
<skappos@waukee.org>; stevek@coreconstructionia.com
Subject: Door hardware
To switch from 24 volt too 12 volt is going to be around $5200. Have you looked into have Tri-City making
changes to accommodate the 24 volt hardware? Im not sure which will be cheaper. Please advise.
Note my email address has changed please update my contact info
Jeremy Roush
Project Manager / Estimator
3093 NW Prairie Ln, Des Moines IA 50313
Office 515/264-5156 x204 Cell 515/419-3700
Fax 515/257-4311