HomeMy WebLinkAbout2023-11-20 I10A T Ave Corridor, W Hickman Rd to NW Douglas Pkwy_Change Order 1AGENDA ITEM:
CITY OF WAUKEE, IOWA
CITY COUNCIL MEETING COMMUNICATION
MEETING DATE: November 20, 2023
AGENDA ITEM:Consideration of approval of Change Order No. 1 to All-Star Concrete,
LLC for the T Avenue Corridor Improvements, W Hickman Road to NW
Douglas Parkway Project increasing the contract amount by $53,927.00.
FORMAT:Motion
SYNOPSIS INCLUDING PRO & CON: Plan change 1 decreased the amount of 12” RCP by
more than 20% so the contractor requested a bid item adjustment. Plan change 1 and 2 also
changed the building outlet piping. In addition, trail signage was needed on the bike trail to
increase safety and direct bikes/pedestrians to the detour. There was also a requested change from
the city to the video detection and signage at the traffic signal at T Avenue (NW 20th) and
Douglas. The remainder of adjustments are for quantity changes due to Plan Change 1 and 2
without price adjustments.
FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS: The net result of this
Change Order increases the contract price in the amount of $53,927.00.
COMMISSION/BOARD/COMMITTEE COMMENT:
STAFF REVIEW AND COMMENT:
RECOMMENDATION: Approve the change order.
ATTACHMENTS: I. Change Order No. 1
II. Letter of Recommendation
PREPARED BY:Beth Richardson
REVIEWED BY:Sara Kappos SKK
PUBLIC NOTICE INFORMATION –
NAME OF PUBLICATION:
DATE OF PUBLICATION:
I10A
8191 Birchwood Court, Suite L Johnston, IA 50131 Phone: (515) 254-1393
November 13, 2023
Sara Kappos, P.E.
Assistant Public Works Director
805 University Avenue
Waukee, IA 50263
RE: Change Order #1
T Avenue Corridor Improvements – W Hickman Road to NW Douglas Parkway
Dear Mrs. Kappos:
Attached please find a detailed Change Order for City Council approval on November 20, 2023.
Change Description:
Plan change 1 decreased the amount of 12" RCP by more than 20% so the contractor requested
a bid item adjustment. Plan change 1 and 2 also changed the building outlet piping. In addition,
trail signage was needed on the bike trail to increase safety and direct bikes/pedestrians to the
detour. There was also a r equested change from the city to the video detection and signage at
the traffic signal at T Ave (NW 20th) and Douglas. The remainder of adjustments are for quantity
changes due to Plan Change 1 and 2 without price adjustments.
We have reviewed the submitted quotes from All - Star and they appear to be in order with current
industry pricing. If City Staff concurs with this pricing, we recommend the City of Waukee
Increase the contract price in the amount of $53,927.00 to complete the additional work
associated with Change Order #1. If you have any questions, please contact me.
Sincerely,
Foth Infrastructure & Environment, LLC
Rob Kline, P.E.
Lead Civil Engineer
Encl: Change Order #1 dated 11/13/2023
CHANGE ORDER 01
Distribution:
Owner - Finance ____
Owner - Public Works ____
Engineer ____
Contractor ____
Contractor:All-Star Concrete LLC.
4989 NW Johnston Dr.
Johnston, Iowa 50131 $10,683,619.98 August 7, 2023
2.10 Division 2 2010-J-1006 CY $62.00 3.00 $186.00
4.1 Division 2 4010-A-1004 LF $85.00 11.00 $935.00
4.2 Division 2 4010-A-1006 LF $87.00 39.00 $3,393.00
4.14 Division 2 4020-A-1512 LF $75.00 -1125.00 ($84,375.00)
CO 4.14 Division 2 4020-A-1512 LF $85.00 752.00 $63,920.00
4.15 Division 2 4020-A-1515 LF $80.00 102.00 $8,160.00
4.24 Division 2 4030-B-1312 EA $2,320.00 -1.00 ($2,320.00)
4.25 Division 2 4030-B-1315 EA $2,430.00 1.00 $2,430.00
4.27 Division 2 4030-B-1324 EA $2,725.00 2.00 $5,450.00
4.31 Division 2 4040-A-1004 LF $18.00 -709.00 ($12,762.00)
4.33 Division 2 4040-C-1000 EA $1,455.00 -3.00 ($4,365.00)
4.34 Division 2 4040-D-1000 EA $550.00 -1.00 ($550.00)
4.39 Division 2 Special LF $85.00 91.00 $7,735.00
4.40 Division 2 Special LF $85.00 0.00 $0.00
4.41 Division 2 Special LF $90.00 0.00 $0.00
4.42 Division 2 Special LF $88.00 82.00 $7,216.00
5.8 Division 1 5010-C-1000 LF $19.00 1392.00 $26,448.00
6.3 Division 2 6010-A-1548 EA $3,600.00 1.00 $3,600.00
6.5 Division 1 6010-A-1560 EA $6,000.00 1.00 $6,000.00
6.5 Division 2 6010-A-1560 EA $6,000.00 -1.00 ($6,000.00)
6.13 Division 2 6010-B-1505 EA $6,100.00 -1.00 ($6,100.00)
6.14 Division 2 6010-B-1505 EA $10,000.00 1.00 $10,000.00
6.20 Division 2 6010-B-1512 EA $6,600.00 1.00 $6,600.00
8.1 Division 1 8010-A-1000 LS -$8,824.00 1.00 ($8,824.00)
8.19 Division 1 Special LS $4,400.00 1.00 $4,400.00
9.4 Division 1 9040-A-1500 AC $300.00 -9.10 ($2,730.00)
9.17 Division 1 Special AC $2,800.00 9.10 $25,480.00
$53,927.00
THE CONTRACT IS CHANGED AS FOLLOWS: Plan change 1 decreased the amount of 12" RCP by more than 20% so the contractor requested a bid item adjustment. Plan change
1 and 2 also changed the building outlet piping. In addition, trail signage was needed on the bike trail to increase safety and direct bikes/pedestrians to the detour. There was also
a requested change from the city to the video detection and signage at the traffic signal at T Ave (NW 20th) and Douglas. The remainder of adjustments are for quantity changes due
to Plan Change 1 and 2 without price adjustments.
T Avenue Corridor Improvements
W Hickman Rd to NW Douglas Pkwy
1
22W007.00
Waukee Project File Number
November 13, 2023
Foth Project File Number
Orig. Contract Amount & Date
Date
Change Order Number
Project Title
Department of Public Works
805 University Avenue
Waukee, IA 50263
(515) 987-7920 Fax (515) 987-3979
Value AdjustmentQuantity
AdjustmentUnit PriceDescriptionUnitItem No.
TRAFFIC SIGNALIZATION
STORM SEWER, TRENCHED, RCP, CLASS V, 12 IN.
TRAFFIC CONTROL FOR TRAIL DETOUR
CONVENTIONAL SEEDING, TYPE 5 (RURAL TEMPORARY EROSION CONTROL
MIX)
MULCHING FOR AREAS RETURNED TO FARM GROUND
INTAKE, SW-505, DOUBLE GRATE
INTAKE, SW-505, DOUBLE GRATE, MOD 1
INTAKE, SW-512, 36 IN.
STORM SEWER, TRENCHED, RCP, CLASS V, 15 IN.
PIPE APRON, CONCRETE, 12 IN.
MODIFIED SUBBASE, 6 IN.
SANITARY SEWER GRAVITY MAIN, TRENCHED, PVC, 4 IN.
SANITARY SEWER GRAVITY MAIN, TRENCHED, PVC, 6 IN.
Division Item Code
MANHOLE, STORM SEWER, SW-401, 60 IN.
WATER MAIN, TRENCHED, PVC C900, DR18, 6 IN.
MANHOLE, STORM SEWER, SW-401, 48 IN.
MANHOLE, STORM SEWER, SW-401, 60 IN.
STORM SEWER, TRENCHED, PVC, 10 IN. - added in PC1 / omitted PC2
STORM SEWER, TRENCHED, PVC, 15 IN. - added in PC1 / omitted in PC2
STORM SEWER, TRENCHED, PVC, 12 IN.
SUBDRAIN CLEANOUT, TYPE A-1
SUBDRAIN, OUTLET, CONNECTION TO INTAKE OR PIPE
STORM SEWER, TRENCHED, PVC, 8 IN.
PIPE APRON, CONCRETE, 15 IN.
PIPE APRON, CONCRETE, 24 IN.
SUBDRAIN, LONGITUDINAL, SHOULDER, PVC, 4 IN., (DR-303)
STORM SEWER, TRENCHED, RCP, CLASS V, 12 IN.
CO1-2023-1120-Waukee T Avenue.xlsx Change Order 1 Page 1 of 2
$10,683,619.98
$0.00
$10,683,619.98
$53,927.00
$10,737,546.98
0 Days
Recommended By:
All-Star Concrete LLC.
Signature:
Name: Bryan Sprigs
Title: Project Manager
Date:
Owner:City of Waukee
□ ≤$500 Department Director X_______________________________________Date___________________
□ $501 to $2,500 City Administrator X_______________________________________Date___________________
□ Date___________________
□ >$2,501 City Council approved or ratified at Council meeting on Date___________________
Date:
Name: Brad Deets
Checked By: Prepared By:
Date:
The Contract Time will be increased by
CHANGE ORDER SUMMARY
NOT VALID UNTIL SIGNED BY THE CONTRACTOR, OWNER'S REPRESENTATIVE (if applicable) AND OWNER
The Original Contract Sum was
The new Contract Sum including this Change Order will be
Signature:
City of Waukee
Title: Lead Civil Engineer
Signature:
The Contract Sum will be increased by this Change Order in the amount of
Net Change by previously authorized Change Orders
Title: City Administrator
Foth Infrastructure & Environment, LLC
The Contract Sum prior to This Change Order was
Name: Rob Kline, P.E.
CO1-2023-1120-Waukee T Avenue.xlsx Change Order 1 Page 2 of 2