HomeMy WebLinkAbout2024-03-18 I01H_07 Transite Water Main Replacement Phase 3_Pmt Est 4AGENDA ITEM: CITY OF WAUKEE, IOWA CITY COUNCIL MEETING COMMUNICATION MEETING DATE: March 18, 2024 AGENDA ITEM:Consideration of approval of Payment Estimate No. 4 to Busy Bee Construction for the Transite Water Main Replacement – Phase 3 Project, in the amount of $136,980.05. FORMAT:Consent Agenda SYNOPSIS INCLUDING PRO & CON: Busy Bee Construction requested Payment Estimate No. 4 for the work completed on the Transite Water Main Replacement – Phase 3 Project, in the amount of $136,980.05. Veenstra & Kimm has reviewed the payment estimate and recommends payment. The partial payment is for the pay period January 8, 2024 to March 8, 2024. This pay estimate is primarily for water services installation. FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS: $136,980.05 COMMISSION/BOARD/COMMITTEE COMMENT: STAFF REVIEW AND COMMENT: RECOMMENDATION: Approve Payment Estimate No. 4 ATTACHMENTS: I. Payment Estimate No. 4 II. Letter of Recommendation PREPARED BY:Beth Richardson REVIEWED BY:Sara Kappos SKK PUBLIC NOTICE INFORMATION – NAME OF PUBLICATION: DATE OF PUBLICATION: I1H7 March 13, 2024 Rudy Koester Director of Public Works City of Waukee 805 University Avenue Waukee, Iowa 50263 CITY OF WAUKEE, IOWA TRANSITE WATER MAIN REPLACEMENT – PHASE 3 PAY ESTIMATE NO. 4 Enclosed are three signed copies of Pay Estimate No. 4 in accordance with the contract between the City of Waukee and Busy Bee Construction for the Transite Water Main Replacement – Phase 3 Project. The partial payment estimate is for the period of January 8, 2024 to March 8, 2024. We have checked and recommend approval of Pay Estimate No 4. We recommended payment to Busy Bee Construction in the amount of $136,980.05. Pay Estimate No. 4 is primarily for water services. Please sign all copies of Pay Estimate No. 4 in the spaces provided. Please return one set of signed copies to Veenstra & Kimm, Inc. and forward one set of copies to Busy Bee Construction with payment. If you have any questions or comments, please contact us at 515-225-8000. VEENSTRA & KIMM, INC. Jordan Kappos JDK 275368 Enclosures cc: Busy Bee Construction – w/enclosure (email) Sara Kappos, City of Waukee – w/enclosure (email) Becky Schuett, City of Waukee – w/enclosure (email) Beth Richardson, City of Waukee – w/enclosure (email) Rachel Bruns, City of Waukee – w/enclosure (email) Tracy Lovetinsky, City of Waukee – w/enclosure (email) QUANTITY VALUE ESTIMATED AUTHORIZED COMPLETED COMPLETED ITEM NO.DESCRIPTION UNIT (ORIG. CONT.)(INCL. C.O.'S)TO DATE UNIT PRICE TO DATE 1.1 Mobilization LS 1.00 1.00 1.00 25,000.00$ $25,000.00 1.2 Traffic Control LS 1.00 1.00 0.75 15,000.00$ $11,250.00 1.3 8" PVC Water Main Directional Bored in Place LF 3,532.00 3,532.00 3,558.00 72.65$ $258,488.70 1.4 1" Water Service Connection Each 71.00 71.00 71.00 535.97$ $38,053.87 1.5 1" Curb Stop and Box Each 71.00 71.00 71.00 783.97$ $55,661.87 1.6 1" Water Service Pipe in Open Cut LF 340.00 340.00 462.00 29.31$ $13,541.22 1.7 1" Water Service Pipe Directional Bored in Place LF 1,730.00 1,730.00 1,872.00 28.89$ $54,082.08 1.8 8" Gate Valve Each 6.00 6.00 6.00 2,828.37$ $16,970.22 1.9 Tapping Valve Assembly, 8"x8" Tapping Sleeve and 8" Valve Each 2.00 2.00 2.00 6,321.27$ $12,642.54 1.10 Tapping Valve Assembly, 12"x8" Tapping Sleeve and 8" Valve Each 1.00 1.00 0.00 6,917.31$ $0.00 1.11 Hydrant Assembly Each 12.00 12.00 12.00 9,287.30$ $111,447.60 1.12 Connection to Existing System Each 1.00 1.00 1.00 5,000.00$ $5,000.00 1.13 PPC Sidewalk SY 350.00 350.00 16.94 170.00$ $2,879.80 1.14 PCC Pavement SY 35.00 35.00 19.97 170.00$ $3,394.90 1.15 Sodding LS 1.00 1.00 0.00 35,000.00$ $0.00 $608,412.80 CO 1 CO 1.1 Connection to Existing 12" Water Main LS 0.00 1.00 1.00 30,000.00$ $30,000.00 $30,000.00 $638,412.80Total Value Completed - Bid Items BID ITEMS PROJECT TITLE: TRANSITE WATER MAIN REPLACEMENT - PHASE 3 Contractor: Busy Bee Construction Original Contract Amount: Pay Period: January 8, 2024 to March 8, 2024 Change Order No. 1 Value Completed Base Bid Value Completed ESTIMATE OF CONSTRUCTION COMPLETED PARTIAL PAYMENT NO. 4 $703,688.31 Date: January 13, 2024 275368 Page 1 of 2 Total Completed $608,412.80 Total Completed $30,000.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $30,000.00 Total Completed $638,412.80 Total Completed $0.00 $638,412.80 $31,920.64 $606,492.16 $469,512.11 $136,980.05 $136,980.05 is recommended for approval for payment in accordance with the terms of the Contract. $703,688.31 $726,771.00 $136,980.05 $606,492.16 $120,278.84 87.8% Busy Bee Construction Signature Signature Signature Name Jordan Kappos Name Name Title Project Engineer Title Title Date Date Date $0.00 SUMMARY Bid Item Subtotal $703,688.31 Original Contract 1 Description/Notes Kaylin Drive and Ashworth Road Tie in 12" Water Main 2 3 6 7 $0.00 Total Approved Veenstra & Kimm, Inc. 9 10 Total Previously Approved City of Waukee Approved: CONTRACT SUMMARY $0.00 BALANCE ORIGINAL CONTRACT AMOUNT TOTAL PARTIAL PAYMENTS INCL THIS PAYMENT PERCENT COMPLETE TOTAL CONTRACT AMOUNT PLUS CHANGE ORDERS THIS PARTIAL PAYMENT $0.00 Amount Due This Request $0.00 $0.00 $0.00 $0.00 $293,496.60 Recommended By: Contractor: Note: The amount 6 7 4 5 8 2 3 $119,692.37 $56,323.14 September 20, 2023 to November 9, 2023 Period $0.00 Total Completed Plus Materials Stored Total Change Orders APPROVED CHANGE ORDERS $0.00 $0.00 $0.00 $0.00 $0.00 4 5 Change Order No. 1 Total Approved $23,082.69 November 10, 2023 to December 7, 2023 December 8, 2023 to January 7, 2024 9 10 Partial Payment No. APPROVED PARTIAL PAYMENTS Revised Contract Price $23,082.69 8 $0.00 $0.00 Total Approved $726,771.00 Total Materials Stored Retainage (5%) Total Earned Less Retainage 275368 Page 2 of 2