Loading...
HomeMy WebLinkAbout2024-04-01 I01H_01 Bluestem Trunk Sewer Phase 2_Pmt Est 1AGENDA ITEM: CITY OF WAUKEE, IOWA CITY COUNCIL MEETING COMMUNICATION MEETING DATE: April 1, 2024 AGENDA ITEM:Consideration of approval of Payment Estimate No. 1 to Synergy Contracting, LLC for the Bluestem Trunk Sewer – Phase 2 project, in the amount of $42,838.35. FORMAT:Consent Agenda SYNOPSIS INCLUDING PRO & CON: Synergy Contracting, LLC requested Payment Estimate No. 1 for the work completed on the Bluestem Trunk Sewer – Phase 2 project in the amount of $42,838.35. Veenstra & Kimm, Inc. has reviewed the payment estimate and recommends payment. The partial payment is for the pay period March 1, 2024 to March 22, 2024. This pay estimate is for SWPPP preparation and project bonding. FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS: $42,838.35 COMMISSION/BOARD/COMMITTEE COMMENT: STAFF REVIEW AND COMMENT: RECOMMENDATION: Approve Payment Estimate No. 1 ATTACHMENTS: I. Letter of Recommendation II.Payment Estimate No. 1 PREPARED BY:Beth Richardson REVIEWED BY:Sara Kappos SKK PUBLIC NOTICE INFORMATION – NAME OF PUBLICATION: DATE OF PUBLICATION: I1H1 March 27, 2024 Rudy Koester Director of Public Works City of Waukee 805 University Avenue Waukee, Iowa 50263 WAUKEE, IOWA BLUESTEM TRUNK SEWER - PHASE 2 PAYMENT ESTIMATE NO. 1 Enclosed are three signed copies of Pay Estimate No. 1 in accordance with the contract between the City of Waukee and Synergy Contracting, LLC for the Bluestem Trunk Sewer – Phase 2 Project. The partial payment estimate is for the period March 1 through March 22, 2024. Payment Estimate No. 1 is for SWPPP and bonding. We have checked and recommend approval of Pay Estimate No 1. We recommended payment to Synergy Contracting, LLC in the amount of $42,838.35. Please sign all copies of Pay Estimate No. 1 in the spaces provided. Please return one set of signed copies to Veenstra & Kimm, Inc. and forward one set of copies to Synergy Contracting, LLC with payment. If you have any questions or comments, please contact us at 515-225-8000. VEENSTRA & KIMM, INC. Andy Willcuts, P.E. ARW:rsb 275370 Enclosure cc: Synergy Contracting, LLC (email) Sara Kappos, City of Waukee – w/enclosure (email) Becky Schuett, City of Waukee – w/enclosure (email) Beth Richardson, City of Waukee – w/enclosure (email) Rachel Bruns, City of Waukee – w/enclosure (email) Tracy Lovetinsky, City of Waukee – w/enclosure (email) Original Contract Amount:                  QUANTITY VALUE ESTIMATED AUTHORIZED COMPLETED COMPLETED ITEM NO. DESCRIPTION UNIT (ORIG. CONT.) (INCL. C.O.'S) TO DATE UNIT PRICE TO DATE 1.1 Mobilization LS 1.00 1.00 0.08 $459,200.00 $38,853.00 1.2 Erosion Control & SWPPP LS 1.00 1.00 0.20 $31,200.00 $6,240.00 1.3 Traffic Control LS 1.00 1.00 0.00 $8,400.00 $0.00 1.4 Clearing and Grubbing LS 1.00 1.00 0.00 $21,000.00 $0.00 1.5 Stabilizing Material TONS 185.00 185.00 0.00 $56.00 $0.00 1.6 Off‐Site Topsoil CY 160.00 160.00 0.00 $21.00 $0.00 1.7 Steel Sheeting Left in Place SF 500.00 500.00 0.00 $77.00 $0.00 1.8 Seeding LS 1.00 1.00 0.00 $32,400.00 $0.00 1.9 Rip‐Rap TONS 129.00 129.00 0.00 $77.00 $0.00 1.10 Field Drain Lines LF 200.00 200.00 0.00 $35.00 $0.00 1.11 8" Sanitary Sewer in Place LF 827.00 827.00 0.00 $119.00 $0.00 1.12 12" Sanitary Sewer in Place LF 575.00 575.00 0.00 $133.00 $0.00 1.13 12" Sanitary Sewer, Trenchless LF 2,100.00 2,100.00 0.00 $259.00 $0.00 1.14 Sewer Service Connection EA 1.00 1.00 0.00 $7,000.00 $0.00 1.15 48" Manhole EA 7.00 7.00 0.00 $9,800.00 $0.00 1.16 60" Manhole EA 4.00 4.00 0.00 $11,200.00 $0.00 1.17 48" Manhole Extra Depth VF 30.00 30.00 0.00 $280.00 $0.00 1.18 60" Manhole Extra Depth VF 121.00 121.00 0.00 $420.00 $0.00 1.19 Connection to Existing Manhole EA 2.00 2.00 0.00 $10,500.00 $0.00 1.20 8" External Drop Connection EA 1.00 1.00 0.00 $10,500.00 $0.00 1.21 24" RCP Culvert LF 40.00 40.00 0.00 $175.00 $0.00 1.22 24" CMP Culvert LF 59.00 59.00 0.00 $168.00 $0.00 1.23 24" RCP Apron EA 2.00 2.00 0.00 $4,620.00 $0.00 1.24 24" CMP Apron EA 2.00 2.00 0.00 $2,401.00 $0.00 1.25 6" PCC Driveway SY 13.00 13.00 0.00 $105.00 $0.00 1.26 8" PCC Driveway SY 220.00 220.00 0.00 $91.00 $0.00 1.27 Lift Station Demolition LS 1.00 1.00 0.00 $60,000.00 $0.00 $45,093.00 PARTIAL PAYMENT NO. 1                 Date:  3/27/24 $1,663,600.00 ESTIMATE OF CONSTRUCTION COMPLETED Total Value Completed ‐ Bid Items BID ITEMS PROJECT TITLE: Bluestem Trunk Sewer ‐ Phase 2 Contractor:  Synergy Contracting, LLC Pay Period:  March 1, 2024 to March 22, 2024 275370 Page 1 of 2