HomeMy WebLinkAbout2024-05-06 I01J_09 Transite Water Main Replacement Phase 3_Change Order 2AGENDA ITEM: CITY OF WAUKEE, IOWA CITY COUNCIL MEETING COMMUNICATION MEETING DATE: May 6, 2024 AGENDA ITEM:Consideration of approval of Change Order No. 2 to Busy Bee Construction for Transite Water Main Replacement – Phase 3 project decreasing the contract amount by $49,608.20. FORMAT:Consent Agenda SYNOPSIS INCLUDING PRO & CON: Change Order No. 2 is to adjust the plan quantities to the as-constructed quantities. FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS: The net result of this Change Order decreases the contract price in the amount of $49,608.20. COMMISSION/BOARD/COMMITTEE COMMENT: STAFF REVIEW AND COMMENT: RECOMMENDATION: Approve Change Order No. 2 ATTACHMENTS: I. Change Order No. 2 II. Letter of Recommendation PREPARED BY:Beth Richardson REVIEWED BY:Sara Kappos SKK PUBLIC NOTICE INFORMATION – NAME OF PUBLICATION: DATE OF PUBLICATION: I1J9 April 22, 2024 Rudy Koester Public Works Director City of Waukee 805 University Avenue Waukee, Iowa 50263 WAUKEE, IOWA TRANSITE WATER MAIN REPLACEMENT – PHASE 3 CHANGE ORDER NO. 2 AND PAY ESTIMATE NO. 5 (FINAL) CERTIFICATE OF COMPLETION Enclosed are three copies of Change Order No. 2 for the above-mentioned project under the contract between the City of Waukee and Busy Bee Construction. Change Order No. 2 is to adjust the plan quantities to the as-constructed quantities. Change Order No. 2 decreases the contract price by a total of $49,608.20. Veenstra & Kimm, Inc. recommends approval of Change Order No. 2. Also enclosed are three copies of Partial Payment Estimate No. 5 (Final) for the period between March 9, 2024 and April 19, 2024 for the above-mentioned project. Partial Pay Estimate No. 5 (Final) provides that 31 days after the acceptance of the project, the retainage in the amount of $33,858.14 will be paid to Busy Bee Construction provided it has submitted the necessary documentation. Also enclosed are two copies of the Certificate of Completion. This certificate should be executed after the City Council has approved acceptance of the project. Please sign both certificates and return one signed copy to our office. Please sign Change Order No. 2 and Partial Payment Estimate No. 5 (Final) in the spaces provided. Return one signed copy of each to our office and one signed copy of each to Busy Bee Construction. The remaining copy is for the City of Waukee’s records. Rudy Koester April 22, 2024 Page 2 If you have any questions or comments, please contact us at 515-225-8000. VEENSTRA & KIMM, INC. Jordan Kappos JDK 275368 Enclosures cc: Busy Bee Construction – w/enclosure (email) Sara Kappos, City of Waukee – w/enclosure (email) Becky Schuett, City of Waukee – w/enclosure (email) Beth Richardson, City of Waukee – w/enclosure (email) Rachel Bruns, City of Waukee – w/enclosure (email) Tracy Lovetinsky, City of Waukee – w/enclosure (email)