CITY OF WAUKEE, IOWA
CITY COUNCIL MEETING COMMUNICATION
MEETING DATE: June 17, 2024
AGENDA ITEM:Consideration of approval of a resolution approving Supplemental Agreement
for Additional Services No. 3 with Snyder & Associates, Inc. [Ute Avenue &
Ashworth Road Intersection Improvement Project]
FORMAT:Resolution
SYNOPSIS INCLUDING PRO & CON: The original agreement ($396,900) was approved by City
Council on August 3, 2020. Supplemental Agreement No. 1 ($48,300) was approved by City Council
on June 21, 2021. Supplemental Agreement No. 2 ($26,100) was approved by City Council on
September 7, 2021. Supplemental Agreement No. 3 covers additional construction services provided
by the consultant due to the contractor exceeding the contract completion date by 206 calendar days.
Staff have included the cost of supplemental agreement no. 3 in the damages to be assessed to the
contractor as a direct result of the project being completed past the contract completion date.
FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS: Amendment No. 3 is for an
additional amount not to exceed $9,800.00. This amendment will bring the new contract amount to
$481,100.00.
COMMISSION/BOARD/COMMITTEE COMMENT:
STAFF REVIEW AND COMMENT:
RECOMMENDATION: Approve the Resolution.
ATTACHMENTS: I. Resolution
II. Supplemental Agreement for Additional Services No. 3
PREPARED BY: Rudy Koester
REVIEWED BY: Rudy Koester RK
I1G5
THE CITY OF WAUKEE, IOWA
RESOLUTION 2024-
APPROVING SUPPLEMENTAL AGREEMENT FOR ADDITIONAL SERVICES NO. 3
WITH SNYDER & ASSOCIATES, INC. [UTE AVENUE & ASHWORTH ROAD
INTERSECTION IMPROVEMENT PROJECT]
IN THE NAME AND BY THE AUTHORITY OF THE CITY OF WAUKEE, IOWA
WHEREAS, the City of Waukee, Iowa is a duly organized municipality within Dallas County;
AND,
WHEREAS, on August 3, 2020 (Resolution #2020-292), the Waukee City Council approved an
agreement with Snyder & Associates for Professional Consulting Services related to the Ute
Avenue and Ashworth Road Intersection Improvement Project; AND,
WHEREAS, on June 21, 2021 (Resolution #2021-274) and September 7, 2021 (Resolution
#2022-373), the Waukee City Council approved Supplemental Agreements No. 1 and 2
respectively with Snyder & Associates for Professional Consulting Services related to the Ute
Avenue and Ashworth Road Intersection Improvement Project; AND,
WHEREAS, Supplemental Agreement No. 3 covers additional construction services provided
by the consultant due to the contractor exceeding the contract completion date by 206 calendar
days.
NOW THEREFORE BE IT RESOLVED by the City of Waukee City Council in session this
17th day of June, 2024, that it hereby approves the Supplemental Agreement for Additional
Services No. 3 with Snyder & Associates [Ute Avenue & Ashworth Road Intersection
Improvements Project].
____________________________
Courtney Clarke, Mayor
Attest:
___________________________________
Rebecca D. Schuett, City Clerk
ROLL CALL VOTE AYE NAY ABSENT ABSTAIN
Anna Bergman Pierce
R. Charles Bottenberg
Chris Crone
Rob Grove
Ben Sinclair
Rev 04-16-19 Page 1 of 1
V:\Projects\2020\120.0783.01\Administration\Agmt_2024-06-04_SA03.docm
SUPPLEMENTAL AGREEMENT FOR ADDITIONAL SERVICES # 03
To: Snyder & Associates, Inc.
2727 SW Snyder Blvd.
Ankeny, IA 50023
Attn: Nathan Carhoff
Phone: 515-964-2020
Fax: 515-964-7938
This is authorization for Snyder & Associates, Inc. to proceed with the following described additional services.
Client: City of Waukee
Project Name: Ute Avenue & Ashworth Road Intersection Improvement Project
S&A Project Number: 120.0783.01 Original Agreement Date: August 3, 2020
DESCRIPTION OF ADDITIONAL SERVICES:
Refer to Attachment 1C.
Lump Sum in the amount of: $
Hourly plus expenses per original agreement or attached fee schedule, not to exceed budget: $9,800
Document attached:
The undersigned, on behalf of the Client, understands and agrees that the services described in this
Supplemental are additional services, scope of which is not contained within the original scope of services
defined in the original agreement. The Additional Services in this Supplemental are subject to the general
conditions contained in the original Professional Services Agreement.
City of Waukee (Client) SNYDER & ASSOCIATES, INC. (Professional)
(Type or Print Name above line)
By: By:
(Authorized Agent) (Authorized Agent)
Courtney Clarke, Mayor
(Printed or typed signature) (Printed or typed signature)
Date: Date:
Route executed to: Nathan Carhoff
June 5, 2024
Mark A. Land, P.E., CFM
-1-
V:\Projects\2020\120.0783.01\Administration\Agmt_2024-06-04_SA03Scope.docx
ATTACHMENT 1C
UTE AVENUE & ASHWORTH ROAD INTERSECTION IMPROVEMENT PROJECT
WAUKEE, IOWA
CLIENT: CITY OF WAUKEE
230 W. HICKMAN ROAD
WAUKEE, IOWA, ZIPCODE
C/O RUDY KOESTER
Hereinafter referred to as the “City”
ENGINEER: SNYDER & ASSOCIATES, INC.
2727 SW SNYDER BLVD
ANKENY, IOWA 50023
Hereinafter referred to as the “Consultant”
PROJECT: UTE AVENUE & ASHWORTH ROAD INTERSECTION IMPROVEMENT PROJECT
DATE: JUNE 4, 2024
SCOPE OF SERVICES:
I. GENERAL
The Contractor exceeded the construction completion date leading to additional construction progress
meetings, payment applications, and general construction administration for the project. To date, the
Contractor has exceeded the completion date by 206 calendar days. The current Consultant construction
administration budget is not able to absorb the additional effort.
This supplemental agreement request covers the additional construction service efforts.
II. CONSTRUCTION SERVICES
The Consultant will perform the following tasks related to construction administration.
A. Attend on-site construction meetings as necessary beyond construction contract substantial
completion.
B. Create and process partial payment requests and change orders beyond construction contract
substantial completion.
C. General construction coordination and administration as necessary beyond construction contract
substantial completion.
-2-
V:\Projects\2020\120.0783.01\Administration\Agmt_2024-06-04_SA03Scope.docx
III. COMPENSATION
In consideration of the professional services provided herein, the City agrees to pay the Consultant the
following sum, NOT-TO-EXCEED, including any authorized reimbursable expenses, pursuant to the
Schedule of Fees set forth in Attachment 3 of the original agreement. The compensation schedule as set
forth in Article 3 of the original agreement is amended as follows:
Basic Services of the Consultant
Approved
Agreements
Supplemental
Agreement
No. 03 Total
A. Project Management $31,000 $31,000
B. Topographic Survey $21,900 $21,900
C. Boundary Survey $6,500 $6,500
D. Wetland and Stream Delineation $6,000 $6,000
E. Threatened Endangered Species Habitat Survey $2,000 $2,000
F. Phase I Environmental Site Assessment $3,100 $3,100
G. Cultural Resources $18,000 $18,000
H. Intersection Alternatives Analysis $21,600 $21,600
I. Preliminary Roadway Design $61,900 $61,900
J. Right-of-Way Layout and Plot Plans $7,500 $7,500
K. Right-of-Way Plats $17,000 $17,000
L. Right-of-Way Acquisition $45,700 $45,700
M. Traffic Signal and Lighting Design $24,200 $24,200
N. Final Roadway Design $97,100 $97,100
O. Geotechnical Investigation $20,000 $20,000
P. Gas Main Relocation Staking $4,100 $4,100
SUBTOTAL (Hourly Rate + Expenses) $387,600 $387,600
Construction Phase Services of the Consultant
Base
Agreement
Supplemental
Agreement
No. 03 Total
A. Bidding $4,700 $4,700
B. Construction Administration $59,100 $9,800 $68,900
C. Traffic Signal Construction Phase Services $14,800 $14,800
D. Record Drawings $5,100 $5,100
SUBTOTAL (Hourly Rate + Expenses) $83,700 $9,800 $93,500
TOTAL (Hourly Rate + Expenses) $471,300 $9,800 $481,100