Loading...
HomeMy WebLinkAbout2024-06-17 I01H_06 T Ave Corridor, W Hickman Rd to NW Douglas Pkwy_Change Order 7AGENDA ITEM: CITY OF WAUKEE, IOWA CITY COUNCIL MEETING COMMUNICATION MEETING DATE: June 17, 2024 AGENDA ITEM:Consideration of approval of Change Order No. 7 to All-Star Concrete, LLC for the T Avenue Corridor Improvements – W Hickman Road to NW Douglas Parkway Project increasing the contract amount by $3,930.00. FORMAT:Motion SYNOPSIS INCLUDING PRO & CON: Detour routes from the T Ave project and the NW 10th St Crack and Seat project has conflicting signage, requiring sign modification to avoid confusing drivers. The bike trail has had slippery conditions due to construction adjacent to the trail, therefore adding signage to improve safety to trail users. FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS: The net result of this Change Order increases the contract price in the amount of $3,930.00. COMMISSION/BOARD/COMMITTEE COMMENT: STAFF REVIEW AND COMMENT: RECOMMENDATION: Approve the change order. ATTACHMENTS: I. Change Order No. 7 II. Letter of Recommendation PREPARED BY:Lisa Bauman REVIEWED BY:Sara Kappos SKK PUBLIC NOTICE INFORMATION – NAME OF PUBLICATION: DATE OF PUBLICATION: I1H6 8191 Birchwood Court, Suite L Johnston, IA 50131 Phone: (515) 254-1393 June 10, 2024 Sara Kappos, P.E. Assistant Public Works Director 805 University Avenue Waukee, IA 50263 RE: Change Order #7 T Avenue Corridor Improvements – W Hickman Road to NW Douglas Parkway Dear Mrs. Kappos: Attached please find a detailed Change Order for City Council approval on June 17, 2024. Change Description: The detour route from T Avenue and the 10th Street Crack and Seat project had conflicts between the two. Modified some of the signage that showed conflicting directions to public. In addition, the bike trail that runs through the project had two additional slippery when wet signs added for increased safety. We have reviewed the submitted quotes from All - Star and it appears to be in order with current industry pricing. If City Staff concurs with this pricing, we recommend the City of Waukee Increase the contract price in the amount of $3,930.00 to complete the additional work associated with Change Order #7. If you have any questions, please contact me. Sincerely, Foth Infrastructure & Environment, LLC Rob Kline, P.E. Lead Civil Engineer Encl: Change Order #7 dated 6/10/2024 CHANGE ORDER 07 Distribution: Owner - Finance ____ Owner - Public Works ____ Engineer ____ Contractor ____ Contractor:All-Star Concrete LLC. 4989 NW Johnston Dr. Johnston, Iowa 50131 $10,683,619.98 August 7, 2023 8.23 Division 1 Special LS $2,500.00 1.00 $2,500.00 8.24 Division 1 Special LS $1,430.00 1.00 $1,430.00 $3,930.00 $10,683,619.98 $161,129.94 $10,844,749.92 $3,930.00 $10,848,679.92 0 Days Recommended By: All-Star Concrete LLC. Signature: Name: Bryan Sprigs Title: Project Manager Date: Owner:City of Waukee □ ≤$500 Department Director X_______________________________________Date___________________ □ $501 to $2,500 City Administrator X_______________________________________Date___________________ □ Date___________________ □ >$2,501 City Council approved or ratified at Council meeting on Date___________________ Value AdjustmentItem No. Signature: The Contract Sum will be increased by this Change Order in the amount of Net Change by previously authorized Change Orders Foth Infrastructure & Environment, LLC The Contract Sum prior to This Change Order was Division Item Code Traffic Control, Detour Modification Quantity AdjustmentUnit Price City of Waukee Description Unit Trafic Control, Trail Signage Prepared By: Date: The Contract Time will be increased by CHANGE ORDER SUMMARY NOT VALID UNTIL SIGNED BY THE CONTRACTOR, OWNER'S REPRESENTATIVE (if applicable) AND OWNER The Original Contract Sum was Title: Lead Civil Engineer Title: City Administrator Name: Rob Kline, P.E. The new Contract Sum including this Change Order will be Signature: Date: Name: Brad Deets Checked By: Department of Public Works 805 University Avenue Waukee, IA 50263 (515) 987-7920 Fax (515) 987-3979 THE CONTRACT IS CHANGED AS FOLLOWS: Detour route from T Avenue and the 10th Street Crack and Seat project had conflicts between the two. Modified some of the signage that showed conflicting directions to public. The bike trail that runs through the project had two additional slippery when wet signs added for increased safety. T Avenue Corridor Improvements W Hickman Rd to NW Douglas Pkwy 7 22W007.00 Waukee Project File Number May 31, 2024 Foth Project File Number Orig. Contract Amount & Date Date Change Order Number Project Title CO7-2024-0531-Waukee T Avenue.xlsx Change Order 1 Page 1 of 1