HomeMy WebLinkAbout2024-08-05 I01G_07 Electrical Engineering Services_Library Fire Alarm System ReplacementAGENDA ITEM:
CITY OF WAUKEE, IOWA
CITY COUNCIL MEETING COMMUNICATION
MEETING DATE: August 5, 2024
AGENDA ITEM:Consideration of approval of a resolution approving Electrical Engineering
Services Proposal with KCL Engineering [Waukee Public Library Fire Alarm
System Replacement Project]
FORMAT:Resolution
SYNOPSIS INCLUDING PRO & CON:
The City of Waukee sought proposals for engineering services to design a
replacement fire alarm system for the current system at the Waukee Public
Library. The current system is obsolete and is no longer supported by vendors
in the event of a component or system failure. KCL Engineering has
submitted a proposal for these services in the amount of $6000. Deliverables
from this agreement will be diagrams and specifications for the installation of
a new fire alarm system which will meet current state and local fire codes.
FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS:
The cost for these services is $6000 for engineering, design and cost
estimation for the replacement fire alarm system at the Waukee Public
Library.
COMMISSION/BOARD/COMMITTEE COMMENT:
STAFF REVIEW AND COMMENT:
RECOMMENDATION: Staff recommends approval
ATTACHMENTS: I. Proposed Resolution
II. Electrical Engineering Services Proposal
PREPARED BY: Christine Maduro
REVIEWED BY: Christine Maduro
PUBLIC NOTICE INFORMATION –
NAME OF PUBLICATION:
DATE OF PUBLICATION:
I1G7
THE CITY OF WAUKEE, IOWA
RESOLUTION 2024-
APPROVING ELECTRICAL ENGINEERING SERVICES PROPOSAL WITH
KCL ENGINEERING [WAUKEE PUBLIC LIBRARY FIRE ALARM SYSTEM
REPLACEMENT PROJECT]
IN THE NAME AND BY THE AUTHORITY OF THE CITY OF WAUKEE, IOWA
WHEREAS, the City of Waukee, Iowa is a duly organized municipality within Dallas
County; AND,
WHEREAS, Waukee City staff solicited proposals for engineering services to design a
replacement fire alarm system for the Waukee Public Library; AND,
WHEREAS, the current fire alarm system is obsolete and is no longer supported by
vendors in the event of a component or system failure; AND,
WHEREAS, City staff recommend approval of a proposal from KCL Engineering to
provide diagrams and specifications for the installation of a new fire alarm system which
will meet current state and local fire codes;
NOW THEREFORE BE IT RESOLVED by the City of Waukee City Council on this
5th day of August, 2024, that the Electrical Engineering Services Proposal with KCL
Engineering [Waukee Public Library Fire Alarm System Replacement Project] is hereby
approved.
____________________________
Courtney Clarke, Mayor
Attest:
___________________________________
Rebecca D. Schuett, City Clerk
RESULTS OF VOTE: AYE NAY ABSENT ABSTAIN
R. Charles Bottenberg
Chris Crone
Rob Grove
Anna Bergman Pierce
Ben Sinclair
1
July 23, 2024
Christine Maduro
City of Waukee
230 W Hickman Rd
Waukee, Iowa 50263
SUBJECT: Waukee Public Library Fire Alarm System Replacement
Waukee, IA
Dear Chrisine,
We are pleased to respond to your request to provide electrical engineering services for the subject project. We
understand the project consists of a full fire alarm replacement for the building. The building is approximately
14,584 sq. ft.
Our proposed scope of services includes the following:
Design Phase Services
1. Electrical design services including:
a. Fire alarm system
2. Meetings and site visits
a. 2 owner design meetings for review and on-site verification
3. Deliverables
a. DD – Design Development drawings
b. Construction drawings and specifications suitable for bidding and construction
c. Opinion of probable cost based on square feet pricing
d. Documentation for Permit
i. Permit set documents
ii. Responses to review comments
iii. One resubmittal set, when required
Bidding/Negotiating Phase Services – ADD SERVICE
1. Attend pre-bid meeting
2. Respond to questions and prepare addenda as necessary
Construction Phase Services – ADD SERVICE
1. Attend pre-construction meeting
2. Perform industry standard contract administration services including:
a. Respond to contractor questions and RFIs
b. Prepare change orders and review contractor pricing
c. Review shop drawing submittals
d. Review monthly contractor pay applications
3. Attend bi-weekly construction meetings and provide job site observation reports, where applicable
4. One punch list site visit and one follow up visit
5. Review closeout submittals (e.g. as-built documents and O&M manuals)
2
Services Not Included in Scope
1. Services, consultation, and/or field trips in excess of those indicated above
2. Revisions to previously approved drawings and documents
3. Value engineering or other changes after completion of 100% construction documents
4. Fire protection system sprinkler head layouts, hydraulic calculations, or fire pump design.
5. Emergency responder distributed antenna system for IFC 510 compliance.
6. Detailed “take-off” cost estimating
7. Commissioning services or assisting contractor with system startup or adjustment
8. Verifying accuracy and completeness of as-built documents
Compensation
We propose to perform the services defined above for a lump sum fixed fee of $6,000.
This is fee will cover the Design and bidding services. Additional services will be required for construction if the
project proceeds.
We understand that construction and installation will be contingent on budget for the project. We will not bill for
construction if the project does not proceed with the lowest bidder.
We do not anticipate asking for any reimbursable expenses.
This proposal is valid for 60 days and subject to adjustment if there is a material change in the schedule and/or
scope of work.
Thank you for the invitation to submit this proposal. We look forward to the opportunity of serving you. If this
proposal is acceptable, please sign at the space indicated below and return one copy to this office for our files. If
there are any questions, please contact me.
Sincerely,
Eric Heynen, PE
Senior Electrical Engineer
The undersigned, having read the foregoing letter of agreement between City of Waukee and KCL Engineering
LLC, agrees to the conditions set therein and the terms and conditions attached.
________________________________ ______________________
City of Waukee Date
3
Terms and Conditions:
Services provided by KCL (hereinafter referred to as "the Consultant") under this Agreement will be performed in a manner
consistent with the human degree of care and skill ordinarily exercised by members of the same profession currently
practicing under similar circumstances.
The Client agrees, to the fullest extent permitted by law, to indemnify and hold harmless the Consultant, its officers, directors,
employees and subconsultants (collectively, Consultant) against all damages, liabilities or costs, including reasonable
attorneys’ fees and defense costs, arising out of or in any way connected to their reuse of the construction documents on
any other project or site without the involvement of the consultant in the construction phase services normally provided on
such projects, excepting only those damages, liabilities or costs attributable to the sole negligence of willful misconduct b y
the Consultant.
In the event the Client, the Client’s contractors or subcontractors, or anyone for whom the Client is legally liable makes or
permits to be made any changes to any reports, plans, specifications, or other construction documents prepared by the
Consultant without obtaining the Consultant's prior written consent, the Client shall assume full responsibility for the results
of such changes. Therefore, the Client agrees to waive any claim against the Consultant and to release the Consultant from
any liability arising directly or indirectly from such changes. In addition, the Client agrees, to the fullest extent permitted by
law, to indemnify and hold harmless the Consultant from any damages, liabilities, or costs, including reasonable attorneys’
fees and costs of defense, arising from such changes.
The Consultant shall not be responsible for, nor have control over or charge of, construction means, methods, sequence,
techniques, or procedures, or for any health or safety precautions required by any regulatory agencies in connection with the
project.
The Client agrees to include in any contracts for construction appropriate language that prohibits the Contractor or any
subcontractor of any tier from making any changes or modifications to the Consultant's construction documents without the
prior written approval of the Consultant and that further requires the Contractor to indemnify both the Consultant and Client
from any liability or cost arising from such changes made without such proper authorization.
It is agreed that the Consultant’s liability for this project for negligent acts, errors, or omissions, and all claims, losses, costs,
damages, cost of defense, expenses from any cause, including Client, Contractors, and Attorney fees, is limited to $2,000,000.
All amounts due to KCL Engineering, LLC shall be payable within 30 days of presentation of an invoice which shall be rendered
from time to time but not more frequently than monthly. Hourly agreements shall be billed at published hourly rates for the
time incurred on the project. Reimbursable expenses shall be included on invoices as the expenses are incurred. Any
franchises, sales, service, use and/or value-added taxes levied by any governmental authority which would be deemed
applicable by KCL Engineering, LLC will be invoiced in addition to any stated fee and/or reimbursable expenses.
KCL Engineering, LLC reserves the right to suspend work or terminate this Agreement and charge 1.5% interest per month on
invoiced amounts when invoices are thirty (30) days past due. All attorney fees, court costs, accrued interest and other
interest and other collection costs incurred during collection procedures for delinquent accounts shall be paid to KCL
Engineering, LLC.