HomeMy WebLinkAbout2024-08-19 I10A NE Outfall Sewer_Change Order 4AGENDA ITEM:
CITY OF WAUKEE, IOWA
CITY COUNCIL MEETING COMMUNICATION
MEETING DATE: August 19, 2024
AGENDA ITEM:Consideration of approval of Change Order No. 4 to S.J. Louis
Construction, Inc. for the Northeast Outfall Sewer project increasing the
contract amount by $199,446.80.
FORMAT:Consent Agenda
SYNOPSIS INCLUDING PRO & CON: Change Order No. 4 is to adjust plan quantities to the
as-constructed quantities. The change order also provides a deduct for an existing pump that was
intended to be salvaged and was damaged beyond repair by the contractor.
FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS: The net result of this
Change Order increases the contract price in the amount of $199,446.80.
COMMISSION/BOARD/COMMITTEE COMMENT:
STAFF REVIEW AND COMMENT:
RECOMMENDATION: Approve the change order.
ATTACHMENTS: I. Change Order No. 4
II. Letter of Recommendation
PREPARED BY:Sara Kappos
REVIEWED BY:Sara Kappos SKK
PUBLIC NOTICE INFORMATION –
NAME OF PUBLICATION:
DATE OF PUBLICATION:
I10A
August 14, 2024
Rudy Koester
Public Works Director
City of Waukee
805 University Avenue
Waukee, Iowa 50263
WAUKEE, IOWA
NORTHEAST OUTFALL SEWER
CHANGE ORDER NO. 4
PAY ESTIMATE NO. 17 (FINAL)
EARLY RELEASE OF RETAINAGE
Enclosed are three signed copies of Change Order No. 4 and Pay Estimate No. 17 (Final) in
accordance with the contract between the City of Waukee and S.J. Louis Construction, Inc. for
the Northeast Outfall Sewer project. The partial payment estimate is for the period of July 1,
2024 to July 31, 2024.
Change Order No. 4 is for a deduct for a broken pump and to adjust plan quantities to the as‐
constructed quantities. Change Order No. 4 increases the price for the project by a total of
$199,446.80. We recommend approval of Change Order No. 4 by the City Council of the City of
Waukee.
S.J. Louis Construction, Inc. is also requesting early partial release of the retainage on the
Northeast Outfall Sewer project. Enclosed is the sworn statement notice from S.J. Louis
Construction, Inc. as required by Iowa Code Section 573.28.
We have checked and recommend approval of Pay Estimate No. 17 (Final). We recommended
payment to S.J. Louis Construction, Inc. in the amount of $538,605.68. Pay Estimate No. 17
(Final) is for Change Order No 4 and for partial release of retainage.
Retaining retainage in the amount of $80,000.00 is recommended for payment 30 days after the
project has been accepted by the City.
Please sign all copies of Change Order No. 4 and Pay Estimate No. 17 (Final) in the spaces
provided. Please return one set of signed copies to Veenstra & Kimm, Inc. and forward one set
of copies to S.J. Louis Construction, Inc. with payment.
If you have any questions or comments, please contact us at 515‐225‐8000.
VEENSTRA & KIMM, INC.
Andy Willcuts
ARW
275354
cc: Sara Kappos, City of Waukee – w/enclosure (email)
Becky Schuett, City of Waukee – w/enclosure (email)
Lisa Bauman, City of Waukee – w/enclosure (email)
Rachel Bruns, City of Waukee – w/enclosure (email)
Tracy Lovetinsky, City of Waukee – w/enclosure (email)
275354 Page 1 of 2
August 14, 2024 CHANGE ORDER NO. 4
WAUKEE, IOWA
NORTHEST OUTFALL SEWER
Change Order No. 4 is to document modifications to the construction contract as shown below:
Item Description Unit Quantity Unit Price Total Price
5.1 Broken Pump Deduct LS 1 ($43,000.00) ($43,000.00)
($43,000.00)
Change Order No. 4 is also to adjust the plan quantities to the as‐constructed quantities as shown
below:
Item Description Unit Quantity Unit Price Total Price
1.5 6" PCC Trail SY 746.00 $85.00 $63,410.00
1.6 Rock Excavation CY 4,065.00 $1.00 $4,065.00
1.7 Stabilizing Material TONS 705.00 $95.00 $66,975.00
1.12 Rip‐Rap TONS 375.68 $110.00 $41,324.80
1.13 Field Drain Lines LF 215.00 $90.00 $19,350.00
1.14 Rolled Erosion Control Product,
Type 2
SY 516.00 $2.50 $1,290.00
1.15 12" Water Main in Open Cut LF 36.00 $300.00 $10,800.00
1.17 8" Sanitary Sewer in Place LF ‐10.00 $750.00 ($7,500.00)
1.19 18" Sanitary Sewer in Place LF 6.00 $785.00 $4,710.00
1.20 21" Sanitary Sewer in Place LF ‐2.00 $895.00 ($1,790.00)
1.21 24" Sanitary Sewer in Place LF ‐11.00 $450.00 ($4,950.00)
1.22 30" Sanitary Sewer in Place LF ‐16.00 $353.00 ($5,648.00)
275354 Page 2 of 2
Item Description Unit Quantity Unit Price Total Price
1.23 30" Sanitary Sewer Trenchless LF 5.00 $1,990.00 $9,950.00
1.26 60" Manhole EA 3.00 $17,000.00 $51,000.00
1.27 84" Manhole EA ‐1.00 $26,000.00 ($26,000.00)
1.28 60" Manhole Extra Depth VF 35.00 $800.00 $28,000.00
1.29 84" Manhole Extra Depth VF ‐5.00 $1,300.00 ($6,500.00)
1.30 Subdrain 6" to 8" LF ‐55.00 $50.00 ($2,750.00)
1.32 Salvage and Reinstall Storm
Sewer, 12" to 36"
LF ‐70.00 $47.00 ($3,290.00)
$242,446.80
Change Order No. 4 increases the contract price by a total of $199,446.80.
S.J. LOUIS CONSTRUCTION, INC. CITY OF WAUKEE, IOWA
By By
Title Title
Date Date
VEENSTRA & KIMM, INC. ATTEST:
By By
Title Project Engineer Title
Date Date