HomeMy WebLinkAbout2024-09-16 I01F_09 Transite Water Main Replacement Phase 4_Pmt Est 1AGENDA ITEM: CITY OF WAUKEE, IOWA CITY COUNCIL MEETING COMMUNICATION MEETING DATE: September 16, 2024 AGENDA ITEM:Consideration of approval of Payment Estimate No. 1 to Busy Bee Construction for the Transite Water Main Replacement – Phase 4 Project, in the amount of $165,293.01. FORMAT:Consent Agenda SYNOPSIS INCLUDING PRO & CON: Busy Bee Construction requested Payment Estimate No. 1 for the work completed on the Transite Water Main Replacement – Phase 4 Project, in the amount of $165,293.01. Veenstra & Kimm has reviewed the payment estimate and recommends payment. The partial payment is for the pay period July 30, 2024 to August 30, 2024. This pay estimate is for water main and appurtenances installed FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS: $165,293.01 COMMISSION/BOARD/COMMITTEE COMMENT: STAFF REVIEW AND COMMENT: RECOMMENDATION: Approve Payment Estimate No. 1 ATTACHMENTS: I. Payment Estimate No. 1 II. Letter of Recommendation PREPARED BY:Lisa Bauman REVIEWED BY:Sara Kappos SKK PUBLIC NOTICE INFORMATION – NAME OF PUBLICATION: DATE OF PUBLICATION: I1F9 September 11, 2024 Rudy Koester Public Works Director City of Waukee 805 University Avenue Waukee, Iowa 50263 WAUKEE, IOWA TRANSITE WATER MAIN REPLACEMENT – PHASE 4 CHANGE ORDER NO. 1 AND PAY ESTIMATE NO. 1 Enclosed are three copies of Change Order No. 1 for the above-mentioned project under the contract between the City of Waukee and Busy Bee Construction LLC. Change Order No. 1 is for additional gate valves and fittings. Change Order No. 1 increases the contract price by a total of $6,206.00. Veenstra & Kimm, Inc. recommends approval of Change Order No. 1. Also enclosed are three copies of Partial Payment Estimate No. 1 for the period between July 30, 2024 and August 30, 2024 for the above-mentioned project. Partial Pay Estimate No. 1 is for water main and appurtenances installed. We have checked the estimate and recommend payment to Busy Bee Construction LLC in the total amount of $165,293.01. Please sign Change Order No. 1 and Partial Payment Estimate No. 1 in the spaces provided. Return one signed copy of each to our office and one signed copy of each to Busy Bee Construction LLC with payment. The remaining copy is for the City of Waukee’s records. Rudy Koester September 11, 2024 Page 2 If you have any questions or comments, please contact us at 515-225-8000. VEENSTRA & KIMM, INC. Jordan Kappos JDK 275377 Enclosures cc: Busy Bee Construction LLC – w/enclosure (email) Sara Kappos, City of Waukee – w/enclosure (email) Becky Schuett, City of Waukee – w/enclosure (email) Lisa Bauman, City of Waukee – w/enclosure (email) Rachel Bruns, City of Waukee – w/enclosure (email) Tracy Lovetinsky, City of Waukee – w/enclosure (email) QUANTITY VALUE ESTIMATED AUTHORIZED COMPLETED COMPLETED ITEM NO.DESCRIPTION UNIT (ORIG. CONT.)(INCL. C.O.'S)TO DATE UNIT PRICE TO DATE 1.1 Mobilization LS 1.00 1.00 0.25 25,000.00$ $6,250.00 1.2 Traffic Control LS 1.00 1.00 0.25 15,000.00$ $3,750.00 1.3 8" PVC Water Main Directional Bored in Place LF 4,732.00 4,732.00 1,844.00 71.69$ $132,196.36 1.4 1" Water Service Connection Each 99.00 99.00 0.00 564.23$ $0.00 1.5 1" Curb Stop and Box Each 99.00 99.00 0.00 582.36$ $0.00 1.6 1" Water Service Pipe in Open Cut LF 495.00 495.00 0.00 26.62$ $0.00 1.7 1" Water Service Pipe Directional Bored in Place LF 2,483.00 2,483.00 0.00 26.62$ $0.00 1.8 8" Gate Valve Each 9.00 9.00 3.00 2,973.50$ $8,920.50 1.9 Hydrant Assembly Each 13.00 13.00 1.00 9,203.28$ $9,203.28 1.10 Tapping Valve Assembly, 12"x8" Tapping Sleeve and 8" Valve Each 1.00 1.00 1.00 7,466.50$ $7,466.50 1.11 Connection to Existing System Each 3.00 3.00 0.00 5,516.46$ $0.00 1.12 Sidewalk Removal Each 18.00 18.00 0.00 30.00$ $0.00 1.13 PCC Sidewalk SY 223.00 223.00 0.00 170.00$ $0.00 1.14 Detectable Warnings SF 8.00 8.00 0.00 80.00$ $0.00 1.15 PCC Pavement SY 16.00 16.00 0.00 170.00$ $0.00 1.16 Sodding LS 1.00 1.00 0.00 40,000.00$ $0.00 $167,786.64 CO 1 CO 1.1 8" x 1' MJ Offset EA 0.00 2.00 2.00 1,300.00$ $2,600.00 CO 1.2 6" Gate Valve EA 0.00 1.00 1.00 1,971.00$ $1,971.00 CO 1.3 4" Gate Valve EA 0.00 1.00 1.00 1,635.00$ $1,635.00 $6,206.00 $173,992.64 ESTIMATE OF CONSTRUCTION COMPLETED PARTIAL PAYMENT NO. 1 $824,253.87 Date: September 11, 2024 Change Order No. 1 Value Completed Total Value Completed - Bid Items BID ITEMS PROJECT TITLE: TRANSITE WATER MAIN REPLACEMENT - PHASE 4 Contractor: Busy Bee Construction LLC Original Contract Amount: Pay Period: July 30, 2024 to August 30, 2024 Base Bid Value Completed 275377 Page 1 of 2