HomeMy WebLinkAbout2024-10-07 I08A NW 10th St Crack & Seat_Change Order 1AGENDA ITEM: CITY OF WAUKEE, IOWA CITY COUNCIL MEETING COMMUNICATION MEETING DATE: October 7, 2024 AGENDA ITEM:Consideration of approval of Change Order No. 1 to Grimes Asphalt and Paving Corporation for the NW 10th Street Crack and Seat, NW Douglas Parkway to 260th Street increasing the contract amount by $52,751.00. FORMAT:Motion SYNOPSIS INCLUDING PRO & CON: The change order includes work required to extend Meredith Drive west of NW 10th Street approximately an additional 500’ with HMA. This work specifically includes reshaping existing gravel roadway, asphalt paving, groove cutting for pavement markings, and striping. The agreement for this additional work is for the City of Waukee to invoice the adjacent property owner for $25,000.00 and split the remaining balance with Dallas County. FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS: The net result of this Change Order increases the contract price in the amount of $52,751.00. The City of Waukee will be responsible for $38,875.49 and Dallas County for $13,875.51. COMMISSION/BOARD/COMMITTEE COMMENT: STAFF REVIEW AND COMMENT: RECOMMENDATION: Approve the change order. ATTACHMENTS: I. Change Order No. 1 II. Letter of Recommendation PREPARED BY:Lisa Bauman REVIEWED BY:Sara Kappos SKK PUBLIC NOTICE INFORMATION – NAME OF PUBLICATION: DATE OF PUBLICATION: I8A 8191 Birchwood Court, Suite L Johnston, IA 50131 Phone: (515) 254-1393 September 30, 2024 Sara Kappos, P.E. Assistant Public Works Director 805 University Avenue Waukee, IA 50263 RE: Change Order #1 & Pay Request #1 10th Street Crack and Seat – NW Douglas Parkway to 260th Street Dear Mrs. Kappos: Attached please find a detailed Pay Request and Change Order for City Council approval on October 7, 2024. Submitted Quantity: All items completed on the contract are included in this estimate so far. The only item remaining is pavement markings on the added extension to Meredith. We have reviewed the submitted quantities, and they appear to be in order with what has been constructed in the field. If City Staff concurs with this payment, we recommend the City of Waukee pay Grimes Asphalt of Des Moines, Iowa the amount of $1,333,266.45 for the work completed to date. Change Description: This change order includes the work required to extend Meredith Drive west of NW 10th Street approximately an additional 500' with HMA . The line items include the work to reshape the existing gravel roadway, asphalt pave and stripe with Durable markings. The agreement for this additional work is for the city to invoice the adjacent property owner for $25,000 and split the remainder with Dallas county. This works out to a 0.737 : 0.263 split. This is broken down in detail on the accompanying change order. We have reviewed the submitted quotes from Grimes Asphalt and they appear to be in order with current industry pricing. If City Staff concurs with this pricing, we recommend the City of Waukee Increase the contract price in the amount of $52,751.00 to complete the additional work associated with Change Order #1. If you have any questions, please contact me. Sincerely, Foth Infrastructure & Environment, LLC Rob Kline, P.E. Lead Civil Engineer Encl: Pay Request #1 & Change Order #1 dated 09/30/2024 CHANGE ORDER 01 Distribution: Owner - Finance ____ Owner - Public Works ____ Engineer ____ Contractor ____ Contractor:Grimes Asphalt and Paving Corporation 5550 NE 22nd Street Des Moines, Iowa 50313 $1,254,457.62 May 6, 2024 2.3 1 Special CY $64.00 76.6441 $4,905.22 2.3 2 Special CY $64.00 27.3559 $1,750.78 7.16 1 Special TON $105.00 305.8394 $32,113.13 7.16 2 Special TON $105.00 109.1606 $11,461.87 8.1 1 8020-C-1000 STA $90.00 14.7392 $1,326.53 8.1 2 8020-C-1000 STA $90.00 5.2608 $473.47 8.2 1 8020-M-1000 STA $36.00 14.7392 $530.61 8.2 2 8020-M-1000 STA $36.00 5.2608 $189.39 $52,751.00 $1,254,457.62 $0.00 $1,254,457.62 $52,751.00 $1,307,208.62 0 Days Recommended By: Grimes Asphalt and Paving Corporation Signature: Name: Matt Younker Title: Project Manager Date: Owner:City of Waukee □ ≤$500 Department Director X_______________________________________Date___________________ □ $501 to $2,500 City Administrator X_______________________________________Date___________________ □ Date___________________ □ >$2,501 City Council approved or ratified at Council meeting on Date___________________ THE CONTRACT IS CHANGED AS FOLLOWS: This change order includes the work required to extend Meredith Drive west of NW 10th Street approximately an additional 500' with HMA. The following line items include the work to reshape the existing gravel roadway, asphalt pave and stripe. The agreement for this additional work is for the city to invoice the adjacent property owner for $25,000 and split the remainder with Dallas county. This works out to a 0.737 : 0.263 split. NW 10th Street Crack and Seat NW Douglas Parkway to 260th Street 1 23W034.00 Waukee Project File Number September 30, 2024 Foth Project File Number Orig. Contract Amount & Date Date Change Order Number Project Title Department of Public Works 805 University Avenue Waukee, IA 50263 (515) 987-7920 Fax (515) 987-3979 Date: Name: Brad Deets Checked By: Prepared By: Date: The Contract Time will be increased by CHANGE ORDER SUMMARY NOT VALID UNTIL SIGNED BY THE CONTRACTOR, OWNER'S REPRESENTATIVE (if applicable) AND OWNER The Original Contract Sum was Title: Lead Civil Engineer Title: City Administrator Name: Rob Kline, P.E. Value Adjustment The new Contract Sum including this Change Order will be Signature: Quantity AdjustmentUnit Price City of Waukee Description Unit PAINTED PAVEMENT MARKINGS, DURABLE Signature: The Contract Sum will be increased by this Change Order in the amount of Net Change by previously authorized Change Orders Foth Infrastructure & Environment, LLC The Contract Sum prior to This Change Order was Division Item Code Class 13 Excavation HMA PAVEMENT, 1/2" INTERMEDIATE AND SURFACE MIX, 6 IN. GROOVES CUT FOR PAVEMENT MARKINGS Class 13 Excavation HMA PAVEMENT, 1/2" INTERMEDIATE AND SURFACE MIX, 6 IN. PAINTED PAVEMENT MARKINGS, DURABLE GROOVES CUT FOR PAVEMENT MARKINGS CO1-2024-0726-Waukee 10th Crack and Seat.xlsx Change Order 1 Page 1 of 1