HomeMy WebLinkAbout2024-10-21 H04 University Ave Extension Phase 1_Commence ProjectAGENDA ITEM:
CITY OF WAUKEE, IOWA
CITY COUNCIL MEETING COMMUNICATION
MEETING DATE: October 21, 2024
AGENDA ITEM:Consideration of approval of a resolution approving and authorizing a public
improvement project to construct the University Avenue Extension Phase 1
Project, funding of final site-specific design, final route/site selection, to
acquire land for the project by purchase and, if necessary, to authorize the use
and acquisition of property by eminent domain.
FORMAT:Resolution
SYNOPSIS INCLUDING PRO & CON: Notice has been given to Prairie Village of Iowa, LLC
(Signature Companies of Iowa) that the City of Waukee, Iowa will consider authorizing the
commencement of a project to reconstruct a portion of University Avenue and associated
infrastructure. The project involves reconstructing University Avenue between 11th Street and the
Waukee Public Works Building, including a new intersection at 10th Street and a connection of 10th
Street to a point approximately 250 feet north of the new intersection. The project includes urban
roadway cross sections with curb and gutter, turn lanes, sidewalks, trails, and related earthwork. Other
improvements include storm sewer, water main, traffic signal and a culvert replacement, along with
two pedestrian underpasses and connecting trails and miscellaneous associated work. The project is to
be known as the University Avenue Area Improvements Phase 1 Project.
Under the provisions of Chapter 6B of the Iowa Code, a governmental body which proposes to acquire
agricultural land under power of eminent domain for a public improvement project is required to give
notice of its intent to commence the project to all owners of such agricultural land whose properties
may be acquired in whole or in part for the project. A notice was mailed to one adjacent property
owner, Prairie Village of Iowa, LLC. The City of Waukee will continue to attempt to purchase the
required land and easements through good faith negotiations, however the City may condemn those
property interests if the City is unable to purchase the necessary property and easements.
FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS:
COMMISSION/BOARD/COMMITTEE COMMENT:
STAFF REVIEW AND COMMENT:
RECOMMENDATION: Approve the resolution.
ATTACHMENTS: I. Resolution
PREPARED BY: Lisa Bauman
REVIEWED BY: Rudy Koester RK
PUBLIC NOTICE INFORMATION –
H4
NAME OF PUBLICATION:
DATE OF PUBLICATION:
1
THE CITY OF WAUKEE, IOWA
RESOLUTION 2024-
RESOLUTION APPROVING AND AUTHORIZING A PUBLIC IMPROVEMENT
PROJECT TO CONSTRUCT THE UNIVERSITY AVENUE AREA IMPROVEMENTS –
PHASE 1 PROJECT, FUNDING OF FINAL SITE-SPECIFIC DESIGN, FINAL
ROUTE/SITE SELECTION, TO ACQUIRE LAND FOR THE PROJECT BY
PURCHASE, AND, IF NECESSARY, TO AUTHORIZE THE USE AND ACQUISITION
OF PROPERTY BY EMINENT DOMAIN
IN THE NAME AND BY THE AUTHORITY OF THE CITY OF WAUKEE, IOWA
WHEREAS, under the provisions of Chapter 6B of the Iowa Code, a governmental body which
proposes to acquire agricultural land under power of eminent domain for a public improvement
project is required to give notice of intent to commence the project to all owners of such
agricultural land whose properties may be acquired in whole or in part for the project (See
Sections 6A.21(a) and 6B.2A of the Iowa Code); and
WHEREAS, under the provisions of 6B.2D of the Iowa Code, the acquiring agency is required
to give notice of a proposed resolution, motion, or other document authorizing acquisition of
property by eminent domain to each property owner, contract purchaser of record and any tenant
known to be occupying the property prior to the date of the meeting at which such proposed
authorization will be considered; and
WHEREAS, on September 16, 2024, the Waukee City Council set the time and place for a
public hearing on October 21, 2024, at 5:30 P.M. at which time persons interested in the
following described project may present their views and objections regarding the commencement
and location of the proposed project, and regarding the proposed acquisition of property interests
for the project by purchase or eminent domain, which project is to be known as the
UNIVERSITY AVENUE AREA IMPROVEMENTS – PHASE 1 PROJECT. This project is
further described as follows:
The project involves reconstructing University Avenue between 11th Street and
the Waukee Public Works Building, including a new intersection at 10th Street and
a connection of 10th Street to a point approximately 250 feet north of the new
intersection. The project includes urban roadway cross sections with curb and
gutter, turn lanes, sidewalks, trails, and related earthwork. Other improvements
include storm sewer, water main, and a culvert replacement, along with two
pedestrian underpasses and connecting trails and miscellaneous associated work.
WHEREAS, due notice of the proposed project was given as provided by law, setting forth the
time and place for hearing on the proposal, funding the final site-specific project, to select the
design and route of the project and to authorize the acquisition of property and property interests
through negotiation, or if necessary, the use of eminent domain; and
2
WHEREAS, the Waukee City Council having held the hearing in accordance with the notice to
receive and consider input regarding the commencement of the proposed public improvement
project, its funding, its location and the acquisition of property interests for this project by
purchase or, if necessary, eminent domain; and
WHEREAS, in accordance with Iowa Law, those interested in this proposed project, both for
and against, have been given an opportunity to be heard with respect thereto and have presented
their views to the Waukee City Council.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
WAUKEE:
1.That all objections and endorsements having been fully reviewed and considered, the
hearing providing the opportunity for public input on the questions of the proposed
public improvement, funding of the final site specific project, select the site and route
of the project and to authorization of the acquisition of property and property interests
by purchase, or if necessary the use of eminent domain for the project is hereby
concluded and closed.
2.That the proposed University Avenue Area Improvements – Phase 1 Project is hereby
approved and the City shall proceed accordingly. Funding for the project and the
final site specific design is hereby authorized. The final location of the route as set
forth in the project map on file with the City Clerk is also approved.
3.That acquisition of private property and all property interests for this project,
including acquisition by eminent domain (condemnation) if necessary, is hereby
authorized.
Passed by the City Council of the City of Waukee, Iowa, and approved this 21st of October,
2024.
____________________________
Courtney Clarke, Mayor
Attest:
___________________________________
Rebecca D. Schuett, City Clerk
RESULTS OF VOTE: AYE NAY ABSENT ABSTAIN
R. Charles Bottenberg
Chris Crone
Rob Grove
Anna Bergman Pierce
Ben Sinclair